Capital Budget Monitoring, Forecast for 2025/2026 Financial Year (As at 31 December 2025)
ApprovedExecutive3 papers
AI summaryBlaenau Gwent Cabinet accepted the capital budget monitoring report, noting a forecast breakeven position against a £43.3 million in-year capital budget for 2025/26, with one overspend of £14,479 on the Flood Alleviation Scheme.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedAccept and challenge financial outcomes, support controls
Money£43.3 million forecast 2025/26 spendAgainst an approximate £72.6 million Capital Programme
What happens nextNot stated
Who it affectsCommunities of Blaenau GwentCapital investment delivery across the borough
What was decided
Cabinet accepted the report and approved Option 1, providing appropriate challenge to the financial outcomes, supporting the financial control procedures agreed by Council, and noting the budgetary control and monitoring procedures in place within the Capital Team to safeguard Authority funding. Report P9
Members noted the overall financial position forecast at 31 December 2025 as a breakeven against the total in-year capital budget of £43.3 million, with a small adverse variance of £14,479 in-year. Report P19, P23
Members noted new funding awards received during the quarter, including awards for EV infrastructure, the Ebbw Sports Centre MUGA upgrade, and the Tredegar Secondary Remodelling scheme. Report P28, P29, P30, P31
Why
The report provides Members with an overview of each Portfolio's actual and forecast capital expenditure against funding approvals for 2025/26, as at 31 December 2025. Report P4
It forms part of the Council's financial reporting framework to members and supports the Corporate Plan by ensuring robust forward financial planning and financial resilience. Report 2.2, P11, 4.1
What happens next
A detailed review of all capital schemes will be undertaken to identify potential underspends and slippage, with the Five Year Strategic Capital Programme to be updated and reported to Council for consideration and approval. Report P27
The £14,479 overspend on the Flood Alleviation Scheme will be financed through Capital Contingencies or by utilising an underspend from another capital project at year end. Report P34
The Executive Leadership Team, Scrutiny Committee and Cabinet will continue to consider the budget monitoring reports on a quarterly basis. Report P62
The money
£72.6 million Total agreed Capital Programme Report P15
£28.3 million Welsh Government Grant funding Report P15
£43,367,000 Total forecast to 31 March 2026 Report P27
£44,514 Energy Service EV and EV Charging Infrastructure award Report P29
£281,500 Ebbw Sports Centre MUGA Upgrade award Report P30
£3,171,722 Band B Secondary Remodelling Tredegar award Report P31
£14,479 Overspend on Flood Alleviation Scheme at Railway Street, Llanhilleth Report P34
Options considered
Chosen: Option 1 (Recommended): Members accept the report, provide appropriate challenge, continue to support financial control procedures, and note Capital Team monitoring procedures. Recommended option to maintain financial oversight and controls Report P8, P9
Rejected: Option 2: Members do not accept the report Report 3.2
Implications
Financial: Forecast breakeven position against the £43.3 million in-year capital budget, with a small in-year adverse variance of £14,479 on the Flood Alleviation Scheme. Report P19, P23, P34
Risk: Risk of losing external funding if capital expenditure is delayed, or of capital reserves being committed beyond affordable levels if schemes exceed budgets, with potential deferral or cancellation of other projects. Report P37, P40
Climate: The Capital Programme supports decarbonisation through Re:Fit energy efficiency upgrades, EV charge point installations, WBRID initiatives, and procurement of Ultra Low Emission Vehicles, with new buildings designed to latest energy efficiency standards. Report 6.8, P58, P59, P60
Who and where
Communities of Blaenau Gwent, as recipients of the Council's capital investment Report P47, P48
Users of Tredegar Comprehensive School, with construction and refurbishment to deliver a net-zero carbon facility Report P31
Users of the Multi-Use Games Area at Ebbw Vale Sports Centre, due for upgrade Report P30
Council fleet operations, with new funding to accelerate the transition to zero-emission vehicles Report P29
Residents near Railway Street, Llanhilleth, where the Replacement Culvert Scheme is being delivered Report P34
Timeline
31 December 2025: Reporting date for actual and forecast capital expenditure Report P4, P19
23 February 2026: Cabinet meeting date for this report Report P2, P3
31 March 2026: End of 2025/26 financial year, target completion of in-year capital spend Report P6, P27
2025: Start of transition to zero-emission cars and light vans under EV funding award Report P29
2026/27: Tredegar Comprehensive School Band B project scheduled to commence Report P31
2030: Target early adoption of zero-emission HGVs ahead of this date Report P29
Quarterly: Budget monitoring reports considered by Executive Leadership Team, Scrutiny Committee and Cabinet Report P62
Plain English for the jargon
MUGA: Multi-Use Games Area
WBRID: Welsh Building Retrofit and Infrastructure Development
ULEV: Ultra Low Emission Vehicle
Band B: Phase of the Welsh Government 21st Century Schools and Colleges programme
EV: Electric Vehicle
HGV: Heavy Goods Vehicle
IIA: Integrated Impact Assessment
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
RESOLVED that the report be accepted and Option 1 be approved, as follows:- a) appropriate challenge to the financial outcomes in the report was provided; b) continued to support appropriate financial control procedures agreed by Council; and c) noted the budgetary control and monitoring procedures in place within the Capital Team, to safeguard Authority funding.
Word for word from the decision Blaenau Gwent published for this meeting.Source: democracy.blaenau-gwent.gov.uk
Cabinet and Council only Date signed off by the Monitoring Officer: 10.02.26 Date signed off by the Section 151 Officer: 10.02.26
Committee: Cabinet Date of meeting: 23 February 2026 Report Subject: Capital Budget Monitoring, Forecast for 2025/2026 Financial Year (As at 31 December 2025) Portfolio Holder: Leader of the Council / Cabinet Member Corporate Resources Report Submitted by: Strategic Director Corporate Services
Reporting Pathway Directorate Corporate Portfolio Governance Democratic Performance Cabinet Council Other Management Leadership Holder / Audit Services & Resources (please Team Team Chair Committee Committee Scrutiny state) 11.02.26 23/02/2026
1. Purpose of the Report 1.1 To provide Members with an overview of each Portfolio’s actual and forecast capital expenditure against funding approvals for the 2025/2026 financial year, as at 31st December 2025.
2. Scope and Background 2.1 This report sets out:
• The forecast financial position across all portfolios to 31st March 2026. • Details of any significant adverse and/or favourable variances against approved funding approvals
2.2This report forms part of the Council’s financial reporting framework to members.
3. Options for Recommendation 3.1 Option 1 (Recommended Option)
Members accept the report and • Provide appropriate challenge to the financial outcomes in the report. • Continue to support appropriate financial control procedures agreed by Council. • To note the budgetary control and monitoring procedures in place within the Capital Team, to safeguard Authority funding.
3.2Option 2 Members do not accept the report.
4. Evidence of how this topic supports the achievement of the Corporate Plan / Statutory Responsibilities / Blaenau Gwent Well-being Plan
4.1This report supports the Council’s Forward-Looking Corporate Plan 2022–2027 by ensuring that robust forward financial planning arrangements are in place to maintain and strengthen the Council’s financial resilience. This is a key enabler in achieving the Council’s vision of being:
“An ambitious and innovative council delivering quality services at the right time and in the right place.”.
5. Implications Against Each Option 5.1 Impact on Budget (short and long term impact)
5.1.1 The agreed Capital Programme totals approximately £72.6 million, funded through the following sources: • Welsh Government Grant: £28.3 million • Other Grant Funding: £5.1 million • Council Resources: £39.2 million
5.1.2 Forecasted Expenditure – 2025/26
5.1.3 It is forecast that £43.3 million will be spent on capital projects during the financial year 2025/26, with the remaining funding profiled to future years in line with approved Strategic Capital programme and scheme timelines.
5.1.4 Financial Position as of 31 December 2025
5.1.5 The overall financial position, as forecast at 31 December 2025, indicates a breakeven position against the total in-year capital budget of £43.3 million.
5.1.6 The overall position across all Portfolios is shown below: -
Total Future In year Forecast Actual Forecast Approvals funding funding Expenditure Expenditure to to Variance Q3 31/12/2025 underspent 31/03/2026 (Month 9) / (Dec (overspent) 2025)
£000 £000 £000 £000 £000 £000
72,592 29,240 43,352 43,367 23,162 (14)
5.1.6.1 Forecast Spend to Quarter 4.
5.1.6.2 Actual Expenditure to Q4 Forecast Spend Total Forecast to 31/12/2025 (Month 9) 31/03/2026
£000 £000 £000
23,162 20,205 43,367 5.1.6.3 The current forecast expenditure, based on the assumption that the full funding approval will be spent during quarter 4 is £20.2m. A detailed review will be undertaken of all capital schemes to identify potential underspends and areas of slippage. Following this review, the 5 Year Strategic Capital Programme will be updated and reported to Council for consideration and approval.
5.1.7 New Funding Awards During the quarter, a number of new / additional funding awards have been received including:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.