Resolved
RESOLVED that the report be accepted and Option 1 be endorsed, namely that the proposals set out within the funding packages that align to the principles, aims and objectives, set out within the draft Blueprint for Growth be approved.
the Council approved this item on Wednesday 25 March 2026. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the report be accepted and Option 1 be endorsed, namely that the proposals set out within the funding packages that align to the principles, aims and objectives, set out within the draft Blueprint for Growth be approved.
1.1The purpose of the report is to update Members on the latest stage of the development of the Blueprint for Growth – the Council’s economic and place-based strategy and outline the latest funding packages recently secured by the Council and how they will be allocated to support the delivery of the key aims set out within the Blueprint for Growth.
2. Blueprint for Growth
2.1The current revised working draft document, Thriving Together – Tech Valleys Growth Corridor, proposes a shared vision for inclusive and sustainable growth across Blaenau Gwent and Torfaen.
2.2It also advocates extension in scope and timescale of the existing Tech Valleys initiative. By 2035 we will have created a more prosperous Blaenau Gwent and Torfaen for the benefit of all our communities, businesses and places.
2.3This will be achieved through focussed action around three key themes:
• Infrastructure and Investment • Business and Employment Growth • People and Skills
2.4These proposed themes align more closely with the new Local Growth Fund and Cardiff Capital Region priorities. Action to deliver against these themes will be set out in more detail via a set of joint workstreams. 2.5 Underpinning the shared vision and key themes within the blueprint is the development of a “place framework”, which seeks to bring the blueprint strategic approach to life, through the provision of a local level spatial illustration.
2.6Placemaking plans across the area will include layered maps that show spatially:
• Existing investment areas • Strategic employment, housing, leisure, education sites, etc. • Detailed masterplans for strategic sites. • Town centre revitalisation plans • Transport connectivity
2.7Placemaking plans will be centred around our eco-system of town centres but will also consider how the wider community area is serviced by that town centre and how it will also benefit.
2.8It is recognised that our reliance upon mainly UK and WG government grant funding will not make the economic or place-based impact we require to improve our economic, environmental and social conditions and performance. We intend to secure significant private sector interest and financial support, through the development of “investment ready” business cases to support our project proposals.
2.9Following Cabinet approval, the procurement of a development partner will take place through the summer months, to secure sufficient commercial investment capacity and capability. Whilst it is important to plan our long-term strategic approach, we also need to ensure we gain traction through project mobilisation. The delivery programme for year 1 will therefore focus upon the following areas – Transport connectivity – undertaking an analysis of future transport user demand and working with WG to maximise bus connectivity across the county borough areas, linking to strategic rail hubs and town centres.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Delivering the Blueprint for Growth with External Funding (Local Growth Fund: Pride In Place Neighbourhood Fund: Pride in Place Impact Fund)Report | 204 KB | DownloadRead as text |
Follow the Council at Blaenau Gwent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Jul 2026 | Objection Report on the Proposal to Decrease the Capacity at Abertillery Learning Community Primary PhaseRESOLVED, subject to the foregoing, that the report be accepted and Option 1 be endorsed, namely that the Objections ... | Decided | Open |
| 15 Jul 2026 | Decision Book - November 2025 - June 2026RESOLVED, subject to the foregoing, that the decisions be approved and confirmed as a true record of proceedings. | Approved | Open |
| 15 Jul 2026 | Ordinary Meeting of the CouncilRESOLVED, subject to the foregoing, that the decisions be approved. | Approved | Open |
| 15 Jul 2026 | Proposed Council Forward Work Programme 2026-2027RESOLVED that the report be accepted and Option 1 be endorsed, namely that the Proposed Forward Work Programme for Co... | Agreed | Open |
| 15 Jul 2026 | Annual Scrutiny Report 2025-2026RESOLVED that the report be accepted and - the ‘scrutiny activity’ that had been undertaken by each Scrutiny Committe... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.