Contract Award Surveying Repair and Replacement External Doors and Windows

Approved Executive 1 paper

AI summaryBolsover District Council Executive approved a 4 year contract with Swinstead Enterprises Ltd (Trading as Evendine Utilities) for surveying, repair and replacement of external doors and windows. [D] The total value is £240,000. [2.2]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedContract with Swinstead Enterprises Ltd (Trading as Evendine Utilities). [D]
Money£240,000 contract value [2.2]Existing budgets have sufficient funds for the contractual amount. [P16]
What happens nextJCT contract formalisation [3.1]The arrangement began on 5th January 2026. [2.2]
Who it affectsExternal doors and windows [D]Surveying, repair and replacement are included. [D]

What was decided

The Executive approved a 4 year contract with Swinstead Enterprises Ltd (Trading as Evendine Utilities) for surveying, repair and replacement of external doors and windows.

The contract is to be in Bolsover District Council's name. Report 2.3

The award was also approved by the Portfolio Holder for Housing. Report P14

Why

The Council's procurement team was satisfied that a legally compliant procurement exercise had been followed. The legal team drafted the JCT contract. Report 2.3

The successful bidder was also the incumbent contractor and was already operating under the new arrangement. Report 2.2

The award formed part of the transition of the Dragonfly companies coming back in house. Report 2.1

What happens next

The Council will formalise the arrangement with the successful bidder through a JCT contract. Report 3.1

The contract term is 4 years, based on 2 years plus 1, plus 1 year extension. Report 2.2

The money

  • £240,000 Total value of the 4 year contract Report 2.2
  • £75,000 or more Revenue savings or expenditure threshold for a key decision Report P24
  • £150,000 or more Capital income or expenditure threshold for a key decision Report P25

Options considered

  • Chosen: Award the contract to Swinstead Enterprises Ltd (Trading as Evendine Utilities). The procurement exercise selected it as the best supplier, and it was also the incumbent contractor. Report 2.2, 4.1
  • Rejected: Alternative options. The report records no alternative options. Report 4.1

Implications

  • Financial: There are sufficient funds within existing budgets to meet the contractual amount. Report P16
  • Legal: The contract is to be in Bolsover District Council's name. The procurement team was satisfied that a legally compliant procurement exercise had been followed, and the legal team drafted the JCT contract. Report 2.3
  • Staffing: There are no direct staffing implications from this report. Report P17
  • Equalities: The implications section records no equality and diversity, and consultation implications. Report P18
  • Climate: The implications section records no environmental implications. Report P20
  • Other: The decision is marked as a key decision and is subject to call in. Report P23, P26
  • Other: Consultation was carried out before the report was presented for approval. Report P28
  • Other: The decision links to the Council ambitions for customers, economy, environment and housing. Report P30

Who and where

  • Bolsover District Council Report 2.3
  • Swinstead Enterprises Ltd (Trading as Evendine Utilities) Report 2.1
  • Capital Projects Team Report 1.2
  • Property Services Report 1.2
  • Dragonfly Management (Bolsover) Ltd Report 1.2, 2.1

Timeline

  • 22nd April 2025: The Capital Projects Team and Council procurement team commenced a tender exercise. Report 1.2
  • July 2025: The existing contract for replacement and repair of doors came to an end. Report 1.1
  • Tender exercise reissued: This delayed the identification of a preferred bidder. Report 1.3
  • 5th January 2026: The successful bidder began operating under the new contract arrangement. Report 2.2, 3.1

Plain English for the jargon

  • JCT contract: The contract that the legal team drafted to formalise the arrangement with the successful bidder. [2.3] [3.1]
  • Key decision: An Executive decision with significant impact on two or more wards, or income or expenditure above stated thresholds. [P23]
  • Call in: Only key decisions are subject to call in. [P26]
  • Dragonfly: The companies coming back in house, including Dragonfly Management (Bolsover) Ltd. [1.2] [2.1]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

RESOLVED that the contract for 4 years to Swinstead Enterprises Ltd (Trading as Evendine Utilities) for the provision of Surveying, Repair and Replacement, External Doors and Windows, be approved.
Word for word from the decision Bolsover published for this meeting. Source: committees.bolsover.gov.uk

Follow this further

Built from Bolsover's papers

What the report saysPro

Report to Executive, 4 pages

Background

1.1The existing contract for the replacement and repair of doors, came to an end in July 2025.

1.2The Capital Projects Team operating as part of Property Services, Dragonfly Management (Bolsover) Ltd, working with the Council’s procurement team commenced a re-tender exercise on 22nd April 2025.

1.3Unfortunately the tender exercise had to be reissued which led to a delay in identifying a preferred bidder.

2. Details of Proposal or Information

2.1This report seeks approval to grant the surveying, repair and replacement external doors and windows contract to Swinstead Enterprises Ltd (Trading as Evendine Utilities). This has arisen as part of the transition of the Dragonfly companies coming back in house.

2.2The successful bidder, also the incumbent contractor, has been operating under a new contract arrangement since 5th January 2026. The contract is a 4 year contract based on 2 years plus 1, plus 1 year extension, with a total value of £240,000.

2.3Procurement of the contract commenced under Dragonfly, however at the point the contract award was made, a decision had been made for Dragonfly to return in house, and it was agreed with the successful bidder that the contract would be in Bolsover District Councils name. 2.4 The Council’s Procurement Team have been involved throughout and are satisfied a legal compliant procurement exercise has been followed. In addition, the Legal Team have been involved including drafting the JCT contract.

Reasons for recommendation

3.1Swinstead Enterprises Ltd (Trading as Evendine Utilities) were identified as the successful bidder through a legal complaint procurement exercise. They have been operating under contract terms and conditions since 5th January 2026 and we need to formalise the arrangements by way of a JCT contract.

4 Alternative Options and Reasons for Rejection

4.1None, as Swinstead Enterprises Ltd (Trading as Evendine Utilities.) were identified as the best supplier through an agreed procurement exercise.

________________________________________________________________

RECOMMENDATION(S)

1. Executive approves the contract for 4 years to Swinstead Enterprises Ltd (Trading as Evendine Utilities) for the provision of Surveying, Repair and Replacement, External Doors and Windows.

Approved by Portfolio Holder for Housing

IMPLICATIONS:

Finance and Risk Yes☐ No ☒ Details: There are sufficient funds within existing budgets to meet the contractual amount On behalf of the Section 151 Officer

Legal (including Data Protection) Yes☐ No ☐ Details: Swinstead Enterprises Ltd (Trading as Evendine Utilities) were identified as the best supplier through a procurement exercise. On behalf of the Solicitor to the Council Staffing Yes☐ No ☒ Details: There are no staffing implications rising directly from this report. On behalf of the Head of Paid Service

Equality and Diversity, and Consultation Yes☐ No ☒

Details:

Environment Yes☐ No ☒ Please identify (if applicable) how this proposal/report will help the Authority meet its carbon neutral target or enhance the environment. Details:

DECISION INFORMATION:

☒ Please indicate which threshold applies:

Is the decision a Key Decision? Yes☒ No ☐ A Key Decision is an Executive decision which has a significant impact on two or more wards in the District or which results in income or expenditure to the Council above the following thresholds:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Contract Award Surveying Repair and Replacement External Doors and WindowsReport 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Bolsover

Search all
  1. Contract Award Surveying Repair and Replacement External Doors and WindowsThis decision
  2. Contract Award Homelessness Out of HoursApproved
  3. Contract Award - Replacement of Bathrooms 2026-2031Approved
  4. Contract Award - Repair of Concrete Lintel Features at various Council residential propertiesApproved
  5. Contract Award for the delivery of an Options Appraisal for Pleasley Vale Business ParkNoted
  6. Contract Award to enable the Bolsover Partnership to administer their 'Children and Young People' ProjectDecided

More from Bolsover Executive

All decisions
MeetingDecisionOutcome
27 Jul 2026 Compliments, Comments and Complaints (CCC) Policy Housing Ombudsman ReviewRESOLVED that the CCC Policy changes following recommendations by the Housing Ombudsman, and the Customer Services Sc... Approved Open
27 Jul 2026 Anti-Fraud, Bribery, and Corruption PolicyRESOLVED that the be approved. Approved Open
27 Jul 2026 Anti-Money Laundering PolicyRESOLVED that the be approved. Approved Open
27 Jul 2026 Biodiversity Net Gain Receptor Site ProjectRESOLVED that the option of entering the BNG receptor site market using the limited land currently allocated for envi... Decided Open
27 Jul 2026 Review of the Creation of Climate Resilience Plan and ConsultationRESOLVED that 1) the work undertaken by the Climate Resilience Group to date, to develop the DRAFT Climate Resilience... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies