Briar Close, Shirebrook and High Street, Tibshelf - Pre Construction Funding Arrangements

Approved Executive 1 paper

AI summaryBolsover District Council's Executive approved reducing Dragonfly Development Ltd's dividend by £488,500 to fund preconstruction work at Briar Close, Shirebrook and High Street, Tibshelf, with further reports to follow [D] [P21].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFurther reports will go to Executive and Council [P21]
Money£488,500 [D]Preconstruction costs for both sites, excluding VAT [2.4]
What happens nextFurther pipeline reports required [P21]After detailed scheme viability is established [P21]
Who it affectsTwo proposed housing sites [1.4]Briar Close, Shirebrook and High Street, Tibshelf [1.4]

What was decided

The Executive approved reducing the dividend due from Dragonfly Development Ltd for the 2024\25 financial year by £488,500 [D].

The reduced dividend will allow preconstruction work at Briar Close, Shirebrook and High Street, Tibshelf to be undertaken and paid for [D].

Further reports will be submitted to Executive and Council for the Bolsover Homes funding pipeline after detailed viability is established [P21]. Report P21

Why

Viability must be established before the schemes can be considered for delivery through the Bolsover Homes funding pipeline and submitted for approval [2.1]. Report 2.1

Dragonfly Development Ltd realised a profit after tax of £1,898,495 in 2024\25. The Council could receive this as a dividend because it is the 100% shareholder of the Dragonfly group of companies, and the Projects and Construction Team's estimates show the schemes are viable if Homes England funding is obtained [1.1] [2.2]. Report 1.1, 2.2

The two sites have potential for approximately 30+ units, and preconstruction work needs to start as soon as possible to give the Council's Construction team the best chance of achieving 200 new homes by 2028 [1.4] [3.1]. Report 1.4, 3.1

What happens next

Undertake preconstruction work to confirm the scheme mix and viability, then submit further reports to Executive and Council once detailed viability is established [1.4] [P21]. Report 1.4, P21

Stop work at any RIBA stage if a scheme is found not viable, with no further costs incurred [2.5]. Report 2.5

After planning permission is granted, proceed towards starting on site, use the approved designs for a more detailed cost estimate and confirm Homes England funding [2.6]. Report 2.6

The money

  • £488,500 Dividend reduction approved to fund preconstruction work for both schemes [D] [2.4] Report 2.4
  • £ 338,500 Briar Close total budget, including provisional amounts [P9] Report P9
  • £ 150,000 High Street, Tibshelf total budget, including provisional amounts [P11] Report P11
  • £1,898,495 Dragonfly Development Ltd's 2024\25 profit after tax, which could be returned as a dividend [1.1] Report 1.1
  • £36.2million Potential Bolsover Homes funding stream for both sites, subject to viability [P24] Report P24

Options considered

  • Chosen: Use Dragonfly Development Ltd's 2024\25 profit to fund preconstruction work by reducing the dividend [D] [2.7]. This allows viability to be tested, with work able to stop at any stage if a scheme is not viable [2.1] [2.5] Report 2.1, 2.5, 2.7
  • Rejected: Do not consider the preconstruction schemes for the Bolsover Homes pipeline [4.1]. This would mean much needed housing would not be developed and would undermine the plan to increase affordable social housing units by 200 during The Future 2024 to 2028 [4.1] Report 4.1

Implications

  • Financial: The lower dividend enables Dragonfly Development Ltd to fund the necessary preconstruction work from profit instead [P24]. Report P24
  • Financial: Subject to viability, both sites could enter the £36.2million Bolsover Homes funding stream, but moving both forward would need additional approval unless more external funding is received [P24]. Report P24
  • Risk: Work can stop at any RIBA stage if a scheme is found not viable, with no further costs incurred [2.5]. Report 2.5
  • Legal: The Shareholder Agreement allows the Council to agree how Dragonfly's profit is distributed as a dividend [P26]. Report P26
  • Staffing: No staffing implications arise from the report [P27]. Report P27
  • Equalities: No equality and diversity impact or consultation arises from this report [P28]. Report P28
  • Environment: Scheme design and development will meet necessary environmental requirements, including building energy efficiency standards and Biodiversity Net Gain [P29]. Report P29
  • Other: The decision is a key decision and is subject to call in. Consultation covered Executive, Members and Other, but not the public [P31] [P34]. Report P31, P34

Who and where

  • People needing affordable social housing Report 1.2, 4.1
  • Briar Close, Shirebrook Report 1.4
  • High Street, Tibshelf Report 1.4
  • Bolsover District Council Report P24
  • Dragonfly Development Ltd Report 2.7
  • Homes England Report 2.2, 2.6
  • Bolsover District Council's Projects and Construction Team Report 2.2
  • Bolsover District Council's Construction team Report 3.1

Timeline

  • 2024\25 financial year: Dragonfly Development Ltd realised a profit after tax, and the Council approved a related dividend reduction [1.1] [D]. Report 1.1
  • Before these schemes can be further considered: Scheme viability must be undertaken before submission for approval [2.1]. Report 2.1
  • As soon as possible: Start preconstruction work so the Construction team has the best chance of achieving 200 new homes by 2028 [3.1]. Report 3.1
  • At any of the above stages: Stop work if a scheme is found not viable, with no further costs incurred [2.5]. Report 2.5
  • Following the granting of planning permission: Proceed towards starting on site, obtain a more detailed cost estimate and confirm Homes England funding [2.6]. Report 2.6
  • After detailed viability is established: Submit further reports to Executive and Council for the Bolsover Homes funding pipeline [P21]. Report P21
  • 2024 to 2028: Strategic plan period for increasing affordable social housing stock by 200 units [1.2]. Report 1.2

Plain English for the jargon

  • Bolsover Homes funding pipeline: The route for assessing and delivering potential affordable housing development sites [1.2] [1.3] [2.1]
  • Preconstruction work: Design and investigatory work needed to confirm scheme mix and viability [1.4]
  • RIBA stages: The numbered stages used in the preconstruction cost breakdown [2.4]
  • Biodiversity Net Gain: A stated environmental requirement for scheme design and development [P29]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

RESOLVED that 1) the reduction in the dividend receivable from Dragonfly Development Ltd for the 2024\25 financial year in the amount of £488,500 to allow pre-construction works at Briar Close, Shirebrook & High Street, Tibshelf, to be undertaken and paid for, be approved, 2) further reports be submitted to Executive and Council for Bolsover Homes funding pipeline, following detailed viability of the scheme being established.
Word for word from the decision Bolsover published for this meeting. Source: committees.bolsover.gov.uk

Follow this further

Built from Bolsover's papers

What the report saysPro

Report to Executive, 5 pages

Background

1.1Dragonfly Development Ltd (DDL) during the 2024\25 financial year, realised a profit after tax of £1,898,495. This could be returned to the Council as a dividend as 100% shareholder of the Dragonfly group of companies.

1.2DDL was one of the Council’s strategic vehicles in delivery of its Bolsover Homes pipeline ambitions by way of increasing its affordable social housing stock by 200 units within the Council’s current strategic plan, (The Future) 2024 to 2028.

1.3The Council, in consultation with Dragonfly, had previously reviewed its schedule of potential development sites concluding that smaller sites limiting development potential to 3 units, are not viable. Therefore, other sites included in the original Bolsover Homes pipeline have been considered.

1.4Two of these sites are Briar Close, Shirebrook & High Street, Tibshelf, which have potential to develop approximately 30+ units. However, pre-construction work (i.e. design\investigatory) is necessary to confirm scheme mix and viability.

2. Details of Proposal or Information

2.1Before these schemes can be further considered for delivery through the Bolsover Homes funding pipeline and submitted to Members for approval, viability of the schemes needs to be undertaken.

2.2Bolsover District Council’s newly formed Projects and Construction Team have provided high level cost estimates for these two schemes, and have shown that these schemes are viable, provided that funding can be obtained from Homes England. 2.3 Following this analysis, should the Council wish to proceed with the sites the next stage would be to commence pre-construction works so that planning permission can be obtained.

2.4The costs for pre-construction services for these two schemes at £488,500 excluding VAT is summarised as follows: Briar Close, Shirebrook. Pre-construction Costs Stage Cost RIBA Stage 2 Pre-Construction Services £ 11,750 RIBA Stage 3 Pre-Construction Services £ 27,530 RIBA Stage 4 & 5 Pre-Construction Services £ 111,210 Additional Provisional allowances to cover design costs as £ 188,010 RIBA stages are progressed

Total Budget to be allocated for Briar Close (including £ 338,500 provisional amounts)

High Street, Tibshelf. Pre-construction Costs Stage Cost RIBA Stage 2 Pre-Construction Services £ 8,050 RIBA Stage 3 Pre-Construction Services £ 15,100 RIBA Stage 4 & 5 Pre-Construction Services £ 41,900 Additional Provisional allowances to cover design costs as £ 84,950 RIBA stages are progressed

Total Budget to be allocated for High Street (including £ 150,000 provisional amounts)

2.5Should any scheme be identified as non-viable at any of the above stages, pre- construction work can be stopped at any RIBA stage with no further costs incurred.

2.6Following the granting of planning permission the Council can proceed towards starting on site using the approved designs to provide a more detailed estimate of costs and allowing confirmation of funding available from Homes England.

2.7It is proposed that the DDL profit from 2024/25 is used to fund pre-construction works for development at the above schemes, which would result in any dividend returned to the Council being lowered.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Briar Close, Shirebrook and High Street, Tibshelf: Pre Construction Funding ArrangementsReport 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Bolsover

Search all
  1. Briar Close, Shirebrook and High Street, Tibshelf - Pre Construction Funding ArrangementsThis decision
  2. Briar Close, Shirebrook - demolition of Council owned bungalowsDecided

More from Bolsover Executive

All decisions
MeetingDecisionOutcome
27 Jul 2026 Compliments, Comments and Complaints (CCC) Policy Housing Ombudsman ReviewRESOLVED that the CCC Policy changes following recommendations by the Housing Ombudsman, and the Customer Services Sc... Approved Open
27 Jul 2026 Anti-Fraud, Bribery, and Corruption PolicyRESOLVED that the be approved. Approved Open
27 Jul 2026 Anti-Money Laundering PolicyRESOLVED that the be approved. Approved Open
27 Jul 2026 Biodiversity Net Gain Receptor Site ProjectRESOLVED that the option of entering the BNG receptor site market using the limited land currently allocated for envi... Decided Open
27 Jul 2026 Review of the Creation of Climate Resilience Plan and ConsultationRESOLVED that 1) the work undertaken by the Climate Resilience Group to date, to develop the DRAFT Climate Resilience... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies