RESOLVED that Cabinet (a) Notes that progress in bringing the site (indicatively edged red on the plan attached at appendix 1 of Report 6) forward has stalled and supports an alternative approach which seeks to explore options for bringing this key brownfield site into public ownership. (b) Allocates a sum of £150,000 from Homes England capacity funding to develop a site acquisition strategy with specialist estates and legal advice. (c) Notes that the acquisition strategy will be presented to Council and that members will then be presented with the full business case for site acquisition including the use of Compulsory Purchase Order (CPO) powers as a contingency. Voting: Unanimous To facilitate this key brownfield site to progress to deliver much needed housing and a new community in Poole, and seek to retain the external funding allocated for the site to address the significant adverse infrastructure costs.
Word for word from the decision Bournemouth, Christchurch and Poole published for this meeting.Source: democracy.bcpcouncil.gov.uk
Follow this further
Built from Bournemouth, Christchurch and Poole's papers
Holes Bay, Poole (former power station site) acquisition Report subject strategy Meeting date 12 July 2019
Status Public To inform the Cabinet that the current private-sector led Executive summary development for the former power station site has stalled and recommend the Council pursue an alternative approach which could enable the acquisition of the site with support from Homes England and the Dorset Local Enterprise Partnership (DLEP). Recommendations It is RECOMMENDED that Cabinet: (a) Notes that progress in bringing the site (indicatively edged red on the plan attached at appendix 1) forward has stalled and supports an alternative approach which seeks to explore options for bringing this key brownfield site into public ownership. (b) Allocates a sum of £150,000 from Homes England capacity funding to develop a site acquisition strategy with specialist estates and legal advice. (c) Notes that the acquisition strategy will be presented to Council and that members will then be presented with the full business case for site acquisition including the use of Compulsory Purchase Order (CPO) powers as a contingency.
Reason for To facilitate this key brownfield site to progress to deliver recommendations much needed housing and a new community in Poole, and seek to retain the external funding allocated for the site to address the significant adverse infrastructure costs. Portfolio Holder(s): Councillor Kieron Wilson, Portfolio Holder for Housing
Corporate Director Kate Ryan (Corporate Director of Environment and Community)
Contributors Lorraine Mealings, Director of Housing Julian McLaughlin, Director of Growth and Infrastructure Sarah Varley, Head of Estates
Wards Hamworthy
Classification For Decision Title:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Learning Disability Big Plan 2026–2031RESOLVED that Cabinet approved the Learning Disability Big Plan for future publication and delivery against the prior...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.