Cabinet, Friday 12 July 2019 at 10.00am

Bournemouth International Centre (BIC) investment strategy

Approved Executive 1 paper

Cabinet approved this item on Friday 12 July 2019. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

RESOLVED that (a) Cabinet approves £170,000 funding for a feasibility study to reimagine the BIC for the next 30+ years (b) Cabinet formally agrees to the discontinuance of the procurement process authorised by the Cabinet of Bournemouth Borough Council in October 2018 relating to the hotel adjacent to the BIC. (c) Cabinet confirms its commitment to ongoing investment in the BIC in order for it to remain competitive and requests officers to make specific investment recommendations at a future Cabinet meeting. Voting: Unanimous These are in line with the strategic priorities of the Cabinet.
Word for word from the decision Bournemouth, Christchurch and Poole published for this meeting. Source: democracy.bcpcouncil.gov.uk

Follow this further

Built from Bournemouth, Christchurch and Poole's papers

What the report saysPro

Report to Cabinet

10 CABINET

Report subject Bournemouth International Centre (BIC) investment strategy

Meeting date 12 July 2019

Status Public Report

Executive summary The purpose of this report is to 1. To seek funding approval of £170,000 for a feasibility study to reimagine the BIC for the next 30+ years 2. Provide an update regarding the hotel project relating to the site adjacent to the Bournemouth International Centre (BIC) 3. To seek commitment for the continued reinvestment of a proportion of the annual service fee, payable by BH Live, for the short to medium term refurbishment priorities for the Bournemouth International Centre (BIC), under any scenario.

Recommendations It is RECOMMENDED that:

(a) Cabinet approves £170,000 funding for a feasibility study to reimagine the BIC for the next 30+ years. (b) Cabinet formally agrees to the discontinuance of the procurement process authorised by the Cabinet of Bournemouth Borough Council in October 2018 relating to the hotel adjacent to the BIC. (c) Cabinet confirms its commitment to ongoing investment in the BIC in order for it to remain competitive and requests officers to make specific investment recommendations at a future Cabinet meeting.

Reason for These are in line with the strategic priorities of the Cabinet recommendations Portfolio Holder(s): Portfolio Holder Tourism, Leisure & Communities, Councillor Lewis Allison Portfolio Holder Regeneration and Culture, Councillor Mark Howell

Corporate Director Bill Cotton – Corporate Director Regeneration and Economy

Contributors Chris Shephard – Director Development Beccy Brookwell – Head of Construction & FM Martin Tiffin – Town Centre Vision Programme Leader

Wards Bournemouth Central

Classification For Decision Title:

Background 1. This report is covering three linked topics:  A feasibility study to reimagine the BIC for the next 30+ years  The hotel project relating to the site adjacent to the Bournemouth International Centre (BIC)  Short to medium term investment priorities for the BIC, under any scenario

BIC reimagining feasibility for the next 30+ years 2. The BIC and the hotel site are adjacent, as can be seen in the plan below. Figure 1: 3. The BIC was originally constructed in 1985 as a mixed-use leisure and conference/events facility and is now 35 years old. When it was delivered it was regarded as the premier conference and events facility in the UK and was stated to have contributed £125 million annually to the local economy. Over the past 20 years the building has been added to and the internal space has been reconfigured to compete in the market, as new more bespoke and up to date conference and entertainment venues have been built in a number of the major cities in the UK. The conference and entertainment market is now a more international market than when the BIC was built and it is not only necessary to compete with UK venues but also others in mainland Europe. The current facility is no longer regarded as the premier destination it once was. 4. Taking into account the age of the BIC, and the opportunity to cease the procurement process for the hotel development, now appears to be an appropriate time to consider the wider options for replacing or refurbishing the BIC for the next 30+ years. 5. Should Cabinet decide to look at possible reimagining/ redevelopment options, these could range from; Option A Refurbish as set out in more detail at 2c below Option B Refurbish & Extension Option C Refurbish & Major Extension, possibly containing a hotel Option D New Build on Current Site Option E New Build on New Site

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Bournemouth International Centre (BIC) investment strategyReport 347 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 27 attended
P
Presentthe member of the committee was present as expected at the meeting
A
Apologiesthe member of the committee was unable to attend and reported their apologies in advance (substitute
A
Absentthe member of the committee was not present and did not apologise for their absence
IA
In attendancea councillor, who was not a member of the committee, was also in attendance
VS
Councillor Vikki SladeChairman, present
MH
Councillor Mark HowellVice-Chairman, present
LA
Councillor Lewis AllisonCommittee Member, present
DB
Councillor David BrownCommittee Member, present
LD
Councillor Lesley DedmanCommittee Member, present
AH
Councillor Andy HadleyCommittee Member, present
SM
Councillor Sandra MooreCommittee Member, present
MP
Councillor Margaret PhippsCommittee Member, present

All 27 on the meeting page

On this subject at Bournemouth, Christchurch and Poole

Search all
  1. Bournemouth International Centre (BIC) investment strategyThis decision
  2. The Bournemouth International CentreDecided
  3. Site A1, Enterprise way, Aviation Business Park West, Bournemouth International AirportApproved

More from Bournemouth, Christchurch and Poole Cabinet

All decisions
MeetingDecisionOutcome
2 Sep 2026 2026/27 Council Budget monitoring at Quarter 1RESOLVED that Cabinet: - (a) noted the Quarter 1 position for 2026/27, actions taken by the Section 151 Officer to da... Noted Open
2 Sep 2026 Learning Disability Big Plan 2026–2031RESOLVED that Cabinet approved the Learning Disability Big Plan for future publication and delivery against the prior... Approved Open
2 Sep 2026 IT & Programmes Infrastructure Capital Investment Plan 2026–2032RESOLVED that Cabinet: - (a) approved delegated procurement authority to Director of IT & Programmes; (b) recommend t... Approved Open
2 Sep 2026 BCP Homes Performance and Regulatory Compliance UpdateRESOLVED that Cabinet noted the content of the report and raised any issues for consideration by officers. Voting: Un... Noted Open
22 Jul 2026 Recommendations from the Overview and Scrutiny CommitteesDecision) The Leader thanked Councillor Canavan and the Committee for bringing their recommendation to Cabinet and ex... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies