RESOLVED that Planning Permission be GRANTED in accordance with the recommendation as set out in the report and further updated by the addendum sheet and with the content of Condition 8 amended to reflect the Committee’s wish to ensure that the roots of the oak tree at the front of the site (T11) are fully protected during construction. Voting: For – 8, Against – 4, Abstain – 1 Notes: An earlier move to refuse permission was not carried, the voting being: For – 5, 8 – Against, Abstain – 0. Cllr P Hall asked that his vote against the move to grant permission be recorded in the minutes. Cllr G Farquhar asked that his vote in favour of the move to refuse permission be recorded in the minutes
Word for word from the decision Bournemouth, Christchurch and Poole published for this meeting.Source: democracy.bcpcouncil.gov.uk
Follow this further
Built from Bournemouth, Christchurch and Poole's papers
Summary of Key Issues 1. The key planning issues for Members to consider are set out below. Members will have to balance all of the planning issues and objectives when making a decision on the application, against policy and other material considerations.
Representations received 2. 67 representations have been received. A summary of the 55 objections, 1 comment and 21 support letters have been provided within the consultation section of the report.
Principle of development 3. The site is within a residential locality in the urban envelope where new residential development is permitted under policy KS2. The net increase of dwelling would make a contribution to the five year housing supply, which is currently standing at 3.98 years.
Affordable Housing and Housing mix 4. The Viability Assessment indicates there is no viability for affordable housing and this has been robustly reviewed by consultants acting on behalf of the Council. This is discussed within the main body of the report. The Strategic Housing Assessment (SHMA 2015) states that 2 and 3 bedroom houses are what is mostly required in the Christchurch area. The provision of mainly 2 bed flats is not considered to technically meet this need. However, given the current housing land supply issues, the provision of 13 relatively spacious two bed units with parking is considered to be acceptable.
Design, Layout and form 5. The scale and footprint of the building is considered appropriate for the size of the plot and the scale of properties along Chewton Farm Road. The appearance of the building is also appropriate for this sylvan setting. The development is not considered to be contrary to policy H9 and complies with policies H12 and HE2.
Residential Amenity 6. The scheme does bring built form closer to the side and rear boundaries and the building will be more prominent than the existing property. However, the proposal is considered to comply with the test in Policy HE2 to be compatible in its relationship to nearby properties including minimising general disturbance to amenity and be in accordance with policy H12 by ensuring the residential amenities of existing and future occupiers of dwellings are not adversely affected by noise or disturbance or by loss of light.
Parking and Access
7. The BCP Parking Standards SPD states that one vehicle parking space is required per unit for 1 and 2 bed flats. There are 17 spaces shown in the basement and 3 visitor surface parking spaces at the front of the site. This level of provision is considered to be acceptable on this site and in this locality. The basement parking, with some additional details secured by condition is considered to be acceptable to BCP Highways and the traffic movements associated with the development and the adjacent development are not considered to result in significant or severe impacts on the local highway network and as such would not be contrary to the NPPF. It is considered the scheme is compliant with the Parking SPD and policies KS11 and KS12 of the Local Plan.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning Committee at Bournemouth, Christchurch and Poole and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.