2 Riversmeet Leisure Centre: Energy Improvements Business Case

Approved Executive 3 papers

Cabinet approved this item on Wednesday 8 March 2023. Below is the council's own wording, with the papers it was decided on.

Item143

Resolved

RESOLVED that the application to the Green Futures Fund (as previously approved by the Future Infrastructure Board) for replacement of plant, installation of controls, energy monitoring system and replacement of pool covers at 2Riversmeet Leisure Centre for the sum of £478,500, be approved . Voting: Unanimous Portfolio Holder: Communities, Health and Leisure Recent plant failures due to age and poor condition have jeopardised the operational capacity of the building to heat the areas of the centre and both pools. Further plant failures will potentially lead to the centre being unable to operate and loss of revenue. Replacing existing plant with modern, more efficient plant will also save money in running costs and reduce the amount of greenhouse gas emissions contributing to climate change. Furthermore, new plant provides the opportunity for more long-term low carbon solutions to be added in future, such as heat pumps, which the existing plant does not.
Word for word from the decision Bournemouth, Christchurch and Poole published for this meeting. Source: democracy.bcpcouncil.gov.uk

Follow this further

Built from Bournemouth, Christchurch and Poole's papers

What the report saysPro

Report to Cabinet

CABINET

Report subject 2Riversmeet Leisure Centre: Energy Improvements Business Case

Meeting date 8 March 2023

Status Public Report

Executive summary This application to the Green Futures Fund (as previously approved by the Future Infrastructure Board on 2 December 2022) is for replacement of plant, installation of controls, energy monitoring system and replacement of pool covers at 2Riversmeet Leisure Centre. These urgent works will ensure the ongoing operation of a valued corporate and community asset, whilst achieving reduced energy consumption and therefore reduced carbon emissions in line with the commitment of this Council under the Climate and Ecological Emergency declaration (2019). The funds being sought for the project are £478,500 and the energy savings per annum are estimated at £63,000.

Recommendations It is RECOMMENDED that:

The application to the Green Futures Fund (as previously approved by the Future Infrastructure Board) for replacement of plant, installation of controls, energy monitoring system and replacement of pool covers at 2Riversmeet Leisure Centre for the sum of £478,500, be approved.

Reason for Recent plant failures due to age and poor condition have recommendations jeopardised the operational capacity of the building to heat the areas of the centre and both pools. Further plant failures will potentially lead to the centre being unable to operate and loss of revenue. Replacing existing plant with modern, more efficient plant will also save money in running costs and reduce the amount of greenhouse gas emissions contributing to climate change. Furthermore, new plant provides the opportunity for more long-term low carbon solutions to be added in future, such as heat pumps, which the existing plant does not.

1 $Fhxkxwea Portfolio Holder(s): Councillor Jane Kelly - Portfolio Holder for Communities, Health and Leisure

Corporate Director Jess Gibbons – Chief Operating Officer

Report Authors Dan Stone - Leisure Commissioning Manager, Simon Percival - Asset Investment Manager, Neil Short – Sustainability Manager

Wards Christchurch Town;

Classification For Decision Ti t l e:

Background 1. For full details please see Appendix A: Business Case for Plant Refurbishment and energy savings measures at Two Riversmeet Leisure Centre (2RMLC) Ref: BCPDR-Asset0002, as previously approved by the Future Infrastructure Board on 2 December 2022.

Options Appraisal Option 1: (Recommended) Full plantroom upgrade and connection of energy centre, providing reduced energy costs, complete control of plant to match operational need at a cost of £478,500. Option 2: (Not Recommended) Connection of energy centre only - a temporary option - will not give any control of the systems and high utility costs will continue. Cost: £38,500. Option 3: (Not Recommended) Do nothing and run the risk that further plant failure will compromise the operation of the centre, leading to complete closure.

Summary of financial implications 2. A total of £478,500 is requested, which will impact the MTFP with borrowing costs of £56,000 per annum over 15 years. However, the estimated annual energy savings resulting from the project are £63,000 or greater if energy costs rise further.

Summary of legal implications 3. The Council’s Law and Governance team commented that: The proposed equipment upgrade is in line with the UK government’s Climate Control commitment under Paris Agreement 2016 to reduce Global Warming through various measures including reduction of carbon emissions. The request also enables the Council to attain its own climate control commitment under the Climate and Ecological Emergency declaration (2019). The added advantage of the proposal would be recovering of the cost and achieving additional benefits in terms of improved efficiency and better energy mix and control. The request finds support in the Council policies and there are no adverse legal implications.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2 Riversmeet Leisure Centre: Energy Improvements Business CaseReport 442 KB DownloadRead as text
PDF
Decision Impact Assessment 518 for 2 Riversmeet Leisure Centre: Energy Improvements Business CaseDecisions 190 KB Download
PDF
Equalities Impact Assessment for 2 Riversmeet Leisure Centre: Energy Improvements Business CaseReport 103 KB Download

At this meeting

Whole meeting

Who was there

14 of 18 attended
P
Presentthe member of the committee was present as expected at the meeting
A
Apologiesthe member of the committee was unable to attend and reported their apologies in advance (substitute
A
Absentthe member of the committee was not present and did not apologise for their absence
IA
In attendancea councillor, who was not a member of the committee, was also in attendance
PB
Councillor Philip BroadheadChairman, present
NG
Councillor Nicola GreeneVice-Chairman, present
BD
Councillor Bobbie DoveCommittee Member, in attendance, virtual
BD
Councillor Beverley DunlopCommittee Member, present
MG
Councillor Mike GreeneCommittee Member, present
JK
Councillor Jane KellyCommittee Member, present
KR
Councillor Karen RamptonCommittee Member, present
MW
Councillor Mike WhiteCommittee Member, present

All 18 on the meeting page

On this subject at Bournemouth, Christchurch and Poole

Search all
  1. 2 Riversmeet Leisure Centre: Energy Improvements Business CaseThis decision
  2. Two Riversmeet Leisure Centre, Christchurch, BH23 1HWNoted
  3. Update on Two Riversmeet Leisure CentreNoted
  4. Two Riversmeet Leisure Complex Pool ClosuresNoted

More from Bournemouth, Christchurch and Poole Cabinet

All decisions
MeetingDecisionOutcome
2 Sep 2026 2026/27 Council Budget monitoring at Quarter 1RESOLVED that Cabinet: - (a) noted the Quarter 1 position for 2026/27, actions taken by the Section 151 Officer to da... Noted Open
2 Sep 2026 Learning Disability Big Plan 2026–2031RESOLVED that Cabinet approved the Learning Disability Big Plan for future publication and delivery against the prior... Approved Open
2 Sep 2026 IT & Programmes Infrastructure Capital Investment Plan 2026–2032RESOLVED that Cabinet: - (a) approved delegated procurement authority to Director of IT & Programmes; (b) recommend t... Approved Open
2 Sep 2026 BCP Homes Performance and Regulatory Compliance UpdateRESOLVED that Cabinet noted the content of the report and raised any issues for consideration by officers. Voting: Un... Noted Open
22 Jul 2026 Recommendations from the Overview and Scrutiny CommitteesDecision) The Leader thanked Councillor Canavan and the Committee for bringing their recommendation to Cabinet and ex... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies