Cabinet 4 February 2026 - Minute No. 123 - Hawkwood Road Phase 2 Update

Approved Committee 1 paper

AI summaryBCP Council approves 68 home Hawkwood Road Phase 2 build contract, with £17.3m grant, and authority to market or sell ground floor if NHS does not commit

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedProceed with Option 1 at Hawkwood Road Phase 2
Money£17.3m combined grantMHCLG and Homes England funding for the scheme
What happens nextAward build contractMarket or sell ground floor if NHS does not commit
Who it affectsBoscombe West residentsFuture social housing tenants and local services

What was decided

Council approved proceeding with Option 1 to enter the build contract for 68 homes and commercial floorspace, securing the £17.3m combined grant within the external funder's timescales. Report P1, P4

Council authorised the Estates team to market the ground floor as general commercial if the NHS does not commit funding, noting the full residential scheme is no longer deliverable. Report P2, P17

Council authorised the Corporate Property Officer to sell or long leasehold the ground floor commercial asset to secure a funding strategy to offset the cost of building. Report P3

Why

To meet funding deadlines set by MHCLG and Homes England, with the build required to start in April 2026 and complete by March 2029. Report P4, P15

To deliver 68 social rent homes and regeneration benefits in the Boscombe West ward, an area of high deprivation. Report P10, P31

Option 2 (100% residential) is no longer achievable within grant timeframes, would require a new planning application, and would risk losing £11m of grant. Report P16, P18

What happens next

Award the build contract and continue negotiations with NHS Dorset on a lease for the ground floor of Block A. Report P13, P14

Submit a planning application to vary the consented ground floor use from medical to include a range of commercial uses. Report P17

If NHS funding is not secured, the Estates team to market the ground floor and the Corporate Property Officer to progress sale or long leasehold. Report P2, P3

The money

  • £17.3m Total combined grant from MHCLG and Homes England to be secured Report P1, P4
  • £9.7m Homes England grant secured, the largest allocation for any BCP led scheme Report P11
  • c.£7m Towns Fund grant, required to be fully spent by 2028 Report P15
  • £28.7 million Previous overall scheme cost, reduced to £23.9 million Report P33
  • £22.2 million Revised Housing Revenue Account scheme cost Report P34
  • £4.8 million Revised HRA borrowing requirement, down from £6.1 million Report P37
  • £920,320 Borrowing exposure on the commercial space at PWLB rate of 5.73% Report P41
  • £71,141 Annual debt repayment on commercial space over 50 years Report P41, P47

Options considered

  • Chosen: Option 1: 68 homes with NHS or general commercial use on the ground floor of Block A. Lowest risk, deliverable within current funding programmes, and satisfies Homes England and MHCLG draw-down requirements. Report P17, P21
  • Rejected: Option 2: 100% residential scheme (76 or 78 homes, removing commercial use). Not achievable within grant timeframes, would need a new business case and planning application, and risks losing £11m of grant. Report P18, P26, P27

Implications

  • Financial: A borrowing exposure of £920,000 on the commercial space could increase the MTFP gap if the ground floor is not let. Report P45, P47
  • Financial: Not delivering the scheme could mean loss of £9.6 million Homes England grant and £7.7 million Towns Fund grant. Report P45
  • Legal: VAT partial exemption risk if NHS undertakes work that is landlord responsibility, which could disapply the option to tax. Report P66
  • Legal: Council must comply with procurement requirements and all grant funding conditions. Report P70, P71
  • Risk: Vacant ground floor is the main project risk; market letting prospects in Boscombe are uncertain and a recent valuation raised concerns. Report P43, P49, P84
  • Risk: Extending the build tender end date requires all tenderers to agree; if any decline, the tender must be collapsed, risking further delay. Report P51
  • Climate: Homes will be built to high sustainability standards using Passivhaus principles, contributing to the council's net zero carbon target. Report P76, P77, P78
  • Staffing: Existing Housing Delivery Team will oversee the scheme with no new resource implications. Report P73

Who and where

  • Residents of Boscombe West ward, an area of high deprivation Report P8, P31, P79
  • Future social housing tenants, prioritised through a local lettings plan Report P31
  • Local NHS services, with a neighbourhood health centre still being explored Report P14
  • Construction workforce, with jobs secured through the build phase Report P31
  • Local businesses and the wider Boscombe regeneration area Report P31, P43

Timeline

  • April 2026: Build must start on site to meet grant conditions Report P15
  • June 2026: Indicative start on site date for Option 1 Report P29
  • 31/03/2028: MHCLG Towns Fund full spend deadline Report P15, P29
  • June 2028: Practical Completion for Option 1 Report P29
  • March 2029: Homes England completion deadline Report P15, P29

Plain English for the jargon

  • MHCLG: Ministry of Housing, Communities and Local Government
  • HRA: Housing Revenue Account, the council's landlord account for council housing
  • PWLB: Public Works Loan Board, the government lending facility for local authorities
  • Towns Fund: Government regeneration fund for town centres
  • Passivhaus: High energy efficiency building standard with low carbon heating needs
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item80

Resolved

that Council: 1. grants approval to proceed with Option 1 to enter the build contract for 68 homes and commercial floorspace, prior to executing an Agreement to Lease for the ground floor of Block A, to secure the total combined grant of £17.3m and redevelopment of the Hawkwood Road site within the external funder’s timescales. 2. gives authority to the Estates team to market the non-residential property as general commercial, if the NHS is unable to commit funding for the ground floor of Block A and noting the full residential scheme is no longer deliverable. 3. gives authority to the Corporate Property Officer to proceed to sale or long leasehold of the ground floor commercial asset to ensure a funding strategy is secured to offset the cost of building. Voting: F64, A1 (2 Abstentions)
Word for word from the decision Bournemouth, Christchurch and Poole published for this meeting. Source: democracy.bcpcouncil.gov.uk

Follow this further

Built from Bournemouth, Christchurch and Poole's papers

What the report saysPro

Report to Council

Recommendations

It is RECOMMENDED Cabinet recommends to Council that: 1. Approval to proceed with Option 1 to enter the build contract for 68 homes and commercial floorspace, prior to executing an Agreement to Lease for the ground floor of Block A, to secure the total combined grant of £17.3m and redevelopment of the Hawkwood Road site within the external funder’s timescales.

2. Authority to market the non-residential property as general commercial, if the NHS is unable to commit funding for the ground floor of Block A and noting the full residential scheme is no longer deliverable.

3. Authority to proceed to sale or long leasehold of the ground floor commercial asset to ensure a funding strategy is secured to offset the cost of building.

Reason for To enter the build contract in line with the current active tender recommendations and grant funding milestones prior to the lease of the ground floor being signed. This will enable the Council to achieve the funding deadlines set by MHCLG and Homes England and ensures the project remains deliverable.

Portfolio Holder(s): Cllr Kieron Wilson, Portfolio Holder for Housing and Regulatory Services

Corporate Director Glynn Barton, Chief Operating Officer

Report Authors Peter Friend, Development Project Manager Remi Oshibanjo, Housing Development Manager Jonathan Thornton, Head of Housing Delivery

Wards Boscombe West;

Classification For Recommendation Ti t l e:

Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cabinet 4 February 2026: Minute No. 123: Hawkwood Road Phase 2 UpdateReport 237 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

69 of 80 attended
P
Presentthe member of the committee was present as expected at the meeting
A
Apologiesthe member of the committee was unable to attend and reported their apologies in advance (substitute
A
Absentthe member of the committee was not present and did not apologise for their absence
IA
In attendancea councillor, who was not a member of the committee, was also in attendance
LD
Councillor Lesley DedmanChair, present
SB
Councillor Simon BullVice-Chair, present
CA
Councillor Cameron AdamsCommittee Member, present
SA
Councillor Sue AitkenheadCommittee Member, present
HA
Councillor Hazel AllenCommittee Member, apologies
MA
Councillor Marcus AndrewsCommittee Member, present
SA
Councillor Sara ArmstrongCommittee Member, present
JB
Councillor Julie BagwellCommittee Member, present

All 80 on the meeting page

On this subject at Bournemouth, Christchurch and Poole

Search all
  1. Cabinet 4 February 2026 - Minute No. 123 - Hawkwood Road Phase 2 UpdateThis decision
  2. Cabinet 11 February 2026 - Minute No. 133 - Pokesdown Railway StationDecided
  3. Cabinet 4 February 2026 - Minute No. 120 - Our people and communities: Subsidised Bus Services ReviewApproved
  4. Cabinet 4 February 2026 - Minute No. 122 - Early Years Mainstream Schools Funding 2026/27Approved
  5. Recommendations from Cabinet 5 February 2025 - Minute No. 115 - Phase 2 - Council Sustainable Fleet Management Strategy and Fleet Replacement ProgrammeApproved
  6. Recommendations from the Cabinet - 5 February 2025Agreed

More from Bournemouth, Christchurch and Poole Council

All decisions
MeetingDecisionOutcome
11 Aug 2026 Confirmation of MinutesThat the minutes of the meeting held on 28 July 2026 be approved as a correct record. Approved Open
11 Aug 2026 Appointment of Corporate Director of Children's ServicesRESOLVED that: Council approved the appointment of Claire Shiels to the position of Corporate Director of Children’s ... Approved Open
11 Aug 2026 Notices of Motions in accordance with Procedure Rule 10That this Council resolves to: Instruct officers to review planning policies and advise on lawful options to limit th... Agreed Open
28 Jul 2026 Cabinet 22 July 2026 - Minute No. 26 - BCP Growth PlanRESOLVED that: - (a) the BCP Local Growth Plan be adopted; (b) the expected Dorset Local Enterprise Partnership capit... Approved Open