Cabinet 11 February 2026 - Minute No. 133 - Pokesdown Railway Station
DecidedCommittee1 paper
AI summaryBournemouth, Christchurch and Poole Council votes 38 to 13 to withdraw its £2.6m offer to the Pokesdown Station improvements project, citing higher borrowing costs and a reduced scope from rail partners.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedVote: 38 for, 13 against, 10 abstentions
Money£2.6m contribution withdrawn£9.75m total repayment avoided over 50 years
What happens nextOfficers to support future funding bidWork with partners on Access for All application
Who it affectsPokesdown Station passengers needing liftsDisabled, elderly, pregnant, young passengers affected
What was decided
Council resolved to withdraw the offer of a £2.6m contribution to the Pokesdown Railway Station Improvements project, on the recommendation of Cabinet. Report P7
The motion passed with 38 votes for, 13 against and 10 abstentions; two councillors left the room or meeting before the vote.
The decision takes effect despite the project not being contractually committed by the council and no legal agreement being in place with the rail partners. Report P19
Why
Annual borrowing repayment has risen from £140k in 2022 to over £195k in 2026, meaning £9.75m would be paid across the next 50 years. Report P8, P19
The expected project scope has been cut back to lifts and platform canopies only, with no firm assurance from partners that it is deliverable within budget. Report P5, P8, P14
Withdrawal is intended to safeguard spending on statutory services, with a stated £140k per year saving noted in the financial summary. Report P19
What happens next
Officers will continue to work with South Western Railway and Network Rail on a future Access for All funding application for lifts at the station. Report P14, P19
No contractual liability or compensation arises from withdrawal, as no legal agreement has been signed with the rail partners. Report P19
An Equalities Impact Assessment Screening has been completed, recording a negative impact on passengers needing lift access while the saving is redirected to wider statutory services. Report P23, P25, P29, P37
The money
£2.6m Council contribution offer being withdrawn Report P5, P7
£140k per year Annual borrowing repayment at 2022 Report P8, P14, P19
over £195k per year Annual borrowing repayment at 2026 Report P8, P14, P19
£9.75m Total council repayment over 50 years if project continued Report P8, P19
£55k per year Additional pressure from increased cost of borrowing Report P8, P19
£140k per year Stated saving from withdrawal (financial summary) Report P19
£195k per year Stated saving from withdrawal (recommendation reason) Report P8
£116k Current MTFP allocation to project in 2027/28 Report P19
£79k MTFP pressure in 2028/29 if £2.6m contribution continued Report P19
£24k MTFP pressure in 2028/29 under £1.85m reduced option Report P19
£5.7m Original estimated total scheme cost in November 2021 Report P14
£1.0m Additional SWR/NR funding earmarked in 2023/24 Report P14
£6.7m Updated scheme budget after 2023/24 addition Report P14
£7.19m Revised scheme cost estimate from summer/autumn 2025 Report P14
£0.273m Further SWR funding announced in December 2025 Report P15
£1.6m Amount SWR/NR reported spending on design development Report P19
£1.85m Reduced contribution option considered Report P14
Options considered
Rejected: Option 1: Continue with £2.6m contribution as approved in January 2022. Higher borrowing cost (£195k per year) and uncertain deliverability within budget Report P14
Rejected: Option 2: Reduce council contribution to £1.85m. Unlikely Network Rail and South Western Railway would source the additional £750k and scheme would be deferred Report P14
Chosen: Option 3: Withdraw £2.6m capital contribution. Zero borrowing cost, council officers to continue supporting a future Access for All funding bid Report P14
Implications
Financial: Withdrawal avoids £9.75m in total repayments over 50 years and is presented as helping to safeguard spending on statutory services. Report P8, P19
Equalities: EIA screening records a negative impact: passengers with mobility impairments, including disabled, elderly, young and pregnant users, will not gain lift access at the station until alternative funding is found. Report P25, P29, P31, P32, P33, P35, P37
Legal: The council is not contractually bound to the project and no legal agreement has been signed, so withdrawal does not give rise to compensation liability. Report P19
Risk: Officers identify no significant risk implications from withdrawal; the project could still proceed if partners or government fund it. Report P19
Staffing: Two BCP officers currently engage with rail partners monthly, described as a minimal resource impact. Report P19
Other: Sustainability and public health summaries note that withdrawal may reduce encouragement of sustainable travel, but protects wider statutory services with broader public benefit. Report P19
Who and where
Passengers needing lift access at Pokesdown Station, particularly wheelchair users and those with limited mobility Report P14, P29, P37
Pregnant women and passengers with young children or heavy luggage Report P14, P32
Younger and older passengers who would have benefited from lift access Report P31
South Western Railway and Network Rail as project delivery partners Report P14, P15
Council taxpayers across Bournemouth, Christchurch and Poole, through redirected funding to statutory services Report P19, P34, P36
Timeline
2017: SWR franchise agreement included obligation to provide lifts at Pokesdown Station Report P14
May 2021: New National Rail Contract replaced the 2017 SWR franchise Report P14
November 2021: Estimated total scheme cost set at £5.7m with SWR and Network Rail committing £3.1m Report P14
24 November 2021: Cabinet recommended the £2.6m council contribution from BCP Future Fund Report P14, P20
11 January 2022: Council approved the £2.6m contribution offer Report P5, P14, P22
2023: Scheme cost rose beyond £5.7m budget and SWR/Network Rail added £1.0m, taking budget to £6.7m Report P14
Spring 2025: Structural testing confirmed existing lift shafts could be strengthened and refurbished Report P14
Summer/autumn 2025: Outline design produced revised cost estimate of £7.19m Report P14
November 2025: SWR/Network Rail reported a 5-month delay due to lift mechanism redesign Report P14
19 December 2025: SWR emailed council confirming an additional £0.273m and setting out risk funds Report P15
7 January 2026: Equalities Impact Assessment screening conversation took place Report P28
11 February 2026: Cabinet recommended Council withdraw the £2.6m offer Report P3, P7
24 February 2026: Council voted 38 to 13 (10 abstentions) to withdraw the offer
April 2026: SWR expected to confirm final project costs Report P18
2027/28: MTFP currently allocates £116k to the project Report P19
2027 onwards: Earliest possible delivery of lifts if Option 1 had been pursued Report P14
Plain English for the jargon
SWR: South Western Railway, the train operator
NR: Network Rail, owner and operator of most rail infrastructure
DfT: Department for Transport
BCR: Benefit Cost Ratio, a measure of scheme value for money
MTFP: Medium Term Financial Plan, the council's multi-year budget plan
EIA: Equality Impact Assessment
Access for All: Government programme providing funding for accessibility improvements at railway stations
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item95
Resolved
RESOLVED that Council withdraw the offer of a £2.6m contribution to the Pokesdown Railway Station Improvements project. Voting: For:38, Against:13, Abstentions:10 Councillor Jamie Martin declared an interest in this item and left the room for the discussion and voting thereon. Councillor Rachel Pattinson-West left the meeting at 11.28pm prior to the vote on the substantive motion.
Word for word from the decision Bournemouth, Christchurch and Poole published for this meeting.Source: democracy.bcpcouncil.gov.uk
Follow this further
Built from Bournemouth, Christchurch and Poole's papers
Executive summary On 11 January 2022, the Council approved a contribution of up to £2.6m towards the Pokesdown Railway Station Improvement Project. The original scope was expected to include replacement, or upgrade of the station building, a new forecourt with interchange facilities, CCTV and help point improvements, seating and shelter improvements in addition to converting the existing lift shafts to passenger use and repairing and painting the footbridge and canopies (all subject to available budget). The project has not been delivered, detailed timescales and costs are undetermined, and the expected scope has been reduced to the lifts and canopies over the platforms only. At the same time, the cost of borrowing has increased. In consideration of the above a recommendation is sought from Cabinet regarding the council commitment to the project.
Recommendations It is RECOMMENDED that:
a. Cabinet recommends to Council withdrawal of the offer of a £2.6m contribution to the Pokesdown Railway Station Improvements project.
Reason for 1. Approval for the contribution was 4 years ago. The annual recommendations repayment for borrowing the contribution has increased from £140k per year in 2022 to over £195k per year in 2026. This means that a total of £9.75m would now be paid by the council across the next 50 years if it continues to part fund the project. 2. Supporting the project would create a £55k per year additional pressure for the cost of borrowing. Withdrawing the council’s financial contribution to this project would therefore in-effect create a £195k per year saving helping the council to safeguard statutory (essential) services. 3. The proposed scope of the project has reduced. 4. As of January 2026, whilst there has been email correspondence stating that the total budget has been increased there is no firm assurance from partners that the project is deliverable within the available budget.
Portfolio Holder(s): Councillor Mike Cox – Deputy Leader of the Council, Vice-Chair of Cabinet and Cabinet Member for Finance Councillor Andy Hadley – Cabinet Member for Climate Response, Environment and Energy Councillor Richard Herrett – Cabinet Member for Destination, Leisure & Commercial Operations
Corporate Director Glynn Barton – Chief Operations Officer
Report Authors Richard Pincroft – Head of Transport and Sustainable Travel Claire Clark – LTP & Capital Programme Manager
Wards Council-wide
Classification For Decision and Information Ti t l e:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.