Cabinet 4 March 2026 - Minute No. 155 - Our Place and Environment: BCP Council Lane Rental Scheme
ApprovedCommittee1 paper
AI summaryBCP Council approves applying to the Secretary of State for Transport to set up a Lane Rental Scheme charging up to £2,500 a day for roadworks on the busiest streets.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedVote unanimous, delegation to officer agreed
MoneyUp to £2,500 per day chargeSetup £75k, operating £500k per year
What happens nextSubmit application to Secretary of StateSubject to ministerial approval
Who it affectsUtility companies, council, developersAll road works promoters on key routes
What was decided
Council approved submitting an application to the Secretary of State for Transport to establish and operate a Lane Rental Scheme across Bournemouth, Christchurch and Poole. Report P7
If approved by the Secretary of State, the establishment and operation of the scheme is delegated to the Service Director for Planning and Transport, in consultation with the Portfolio Holder for Climate Mitigation, Energy and Environment. Report P7
The vote was unanimous, with three councillors recorded as leaving the meeting before the close of the item.
Why
Charging works promoters for time spent on the busiest roads at peak times is intended to cut disruption, shorten works, encourage collaboration and drive innovation, with existing schemes reporting congestion reductions of between 9 and 25%. Report P8, P15
Public consultation from 15 December 2025 to 1 February 2026 drew 156 responses, with 85% of individuals and 73% of businesses agreeing or strongly agreeing with the proposal. Report P14
A cost benefit analysis predicts a Benefit Cost Ratio of 8.9, with the scheme expected to generate an annual surplus of about £1.8m after operating costs. Report P17, P21
What happens next
The council will submit the formal application to the Secretary of State for Transport, with the proposal following the Department for Transport's published guidance. Report P5, P14, P24
Around £75k of set up costs will initially be drawn from the Local Transport Consolidated Fund 2026/27 programme, with the Service Director reporting back on the running of the scheme once established. Report P17, P7
A BCPLRS Surplus Fund Management Board will be set up to oversee surplus revenue, and the scheme will be reviewed annually once in operation. Report P17, P14
The money
£2,500 per day Maximum lane rental charge on the busiest roads at the busiest times Report P5
£75k One off set up cost of the scheme Report P17
£500k per annum Estimated ongoing operating cost Report P17
£2.3m per annum Estimated total lane rental charges levied Report P17, P21
£1.8m per annum Estimated annual surplus after operating costs Report P21
£900k Estimated 50% of surplus ringfenced for highway maintenance Report P21
£460k per annum Estimated annual LRS charges to the council as Highway Authority Report P17, P21
£1.85m Estimated annual LRS charges to Public Utility companies Report P17
£40 to £50k per annum Estimated loss of permit scheme income Report P17
Options considered
Chosen: Proceed with an application to establish a BCP Lane Rental Scheme. Existing schemes have cut congestion on defined routes by between 9 and 25%, and the cost benefit analysis projects a Benefit Cost Ratio of 8.9. Report P15, P17
Rejected: Do not proceed with an application. None of the benefits of a lane rental scheme would be realised. Report P16
Rejected: Amend the scheme by reducing charges or widening the times of day that charges do not apply. Lower charges would weaken the incentive to work more efficiently or collaboratively, and broader exemption times would push more works onto traffic sensitive routes. Report P16
Implications
Legal: The scheme operates under Section 74A of the New Roads and Street Works Act 1991, with implementation needing the approval of the Secretary of State for Transport, and the council must report annually on the impact, costs and revenues of both the permit and lane rental schemes. Report P14, P17, P21
Equalities: An Equalities Impact Assessment concluded the scheme will only bring benefits to communities and to people with protected characteristics, through reduced congestion, improved journey reliability and better public transport access. Report P23
Climate: The scheme is expected to reduce congestion and works durations, supporting the council's priority for an eco-friendly and active transport network, although NOx emissions from diesel cars are noted as the largest single road transport contributor. Report P23
Risk: The main risk identified is a legal challenge arising from process or documentation errors; the council says it has followed DfT guidance and used consultants who have implemented other schemes. Report P24
Staffing: Operating the scheme is expected to require 5 new posts (1 Lane Rental Scheme Coordinator, 2 Street Works Inspectors, 2 Permit Officers) and a possible re-evaluation of up to 7 existing posts. Report P22
Other: 50% of net surplus income must be spent on highway maintenance, with the remaining 50% to reduce disruption or support innovation, overseen by a new BCPLRS Surplus Fund Management Board. Report P17, P21
Who and where
Public utility companies and their contractors carrying out street works on the lane rental network Report P14, P17
BCP Council's own highways maintenance and improvement teams, who will pay the same charges as utility companies Report P17, P47
Third-party developers working under Section 278 Highways Act agreements Report P47
Road users across Bournemouth, Christchurch and Poole, including bus passengers, cyclists and pedestrians Report P8, P41
All council wards, as the proposal applies council-wide Report P12
Timeline
8 December 2025: Stakeholder briefing held before public consultation launched Report P14
15 December 2025: Public consultation on the proposed Lane Rental Scheme goes live Report P14
5 January 2026: Amended DfT Regulations on the Code of Practice for the Co-ordination of Street and Road Works take effect Report P17
1 February 2026: Public consultation closes Report P14
Summer 2025: Traffic sensitive network review and consultation completed as a mandatory step before applying Report P14
4 March 2026: Cabinet recommends that Council approve the application Report P3, P6
24 March 2026: Council approves the application and the delegation
Plain English for the jargon
Lane Rental Scheme: A scheme under Section 74A of the New Roads and Street Works Act 1991 that lets a highway authority charge promoters a daily fee for the time their works occupy the busiest parts of the road network at peak times.
Permit Scheme (BCPPS): The council's existing street works permit scheme, in force since September 2020, requiring promoters to apply for permission before carrying out works on the highway.
Traffic sensitive street: A street on a network defined by the council where extra restrictions apply to road works because of the level of traffic.
USRN: Unique Street Reference Number, the identifier used for each street in the National Street Gazetteer.
Promoter: Any person or organisation that commissions or carries out specified works on the highway.
Immediate works: Emergency or urgent works that must be carried out at once to avoid danger or serious damage; these get a 48 hour charge free period under the scheme.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item108
Resolved
RESOLVED that Council: - (a) approved the submission of an application to the Secretary of State for Transport to establish and operate a Lane Rental Scheme across Bournemouth, Christchurch and Poole; and (b) subject to Secretary of State approval, delegate the establishment and operation of a BCP Lane Rental scheme to the Service Director for Planning and Transport in consultation with the Portfolio Holder for Climate Mitigation, Energy and Environment. Voting: Unanimous Councillors John Challinor and Matthew Gillet left the meeting at 9.44pm Councillor Gavin Wright left the meeting at 9.46pm The Chairman advised the Council that it would now consider the additional recommendation arising from the Audit and Governance Committee held on the 19 March 2026, as circulated in the supplementary pack which, was to be brought before Council as an urgent item in accordance with the Constitution.
Word for word from the decision Bournemouth, Christchurch and Poole published for this meeting.Source: democracy.bcpcouncil.gov.uk
Follow this further
Built from Bournemouth, Christchurch and Poole's papers
Report subject Our Place and Environment: BCP Council Lane Rental Scheme
Meeting date 4 March 2026
Status Public Report
Executive summary The council has consulted on the potential establishment of a BCP Lane Rental Scheme (LRS) which would enable the council to charge up to £2,500 per day for works on the busiest roads at the busiest times. This report presents the outputs of the consultation and seeks approval to apply to the Secretary of State for Transport to establish a BCP Lane Rental Scheme.
Recommendations It is RECOMMENDED that Cabinet recommends to Council to:
(a) approve the submission of an application to the Secretary of State for Transport to establish and operate a Lane Rental Scheme across Bournemouth, Christchurch and Poole (b) subject to Secretary of State approval, delegate the establishment and operation of a BCP Lane Rental scheme to the Service Director for Planning and Transport in consultation with the Portfolio Holder for Climate Mitigation, Energy and Environment.
Reason for The introduction of a Lane Rental Scheme would help to recommendations encourage: (a) Behaviour change to minimise the duration of road works occupation of the highway at the busiest locations at the traffic-sensitive times (b) Right first-time reinstatements (c) Minimise the number of works taking place during traffic- sensitive times (d) Contribute to reducing disruption to all road users (e) Encourage a proactive approach to planning and undertaking of works on the highway (f) Encourage innovations that will reduce the duration and need for roadworks (g) Encourage collaborative working amongst activity promotors (h) Ensure parity of treatment for all activity promoters (i) Reduce any unreasonable occupation of the Highway through efficient coordination and minimise the impact of works on the travelling public.
Portfolio Holder(s): Councillor Andy Hadley, Cabinet Member for Climate Mitigation, Energy and Environment
Corporate Director Glynn Barton, Chief Operations Officer
Report Authors Richard Pincroft, Head of Transport and Sustainable Travel Richard Pearson, Transport Network Manager
Wards Council-wide
Classification For Information and Recommendation Ti t l e:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.