CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bournemouth, Christchurch and Poole Council
Council, Tuesday 24 March 2026 at 7.00pm

Audit and Governance Committee 19 March 2026 - Minute No. 119 - Two Riversmeet Studios

Approved Committee 3 papers

AI summaryBournemouth, Christchurch and Poole Council approves £1.8m borrowing for a two-storey extension at Two Riversmeet Leisure Centre in Christchurch, creating two new multi-use studios.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedBorrowing of £1.8m authorised by Council vote
Money£1.8m borrowingIncludes 20% contingency on build costs
What happens nextPlanning application and detailed designSubject to planning permission
Who it affectsTwo Riversmeet Leisure Centre, ChristchurchTwo new multi-use studios to be added

What was decided

Council approved authorised borrowing of £1.8m to finance a two-storey extension at Two Riversmeet Leisure Centre, creating two new multi-use studios, subject to planning permission. Report P7, P13

The vote was carried with 31 members in favour, 9 against and 8 abstentions.

Capital funding will not be drawn down until planning is complete; further risk assessment will follow a planning milestone review before construction begins. Report P21, P16

Why

The extension is intended to give Christchurch dedicated studio space, address unmet demand for group exercise, and strengthen BCP Leisure's financial position under the council's corporate strategy. Report P5, P8, P14

Officers considered five options: doing nothing, new two-storey build, repurposing the squash courts, a mezzanine over the sports hall, and a single-storey extension beside the pool. The new build was preferred for capacity, income potential and strategic fit. Report P15

A competing review by Strategic Leisure Limited and updated marketing analysis both indicated that purpose-built studios are needed to keep the centre competitive and support growth in memberships, facility hire and cultural services such as dance and martial arts. Report P14, P15, P16

What happens next

A planning application will be submitted, with the project timeline built around the nesting season and planning requirements; construction is not expected to start before 2027. Report P15, P16

The Director of Commercial Operations will act as Senior Responsible Officer, chairing a project group with a live risk log and milestone reporting, including a further risk review once planning is granted. Report P21

A separate review of the future management model for the council's five in-house leisure centres is scheduled to be presented to Cabinet later in 2026. Report P14

The money

  • £1.8m Total prudential borrowing to finance the two-storey extension Report P7, P13
  • £1.1m Estimated cost of repurposing the squash courts (rejected option) Report P15
  • £133,416 Estimated part-year borrowing cost in the year of construction Report P16
  • £10,000 Annual sinking fund contribution from 2028/29, accumulating to around £227k over 20 years Report P16
  • £100k+ Income that would have been lost from the sports hall if a mezzanine option was taken Report P15
  • 5.88% PWLB prevailing interest rate used in the financial model Report P16
  • 5.5% BCP low-risk interest rate used in alternative sensitivity scenarios Report P16
  • 20% Contingency built into the £1.8m capital cost estimate Report P16

Options considered

  • Rejected: Do nothing. Carries the highest long-term risk and would leave Christchurch as the only town with no studios in its public leisure centre. Report P15
  • Chosen: Build new two-storey extension with £1.8m capital borrowing. Delivers the highest long-term financial return, supports an estimated 18% membership increase, and provides capacity for cultural services such as dance and martial arts. Report P15, P16
  • Rejected: Repurpose existing squash courts into a single studio. Would cost around £1.1m, only fit 15-20 participants, lose squash income and offer poor value for money. Report P15
  • Rejected: Create a mezzanine level in the sports hall. Required extensive structural work, new piled foundations and would have taken the sports hall out of use, losing more than £100k of income. Report P15
  • Rejected: Single-storey extension adjacent to the swimming pool. Did not provide enough space for the studios, plant rooms and storage requirements. Report P15
  • Rejected: Build on a new standalone site. Not considered due to higher operating costs and loss of the existing community leisure centre offer. Report P15

Implications

  • Financial: Sensitivity analysis shows the scheme is viable at the higher 5.88% PWLB rate only with an 18% membership increase, generating a £880,000 surplus over 20 years; a 10% membership rise would produce a deficit of £1.3m to £1.8m. Report P16
  • Financial: Cost of borrowing begins in 2027/28 on a maturity basis, with a £10,000 per year sinking fund from 2028/29 building to around £227,000 by year 20 for major repairs. Report P16
  • Financial: Best-case scenario (lower interest rate, 5% underspend, optimum membership) could deliver a £1.4m surplus; worst-case could deliver a £1.8m deficit over 20 years. Report P16
  • Legal: The project must comply with BCP Council's Financial Regulations, the Public Contracts Regulations 2015, the Procurement Act 2023, subsidy control, planning, CIL, land and funding conditions, and the council's Constitution. Report P17
  • Equalities: An Equality Impact Assessment conversation has been completed and reviewed by the council's Equality team; new studios are expected to widen access for different abilities, rehabilitation, special educational needs and cultural groups. Report P20
  • Climate: The new studio will integrate with the existing Building Management System controlling PV panels, air handling units, air source heat pumps and boilers, and will meet paragraph 39 of the council's Local List of Requirements for planning. Report P19
  • Risk: A project risk register and governance structure will be maintained, with the Director of Commercial Operations as Senior Responsible Officer and escalation required for any risk above moderate. Report P21
  • Staffing: No additional building management staff are required as duty management already covers the site; class staffing will use a mix of casual and contracted staff on a timetable basis. Report P18

Who and where

  • Residents of Christchurch using Two Riversmeet Leisure Centre Report P5, P11
  • BCP Leisure members and potential new members Report P14, P16
  • Local groups using the centre for dance, drama, martial arts and other cultural activities Report P15
  • GP referral scheme users Report P19
  • Staffing teams operating classes at the centre Report P18

Timeline

  • 14 January 2026: Cabinet approved and referred the business case to Audit and Governance Committee. Report P13
  • 15 January 2026: Audit and Governance Committee asked for additional information before deciding on borrowing. Report P13
  • 19 March 2026: Audit and Governance Committee considered the further information and recommended approval to Council. Report P3
  • 24 March 2026: Council approved the £1.8m borrowing.
  • 2026/27: Planning application phase, with 60% income assumed for a part-year opening once operational. Report P16
  • 2027: Construction expected to begin, with the timeline built around the March-August nesting season; borrowing costs start in 2027/28. Report P15, P16
  • 2028/29: Annual £10,000 sinking fund contribution begins. Report P16
  • Later in 2026: Wider leisure centre transformation review for the five in-house sites to be presented to Cabinet. Report P15

Plain English for the jargon

  • PWLB: Public Works Loan Board, a UK government body that lends to local authorities.
  • MTFP: Medium Term Financial Plan, the council's multi-year budget planning document.
  • EIA: Equality Impact Assessment, an analysis of how a proposal may affect people with protected characteristics.
  • BMS: Building Management System, computer-based controls that monitor and optimise a building's mechanical and electrical services.
  • PV / AHU / ASHP: Photovoltaic (solar) panels, Air Handling Units, and Air Source Heat Pumps used to provide power and heating/cooling.
  • CIL: Community Infrastructure Levy, a charge that local authorities can levy on new development.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item109

Resolved

RESOLVED that Council approved authorised borrowing of the Council to accommodate the £1.8m financing for the extension at Two Riversmeet Leisure Centre proposal. Voting: For:31, Against:9, Abstentions:8
Word for word from the decision Bournemouth, Christchurch and Poole published for this meeting. Source: democracy.bcpcouncil.gov.uk

Follow this further

Built from Bournemouth, Christchurch and Poole's papers

What the report saysPro

Report to Council

AUDIT AND GOVERNANCE COMMITTEE

Report subject Two Riversmeet Studios

Meeting date 19 March 2026

Status Public report with exempt appendices

Executive summary The report provides additional information requested from Audit & Governance Committee regarding the financial considerations for capital borrowing to fund a two-storey extension to Two Riversmeet Leisure Centre (2RM) to address the identified need for dedicated studio space in Christchurch. The investment aims to enhance the centres health, fitness and cultural offer, increase membership and income whilst supporting community wellbeing and aligning with the Council’s corporate strategy.

Recommendations It is RECOMMENDED that Audit and Governance Committee recommend to Council:

a) Approval of authorised borrowing of the Council to accommodate the £1.8m financing for the extension at Two Riversmeet Leisure Centre proposal.

Reason for Enhancing 2RM Leisure Centre with dedicated studio space will recommendations enable the centre under BCP Leisure to grow and strengthen its financial position by offering a refreshed, modern facility for Christchurch. The project aligns with the corporate strategy ensuring people can be active and healthy while expanding access to high-quality cultural, health and wellbeing services for the local community. Portfolio Holder(s): Portfolio Holder for Destination, Leisure & Commercial Operations

Corporate Director Glynn Barton – Chief Operations Officer

Report Authors Amanda Barrie – Director of Commercial Operations Helen Wildman – Head of Leisure & Events

Wards Christchurch Town;

Classification For Decision Ti t l e:

Background 1. A paper was taken to Cabinet on 14 January 2026 recommending Cabinet to recommend to Council approving the building of a two-storey facility extension at Two Riversmeet Leisure Centre (2RM) through prudential borrowing creating two brand new multi-use studios costing £1.8m, subject to planning permission. 2. The Cabinet paper was approved and taken to the Audit and Governance meeting on 15 January, where the committee asked for additional information to be provided before making a decision on the borrowing. 3. This paper sets out the additional information requested by the Audit and Governance Committee.

Current Leisure Centre provision 4. Two Riversmeet Leisure Centre (2RM) is one of ten BCP Council owned leisure centres. Five of these are currently being operated in house as BCP Leisure. 5. This gap limits its ability to meet growing demand for group exercise, health and wellbeing, martial arts and cultural services. 6. A timeline is in place starting from 2027 to undertake a review of the management of leisure centres, looking at the position of leisure across BCP Council and to recommend the future management model. 7. Therefore, alternative management models have not been considered in the options appraisal for the studios. 8. In the meantime, BCP Council will need to continue to maintain the facilities ahead of this work to ensure they remain in line with the market and support the Medium Term Financial Plan (MTFP). 9. The 2RM Studio scheme draws directly on the learning from BCP Council’s recent highly successful leisure investment at Kings Park Leisure and learning Centre in Boscombe, demonstrating the Council’s ability to develop and operate facilities that are both financially robust and strongly aligned to resident demand, ensuring this asset performs effectively for the Council’s wider leisure portfolio. 10. A market competitor analysis was originally completed to assess the need in addition to what had been identified through the Built Facilities Needs Assessment. An updated analysis of the current provision can be found in appendix 9 (restricted). 11. Using the Sports England National Moving Communities data platform, engagement in group workout activities at Two Riversmeet sits at 20.86%, almost 10% more participants than the national benchmark of 10.90%.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
for Two Riversmeet StudiosAppendix 1 204 KB Download
PDF
for Two Riversmeet StudiosAppendix 4 642 KB Download
PDF
Audit and Governance Committee 19 March 2026: Minute No. 119: Two Riversmeet StudiosReport 441 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

71 of 80 attended
P
Presentthe member of the committee was present as expected at the meeting
A
Apologiesthe member of the committee was unable to attend and reported their apologies in advance (substitute
A
Absentthe member of the committee was not present and did not apologise for their absence
IA
In attendancea councillor, who was not a member of the committee, was also in attendance
LD
Councillor Lesley DedmanChair, present
SB
Councillor Simon BullVice-Chair, present
CA
Councillor Cameron AdamsCommittee Member, present
SA
Councillor Sue AitkenheadCommittee Member, present
HA
Councillor Hazel AllenCommittee Member, present
MA
Councillor Marcus AndrewsCommittee Member, present
SA
Councillor Sara ArmstrongCommittee Member, present
JB
Councillor Julie BagwellCommittee Member, apologies

All 80 on the meeting page

On this subject at Bournemouth, Christchurch and Poole

Search all
  1. Audit and Governance Committee 19 March 2026 - Minute No. 119 - Two Riversmeet StudiosThis decision
  2. Appointment of Independent co-opted persons to Audit & Governance (A&G) CommitteeAgreed
  3. Audit and Governance Committee 26 February 2026 - Minute No. 103 - Financial Regulations - Annual evolution for the financial year 2026/27Approved
  4. Audit and Governance Committee 15 January 2026 – Minute No. 86 – Treasury Management Monitoring report for the period April to December 2025 and Treasury Management Strategy 2026/27Approved
  5. Audit and Governance Committee 27 February 2025 - Minute No. 78 - Financial Regulations - Annual evolution for the financial year 2025/26Approved
  6. Recommendations from Audit and Governance Committee 27 January 2025 - Minute No. 64 - Increased Borrowing - Hawkwood Road and Housing Delivery Council Newbuild Housing and Acquisition Strategy (CNHAS)Agreed

More from Bournemouth, Christchurch and Poole Council

All decisions
MeetingDecisionOutcome
11 Aug 2026 Confirmation of MinutesThat the minutes of the meeting held on 28 July 2026 be approved as a correct record. Approved Open
11 Aug 2026 Appointment of Corporate Director of Children's ServicesRESOLVED that: Council approved the appointment of Claire Shiels to the position of Corporate Director of Children’s ... Approved Open
11 Aug 2026 Notices of Motions in accordance with Procedure Rule 10That this Council resolves to: Instruct officers to review planning policies and advise on lawful options to limit th... Agreed Open
28 Jul 2026 Cabinet 22 July 2026 - Minute No. 26 - BCP Growth PlanRESOLVED that: - (a) the BCP Local Growth Plan be adopted; (b) the expected Dorset Local Enterprise Partnership capit... Approved Open
28 Jul 2026 Cabinet 22 July 2026 - Minute No. 28 - Youth Justice Plan 2026-2027RESOLVED that the Youth Justice Plan 2026/27 be approved by Full Council. Voting: Unanimous Councillor Sara Armstrong... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies