AI summaryBCP Planning Committee grants permission for 20-flat redevelopment on Holdenhurst Road, Bournemouth, despite heritage and employment-loss concerns, on a 5-2-1 vote.
Written from the decision and the officer reportPDF Pro
OutcomeDecided20 flats in a 3.5-storey block, car-free
MoneyNot stated
What happens nextS106 legal agreementTo secure financial contributions via legal agreement
Who it affectsEast Cliff & Springbourne WardSite near Grade II listed St Mary's Church
What was decided
The committee resolved to grant planning permission in accordance with the officer's recommendation, as updated by the Committee Addendum.
Permission is for demolition of two two-storey mixed-use buildings and replacement with a 3.5-storey block of 20 flats, accessed from Holdenhurst Road, with no on-site parking. Report P2, P14
The mix is 14 one-bedroom flats and 6 two-bedroom flats, with refuse storage, cycle storage and landscaping. Report P2, P14, P39
Why
Officers accepted the scheme on a tilted balance, noting BCP had only 2.55 years of housing land supply at 9 February 2026, giving significant weight to the 15 net additional homes. Report P37, P70
Amendments from the previously refused 26-flat scheme reduced bulk, mass and dormer windows, with the heritage harm judged less than substantial and outweighed by public benefits. Report P17, P48, P70
Officers considered loss of employment floor space contrary to Policy CS27, but the planning balance under paragraph 11 of the NPPF still weighed in favour of approval. Report P38, P70
What happens next
A S106 agreement is required to secure the £25,000 bus shelter contribution, £5,670 Dorset Heathlands mitigation, and £4,725 New Forest SAMM payment. Report P57, P69
Conditions will secure obscure glazing on rear windows, biodiversity enhancements, contamination reporting, drainage compliance, and landscaping. Report P49, P55, P60, P62
The money
£25,000.00 Financial contribution for a replacement bus shelter with RTI on Holdenhurst Road Report P57
£4,725 New Forest SAMM payment (secured via S106) Report P69
£360 per apartment Heathlands contribution rate, plus 5% admin fee or £75 minimum Report P69
£300 per dwelling New Forest SAMM rate, plus admin fee Report P69
Options considered
Chosen: Grant permission as recommended. Tilted balance under NPPF para 11; housing supply at 2.55 years; public benefits outweigh less than substantial heritage harm Report P37, P70
Implications
Legal: A S106 agreement is needed to secure highways, Heathlands and New Forest contributions before any planning permission is issued. Report P57, P69
Equalities: Officers had due regard to the Public Sector Equalities Duty under section 149 Equality Act 2010. Report P26
Climate: Biodiversity enhancements required as conditions, including swift bricks, bat boxes and bee bricks; site is exempt from the 10% biodiversity net gain requirement as it is entirely hardstanding. Report P62, P64
Risk: Land contamination condition required because of nearby disused fuel tanks at 1 Jefferson Avenue. Report P60
Other: Less than substantial harm identified to the setting of the Grade II listed Church of St Mary, judged to be outweighed by public benefits. Report P48, P70
Who and where
Neighbouring residents of 424 Holdenhurst Road / 1-7 Curzon Road, 9 and 11 Curzon Road, 1 and 1A Jefferson Road, and 434 Holdenhurst Road Report P49, P50
SAMM: Strategic Access Management and Monitoring, a tariff paid by new housing towards protecting protected heathland and New Forest sites from recreational pressure.
Tilted balance: The NPPF paragraph 11 test, applied where a council cannot show a five-year housing land supply, which presumes planning permission should be granted unless harms significantly outweigh benefits.
Less than substantial harm: A category of harm to a heritage asset's significance under the NPPF that must be weighed against the public benefits of a scheme.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item15b
Resolved
RESOLVED to GRANT permission in accordance with the recommendation set out in the officer’s report, as updated by the Committee Addendum published. Voting: For – 5, Against – 2, Abstain – 1 Notes: Cllr Armstrong sat in the public gallery for this item, spoke as a ward Councillor and did not vote on this item.
Word for word from the decision Bournemouth, Christchurch and Poole published for this meeting.Source: democracy.bcpcouncil.gov.uk
Follow this further
Built from Bournemouth, Christchurch and Poole's papers
Proposal Redevelopment of the site to provide residential accommodation of 20 flats (use class C3): including landscaping, refuse storage, cycle storage and other associated infrastructure.
Application Number 7-2024-29061-A
Applicant Clifton Developments Ltd
Agent Ken Parke Planning Consultants Ltd
Ward and Ward East Cliff & Springbourne Ward Member(s) - Councillor Sara Armstrong - Councillor Anne Filler - Councillor Anne-Marie Moriarty
Report Status Public
Meeting Date 5 June 2026
Summary of Grant in accordance with the details set out below Recommendation for the reasons as set out in the report
Reason for Referral to At the request of Councillor Sara Armstrong, for the Planning Committee following reasons: Bins and waste management issue Loss of the existing parking spaces. Parking - impact on already overcrowded surrounding roads. Heritage - look and feel of the area and dominance of the building on the landscape. Deliveries – a modern part of life nowadays. There is nowhere for delivery vans to safely stop. This could cause traffic blockages and reduce access as delivery vans park on the pavements/bus stop.
Page 1 Built up area - demolition and environmental impacts of that. Height of the building- privacy, light impact around surrounding properties. Size of the flats - tiny - quality of life for the residents. Lack of green space for residents. Lack of space to dry clothing. The need for family housing not more 1 bed flats. Against Local Plan
Case Officer Adam Davies
Is the proposal EIA No Development?
Description of Proposal 1. Planning permission is sought for the demolition of two no. two-storey buildings comprised of office spaces on the ground floor and residential on the first floor (5 flats), to be replaced with a 3.5 storey building comprising 20 residential units including landscaping, refuse storage, cycle storage and other associated infrastructure. The ground floor will provide 6 flats, bin store and a small cycle store; the first and second floors will have 6 flats each, and the third floor will have 2 flats that will be set within the roof-scape. All flats will be accessed from a central core staircase and lift. The flats are comprised of fourteen 1-bedroom flats, and six 2-bedroom flats. For further details on the internal spaces of these flats, see the Planning Assessment section below. 2. Pedestrian access to the building is proposed from the footway along Holdenhurst Road with a separate access to a larger cycle store to the rear. No vehicular access is proposed as the development would be a car free scheme. 3. The proposal has been revised from the original scheme of 26 flats to the current layout of 20 flats to address concerns raised by the consultees.
Description of Site and Surroundings 4. The site is located to the southern side of Holdenhurst Road near its junction with Jefferson Avenue. It currently comprises of two detached properties that were originally constructed as pairs of semi-detached villas (426 – 428 and 430 – 432 Holdenhurst Road); both with office spaces on the ground floor and residential uses on the first floor and forming part of a row of matching two storey properties, lining one side of the street. The existing buildings include brick finishes of red and buff colours and bay features set within forward projecting twin gables at the first-floor level. All properties along this row include single storey front extensions, built out to the line of the former front gardens’ boundary walls, to facilitate the conversion of ground floor into commercial use. There is also a regular gap between properties along this row that help in maintaining rhythm for the street and contribute to the local context.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Eastern BCP Planning Committee at Bournemouth, Christchurch and Poole and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.