RESOLVED 1. That virements of £125,000 and £30,000 from The Look Out Car Parking and Easthampstead Park Fire Safety Works capital budgets respectively be approved in order to complete the funding for a new car park and access road at Easthampstead Park with an estimated cost of £270,000. 2. That in order to enhance the overall quality of the facility, the proposed new car park as detailed in the Director of Environment & Leisure’s report be approved.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
3.1The justification for a new car park is detailed within the report.
3.2Financial regulations require Executive approval for the virement of capital budgets necessary to complete this project.
Alternative options considered
4.1Clearly doing nothing is an option, however the desired improvements outlined in this report would not be addressed.
4.2There is an option to provide the new access road and approximately half the new car park and improved lighting to the car park adjacent to the workshops for an estimated cost of £155,000. This would require virement of £40,000. However this would not address the quality/safety improvements for the existing tennis court car park and possibly the main driveway, outlined in this report.
5 SUPPORTING INFORMATION
Case for improved and expanded car parking provision
5.1The case for a new car park is driven by a wish to improve capacity, quality and safety. If these issues are not resolved, there is a real risk that the significant improvement in the financial performance of the site achieved in the past three years, since the management of the conference centre was taken back in house, will be jeopardised. There is thus also a financial justification for the proposal. The location of the site is such that the vast majority of staff and customers will need to park a car. Note that as well as the conference centre there is an Education Support Centre, corporate training facility and Registrars located on the site.
Financial Justification
5.2In financial year 2001/02, which was the first year of direct operation by BFBC, the conference centre recorded a small loss on operating costs, while the budgeted surplus in 2006/07, excluding recharges and capital financing is £246,000 on a turnover, excluding VAT, of approximately £1.7m. Day delegate use at the conference centre alone has risen from 25,623 in 2001/02 to 35,394 in 2005/06. To put the proposal into perspective, at a conference centre normal day delegate rate of £45, the estimated capital financing charges for this proposal equate to approximately 533 day delegate visits over a year. It should also be noted that the Education Centre and Registrar’s generate annual income of around £117,000 and £21,000 respectively.
Capacity Issues
5.3For a number of years the former disused tennis courts at Easthampstead Park have been used as an overflow car park. Due to increased usage of the site by the Education Centre, Corporate Services Training and the Registrars, in addition to increased conference centre patronage, this area is now used on a regular, rather than overflow basis. It is estimated to provide space for perhaps 60 cars. However how people choose to park significantly effects the capacity. Despite this higher utilisation the main drive way to the house is also used extensively for parking. It is not unusual to have over 40 cars parked down the main drive way.
5.4Thus at present the only marked and designated car parking is immediately in front of the main entrance and in the car park located next to the workshop buildings. This provides for approximately 110 marked bays including those designated for disabled use. When the site is busy, management estimate that there could be approximately 350 people on site. Thus there is a significant capacity issue to address.
Safety Improvements
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.