That the outturn capital expenditure and, in particular, the key variances identified in section 5.5 of the report be noted and the carry forward of £7.814m from the 2005/06 capital programme to 2006/07 be approved. 2. That the financing of capital expenditure as shown in Table 3 be noted. 3. That expenditure of up to £0.04m for demolition works on empty properties be approved in advance of the capital receipt from the sale of the land.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
2.1That the outturn capital expenditure and, in particular, the key variances identified in section 5.5 of the report be noted and the carry forward of £7.814m from the 2005/06 capital programme to 2006/07 be approved.
2.2That the financing of capital expenditure as shown in Table 3 be noted.
2.3That expenditure of up to £0.04m for demolition works on empty properties be approved in advance of the capital receipt from the sale of the land.
Reasons for recommendations
3.1The reasons for the recommendations are set out in section 5 below.
Alternative options considered
4.1Not Applicable
5 SUPPORTING INFORMATION
Outturn Capital Expenditure
5.1The capital programme for 2005/06 consisted of £26.8m on projects and programmes determined by Service Departments. The projected outturn is £18.8m (70% of approved expenditure) which is consistent with performance in previous years. These figures remain subject to change, pending external audit. However, no significant movement is anticipated.
5.2Many of the schemes included in the capital programme are both technically and logistically complex to implement. Issues such as planning approvals, land transfers and inclement weather can all lead to unavoidable delays. In addition, their financial scale requires a lengthy tender process to ensure the best price is obtained prior to letting the works contract. It is therefore extremely difficult to complete such schemes within the financial year in which they are approved, with the result being an apparent low level of expenditure against budget.
5.3Table 1 summarises the outturn position for schemes managed by Service Departments based on latest information available. The detailed monitoring sheets are provided at Annexes A-D.
Table 1: Capital outturn for each Service Annexe Service Approved Estimated Carry (Under) budget Outturn forward /Over spend * £’000 £’000 £’000 £’000 A Corporate Services & 2,190 1,534 671 15 Resources A Chief Executive’s office 794 640 153 (1) B Education Children’s 8,471 5,199 3,229 (42) Services & Libraries C Environment & Leisure 9,858 6,839 2,880 4 D Social Service & Housing 1,272 1,047 235 10 D Housing Improvement 3,791 3,305 490 4 Schemes SUBTOTAL 26,376 18,564 7,658 (10) D Improvement Grants 420 264 156 Total Capital Programme 26,796 18,828 7,814 (10) % spent 70% * excludes underspends on S106 schemes
5.4The total carry forwards requested by Service Departments amount to £7.8m This is mainly due to unforeseen circumstances that have resulted in expenditure on planned programmes falling into the current year. Many of the projects have been completed since 31 March or are contractually committed and underway. Out of a total of 207 schemes, 45% were fully completed by the end of the year. The remaining projects were on site or had started. Those schemes for which there was no spend and not started are marked with an asterisk in Annexes A-D. The major projects for which funding is required to be carried forward to 2006/07 are outlined in Annexe E.
5.5According to financial regulations, departments are required to manage their budgets to ensure that the overall department capital programme is not exceeded. As can be seen above the overall the capital programme is underspent against budget and there have been some significant overspends and underspends which are required to be drawn to the attention of Members (>£25,000). The key budget variances are detailed below.
Corporate Services & Resources
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.