Bracknell Forest Council
Executive, Tuesday 13 February 2007 at 5.00pm

Capital Programme 2007/08 - 2009/10

Decided Executive 2 papers

Executive decided this item on Tuesday 13 February 2007. Below is the council's own wording, with the papers it was decided on.

Item234d

Resolved

RESOLVED 1. That General Fund capital funding of £8.010m for 2007/08 be recommended in respect of those schemes listed in Annexes A-E of the Director’s report. 2. That the inclusion of an additional budget of £1m for ‘Invest To Save’ schemes, based on the underlying principles set out in paragraph 5.5, be recommended. 3. That Council Housing Revenue Account capital funding of £5.500m for 2007/08 be recommended in respect of those schemes listed in Annex F. 1. That those schemes that attract external grant funding be recommended for inclusion within the 2007/08 capital programme at the level of funding received. 2. That the release of £1.535m from section 106 monies to fund capital projects outlined in paragraph 5.16 be recommended. 3. That capital schemes that require external funding only proceed once the Council is certain of receiving the grant. 4. That the indicative programme for 2008/09 and 2009/10 be reviewed in the light of resources available and spending priorities in December 2007.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Executive

Recommendations

2.1That General Fund capital funding of £8.010m for 2007/08 be recommended in respect of those schemes listed in Annexes A-E.

2.2That the inclusion of an additional budget of £1m for ‘Invest To Save’ schemes, based on the underlying principles set out in paragraph 5.5, be recommended.

2.3That Council Housing Revenue Account capital funding of £5.500m for 2007/08 be recommended in respect of those schemes listed in Annex F.

2.4That those schemes that attract external grant funding be recommended for inclusion within the 2007/08 capital programme at the level of funding received.

2.5That the release of £1.535m from s106 monies to fund capital projects outlined in paragraph 5.16 be recommended.

2.6That capital schemes that require external funding only proceed once the Council is certain of receiving the grant.

2.7That the indicative programme for 2008/09 and 2009/10 be reviewed in the light of resources available and spending priorities in December 2007.

Reasons for recommendations

3.1The reasons for the recommendation are set out in the report. 4 ALTERNATIVE OPTIONS CONSIDERED

4.1The alternative options are considered in the report below.

5 SUPPORTING INFORMATION

Capital Resources

5.1Each year the Council agrees a programme of capital schemes. In the past these schemes have been funded from three main sources:

• The Council’s accumulated capital receipts • Government Grants • Other external contributions

5.2The Local Government Act 2003 brought in radical changes to the financing of capital expenditure including the “pooling” of housing capital receipts from 1 April 2004. From that date, the Government no longer issues borrowing approvals. Instead, under a new “prudential framework”, Councils can set their own borrowing limits based on the affordability of the debt.

5.3The Council’s estimated total usable capital receipts at 31 March 2007 are zero. The impact of the Thames Basin Heath Special Protection area has meant that the opportunity to dispose of Council property and generate further capital receipts has been severely curtailed over the last year. Even with a robust mitigation strategy in place, it may be some time before the Council is able to realise further capital receipts from the disposal of assets. The proposed capital programme for 2007/08 has been developed, therefore, on the assumption that it will be funded by a combination of Government grants, other external contributions and some borrowing, but not capital receipts. The financing cost associated with the General Fund Capital Programme has been provided for in the Council’s revenue budget plans which appear later on tonight’s agenda.

5.4In addition to the above, £3.385m will be available from the Major Repairs Allowance, together with the remaining capital receipts (£2.115m) arising from the transitional arrangements associated with the “pooling” regime, which are earmarked for investment in the Council’s own housing stock. The total Housing Improvement Programme for 2007/08 is, therefore, £5.500m.

Capital Programme Proposals 2007/08 – 2009/10

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme 2007/08: 2009/10Report 61 KB DownloadRead as text
PDF
Capital Programme AnnexesAppendix 25 KB Download

At this meeting

Whole meeting

Who was there

7 of 7 attended
PB
Councillor Paul Bettison OBE CONChair, present
AW
Alan Ward CONVice-Chair, present
DB
Councillor Dale Birch CONCommittee Member, present
MM
Councillor Mrs Mary Ballin CONCommittee Member, present
GB
Councillor Gareth Barnard CONCommittee Member, present
IM
Iain McCracken CONCommittee Member, present
PN
Peter North CONCommittee Member, present

On this subject at Bracknell Forest

Search all
  1. Capital Programme 2007/08 - 2009/10This decision
  2. Highways and Transport Capital Programme 2026/27Approved
  3. Capital Programme 2026/27Approved
  4. Highways and Transport Capital Programme 2025/26Approved
  5. Capital Programme 2025/26Approved
  6. Highways and Transport Capital Programme 2024/25Approved

More from Bracknell Forest Executive

All decisions
MeetingDecisionOutcome
17 Sep 2024 Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... Noted Open
17 Sep 2024 Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... Agreed Open
17 Sep 2024 Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. Approved Open
17 Sep 2024 Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... Noted Open
17 Sep 2024 Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies