AI summaryCabinet approved for consultation a £8.051m council funded capital programme for 2026/27, plus £4.779m of externally funded schemes and £1m for Invest-to-Save projects, and agreed to repurpose £401,666 of housing budgets to buy temporary accommodation.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedFour-part capital programme package agreed
Money£8.051m council funded, £4.779m externalPlus £1m Invest-to-Save; £401,666 virement
What happens nextPublic consultation 17 December 2025 to 27 January 2026Council decision due 25 February 2026
Who it affectsCouncil services and borough residentsIncludes housing, schools, highways and property
What was decided
Cabinet approved, for consultation, a council funded capital programme of £8.051m for 2026/27, including new schemes listed in Annexes B to D. Report 3.1, 6.19
Cabinet approved, for consultation, £4.779m of externally funded expenditure, including £0.760m of S106 funding. Report 3.2, 6.20
Cabinet approved, for consultation, an additional £1m budget for Invest-to-Save schemes, and the virement of unspent housing budgets to acquire new temporary housing accommodation. Report 3.3, 3.4, 6.27, 6.28
Why
Capital and revenue resources are under pressure, so only the highest priority schemes and programmes have been recommended. Report 2.1, 6.4
The housing market has changed since the original housing transfer budget was set, and previous initiatives have run their course, making temporary accommodation a better use of remaining funds. Report 6.27, 6.28
Invest-to-Save schemes are included because they generate revenue or savings that exceed the council's borrowing costs. Report 6.16
What happens next
The proposals go to consultation from 17 December 2025 to 27 January 2026, with the Overview and Scrutiny Commission, business rate payers, Schools Forum, town and parish councils and voluntary organisations all invited to comment. Report 7.3
Cabinet will consider consultation responses on 10 February 2026, and Full Council will consider the budget proposals on 25 February 2026, alongside prudential indicators for 2026/27 to 2028/29. Report 6.25, 7.3
A review of commercial assets is underway and may produce further capital receipts to reduce borrowing costs; progress will be reviewed in the coming months. Report 6.22
The money
£8.051m Council funded capital programme for 2026/27 Report 3.1, 6.19
£4.779m Externally funded expenditure in 2026/27 Report 3.2, 6.20
£0.760m Section 106 funding within external total Report 3.2, 6.20
£1m Additional budget for Invest-to-Save schemes Report 3.3, 6.16
£2.400m Schemes already committed in 2025/26 and continuing Report 6.5, 6.19
£0.529m Rolling programme investment Report 6.6
£1.455m Property maintenance capital budget Report 6.7
200,000 Revenue allowance for non-capitalisable property works Report 6.8
£1.44m Schools capital maintenance allocation received in 2025/26 Report 6.11
£401,666 Unspent housing budget to be vired into temporary accommodation purchases Report 6.28, 6.29
between £160,000 and £180,000 Estimated cost per one-bedroom temporary housing unit Report 6.28
Options considered
Chosen: Approve £8.051m council funded capital programme for consultation. Reflects prioritised schemes after departmental evaluation under the asset management plan approach Report 3.1, 6.4
Chosen: Include £4.779m of externally funded schemes. Government grants and S106 contributions are available for specific projects Report 3.2, 6.20
Chosen: Add £1m for Invest-to-Save schemes. Schemes under £400,000 are reviewed by the corporate management team and must generate revenue or savings exceeding borrowing costs Report 3.3, 6.16
Chosen: Vire unspent housing budgets of £401,666 to acquire temporary housing. Buying one-bedroom properties would reduce reliance on nightly paid temporary accommodation Report 3.4, 6.27, 6.28
Rejected: Defer or substitute alternative options. Final budget proposals will consider any alternative options raised during the required consultation period Report 5.1
Implications
Financial: Council cash reserves are no longer available for internal borrowing, so capital expenditure above projected receipts will attract interest charges and Minimum Revenue Provision costs. Report 6.21, 6.24
Financial: Current PWLB long-term rates are circa 4.5 to 4.8 percent, reflecting market conditions rather than the Bank of England base rate of 4.00 percent. Report 3.1, 6.23
Risk: Delays to the capital programme could affect services provided by the council. Report 7.5
Equalities: An equalities impact assessment has not been completed for this report. Report 7.4
Climate: A number of schemes in the capital programme have specific objectives to address climate change and reduce CO2 emissions. Report 7.6
Legal: Controls on capital expenditure are contained in the Local Government Act 2003 and related regulations, and the programme is within CIPFA Prudential Code guidelines subject to Full Council approval of prudential indicators. Report 6.25, 7.1
Staffing: Capital investment in IT hardware and infrastructure will require £60k of annual revenue costs for maintenance and licences. Report 6.17
Who and where
Residents needing temporary housing, including single individuals and single parents with young children Report 6.28
Schools and pupils (planned maintenance funded from condition surveys) Report 6.11
Users of the council's housing stock used for homelessness and welfare priorities Report 6.12, 6.13
Users of council commercial, leisure and corporate buildings subject to maintenance works Report 6.7
Business rate payers, the Schools Forum, town and parish councils and voluntary organisations invited to comment during consultation Report 7.3
Timeline
16 December 2025: Cabinet agrees proposals as basis for consultation Report 7.3
17 December 2025 to 27 January 2026: Budget consultation period Report 7.3
10 February 2026: Cabinet considers representations made and recommends budget Report 7.3
25 February 2026: Council considers Cabinet budget proposals Report 7.3
2026/27: Delivery year for the £8.051m council funded programme Report 3.1, 6.19
Plain English for the jargon
Capital programme: The council's planned spending on building and maintaining assets such as buildings, roads and equipment, as opposed to day-to-day running costs.
S106: Section 106 of the Town and Country Planning Act 1990, under which developers contribute to the cost of facilities and infrastructure needed because of their development.
CIL: Community Infrastructure Levy, a charge that local authorities can levy on new development to fund infrastructure.
Invest-to-Save: Capital spending on projects that generate revenue or savings exceeding the cost of borrowing to fund them.
Virement: Moving budget from one purpose to another within the same year's capital programme, permitted under the council's capital financial regulations.
MRP: Minimum Revenue Provision, the amount councils must set aside from revenue each year to repay capital borrowing.
PWLB: Public Works Loan Board, a government body that lends money to local authorities for capital projects.
Prudential Code: CIPFA's framework requiring local authorities to set indicators showing that capital investment is affordable, prudent and sustainable.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item50
Resolved
RESOLVED that the cabinet: I. Approves, for consultation, a council funded capital programme of £8.051m for 2026/27 as set out in paragraph 6.19 and summarised in Annex A, including the new schemes listed in Annexes B – D. II. Approves, for consultation, the inclusion of £4.779m of expenditure to be externally funded (including £0.760m of S106 funding) as outlined in paragraph 6.20. III. Approves, for consultation, the inclusion of an additional budget of £1m for Invest-to-Save schemes. IV. Approves the virement of unspent budgets within the housing programme to support the acquisition of new temporary housing accommodation as set out in paragraph 6.27.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1.1Under the council’s constitution, the cabinet is required to consult on its detailed budget proposals with the council’s overview and scrutiny commission and any other interested parties or individuals for a period of at least six weeks. This report summarises the current position on the council’s capital programme budget preparations for 2026/27.
1.2This report brings together all service area proposals to help the cabinet prepare a capital programme for 2026/27 through 2028/29. While it mainly focuses on 2026/27, it also takes future years into account. The financial effects of these suggestions are covered in the draft revenue budget report. Any updates to the service proposals will be included in that report, which will be released for public consultation after the cabinet meeting.
2. Cabinet Member for Economic Development and Regeneration
2.1The capital programme proposals in this report constitute an important part of the budget preparations and set out how we will build and maintain facilities and infrastructure within our borough in the coming years. We know that resources are under strain, so are proposing a carefully prioritised capital programme, with consideration given to the impact of capital funding decisions on the revenue budget. The proposals in this report will be consulted on alongside the revenue budget proposals in the timeline detailed in the report.
Recommendations
That the cabinet:
3.1Approves, for consultation, a council funded capital programme of £8.051m for 2026/27 as set out in paragraph 6.19 and summarised in Annex A, including the new schemes listed in Annexes B – D.
3.2Approves, for consultation, the inclusion of £4.779m of expenditure to be externally funded (including £0.760m of S106 funding) as outlined in paragraph 6.20.
3.3Approves, for consultation, the inclusion of an additional budget of £1m for Invest-to- Save schemes.
3.4Approves the virement of unspent budgets within the housing programme to support the acquisition of new temporary housing accommodation as set out in paragraph 6.27.
Reasons for recommendations
4.1The reasons for the recommendations are set out in the report.
BFC - CONFIDENTIAL BFC - CONFIDENTIAL
Alternative options considered
5.1The final budget proposals will include consideration of any alternative options highlighted during the required consultation period.
6. Supporting Information
Capital Resources 6.1 Each year the council agrees a programme of capital schemes. These schemes are funded from these main sources:
• the council’s capital receipts (asset sales) • Government grants • other external contributions • internal and external borrowing
6.2The council’s total usable capital receipts generated from disposing of assets at 31st March 2025 are zero as all receipts have been applied to fund prior capital investment. Similarly, all receipts realised during the current financial year will be used to finance the 2025/26 capital programme and the flexible use of capital receipts programme. The council is partly reliant on capital receipts and other contributions to fund its capital programme, although interest generated from capital receipts can also help support the revenue budget in the short term. However, with borrowing rates remaining at relatively high levels it is advantageous to use capital receipts to reduce the level of external borrowing.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report - Q1RESOLVED that Cabinet: · NOTES the performance of the council over the period from April to June 2026, highlighted in...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.