RESOLVED 1. That the outturn capital expenditure and, in particular, the key variances identified in section 5.6 of the Director of Corporate Services’ report be approved. 2. That the carry forward of £8.599m from the 2006/07 capital programme to 2007/08 including £0.200m relating to traffic modelling be approved. 3. That the financing of capital expenditure as shown in Table 3 of the Director of Corporate Services’ report be noted.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
2.1That the outturn capital expenditure and, in particular, the key variances identified in section 5.6 be approved.
2.2That the carry forward of £8.599m from the 2006/07 capital programme to 2007/08 including £0.200m relating to traffic modelling be approved.
2.3That the financing of capital expenditure as shown in Table 3 be noted.
Reasons for recommendations
3.1The reasons for the recommendations are set out in section 5 below.
Alternative options considered
4.1Not Applicable
5 SUPPORTING INFORMATION
Outturn Capital Expenditure
5.1The capital programme for 2005/06 consisted of £26.8m on projects and programmes determined by Service Departments. The projected outturn is £18.6m (69% of approved expenditure) which is consistent with performance in previous years. These figures remain subject to change, pending external audit. However, no significant movement is anticipated. The capital programme is monitored on a monthly basis by officer and reported formally to Corporate Management Team on a quarterly basis and through to Executive Members in the Quarterly Operations Reports.
5.2The published capital budget is based on scheme approvals and it does not reflect the anticipated cash flow. However the revenue budget does make allowance for this cash flow in the calculation of interest. This inconsistent presentation leads to the wrong assumption the Council is not delivering the capital programme. Over past years all schemes have been completed and there have been few over/under spends on capital schemes. Many of the capital schemes are both technically and logistically complex to implement. Issues such as planning approvals, land transfers and inclement weather can all lead to unavoidable delays. In addition, their financial scale requires a lengthy tender process to ensure the best price is obtained prior to letting the works contract. It is therefore extremely difficult to complete such schemes within the financial year in which they are approved, with the result being an apparent low level of expenditure against budget. To enable more realistic budget monitoring, the Borough Treasurer will convert the 2007/08 -2009/10 capital programme into a cash flow forecast. No changes will be made to the individual scheme costs. These figures will be incorporated into the first QOR in 2007/08.
5.3Table 1 summarises the outturn position for schemes managed by Service Departments based on latest information available. The detailed monitoring sheets are provided at Annexes A-D.
Table 1: Capital outturn for each Service Annexe Service Approved Estimated Carry (Under) budget Outturn forward /Over spend £’000 £’000 £’000 £’000 A Corporate Services 1,853 1,143 743 33 A Chief Executive’s office 374 199 175 0 B Education Children’s 7,573 3,953 3,634 14 Services & Libraries C Environment & Leisure 8,591 6,192 2,246 (153) D Social Service & Housing 1,507 971 761 224 D Housing Improvement 6,143 5,316 840 13 Schemes Capitalisation of revenue 800 811 200 211 Total Capital Programme 26,841 18,584 8,599 342 % spent 69%
5.4The total carry forwards requested by Service Departments amount to £8.4m This is mainly due to unforeseen circumstances that have resulted in expenditure on planned programmes falling into the current year. Many of the projects have been completed since 31 March or are contractually committed and underway. Out of a total of 198 schemes, 30% were fully completed by the end of the year. The remaining projects were on site or had started.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.