Resolved
RESOLVED that progress made in the areas of the Engineering Procurement Construction (EPC) Contract and Planning since the last meeting on 5 September 2007 be noted.
Joint Waste Disposal Board noted this item on Wednesday 12 December 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that progress made in the areas of the Engineering Procurement Construction (EPC) Contract and Planning since the last meeting on 5 September 2007 be noted.
The EPC Contractor is maintaining programme anticipating the completion of the Phase 1 works by the end of November currently showing a penetration in to the buffer by 20 days.
All subcontracts for the Phase 1 works have been placed and have been given commencement dates for their works in line with the current programme to complete.
1 HEALTH SAFETY & ENVIRONMENTAL
There have been no reportable accidents in the period.
ACCIDENT and INCIDENT RECORD In Period To date Reportable 0 0 Non reportable 2 2 Near Misses 13 176
Total Site Man Hours to date without a Lost Time Accident (LTA) 81’400 No dangerous occurrences in the period
We have had 2 no non reportable incidents in the period being minor cuts, the JV has taken action with the subcontractor in question to emphasise the need to be fully complaint in the wearing of gloves and the importance of a risk assessment thought process and have carried out toolbox talks with all employees.
Take time Near misses and suggestions are being monitored on a weekly basis and to date no apparent trend is occurring
A environmental incident report and conclusion have bee carried out by the JV to close out the incident involved in routing the main water supply to site by Clugstons Environmental manager.
1 DESIGN
2.1Smallmead
This period has seen the completion of the phase 1 external works and the continuation of the electrical and mechanical works.
Overall progress is summarised below:
• Design of the phase 1 external works, including barriers, fencing, signage and landscaping have been completed. • Design and detailing of the reinforced concrete works to the MRF area has continued, with all reinforced concrete works up to gridline 19 complete. • Outline design of the office steelwork has been completed and detailed design of the steelwork is now underway. • The internal road layout for the HWRC has been completed. Central Berks Waste PFI Project Date of Issue: 2.11.07 Progress Report 11 Page No: 4 of 7
• Building Services design has continued for the phase 1 works and is largely complete. Design of the ventilation system to the HWRC mess facility has been completed. • A Phase 1 commissioning plan has be developed and submitted to RE3. • The preparation of the Health and Safety File and O&M manuals has continued.
MRF A HAZOP has been arranged for 5/6th November when a detailed review of the hazards in operation will be carried out.
2.2Longshot
Work has commenced on the preparation of information required to gain discharge of the relevant planning conditions required, to enable works to commence in-line with the contract programme. An order has been issued for the additional site investigation works required with the timings and exact position of the works to be agreed with RE3.
3 CONSTRUCTION, PROCUREMENT - COMMISSIONING AND OPERATION
3.1Construction
Phase 1 – Main Site
Works are progressing to programme for the main phase one works to be complete for the end of November 2007 to allow a period for any snagging works to be carried out prior to the date given for the HWRC/TS to be fully operational.
Works remaining are as follows :
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Attachment to EPC reportReport | 103 KB | DownloadRead as text |
PDF |
Engineering Procurement Construction (EPC), Planning and Licensing ReportReport | 54 KB | Download |
Follow Joint Waste Disposal Board at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Jun 2026 | Election of ChairRESOLVED that Councillor Finn McGoldrick be elected Chair of the Board for the municipal year 2026/27. | Decided | Open |
| 11 Jun 2026 | Election of Vice-ChairRESOLVED that Councillor Stephen Newton be elected Vice-Chair of the Board for the municipal year 2026/27. | Decided | Open |
| 11 Jun 2026 | re3 Progress ReportRESOLVED that 1 the contents of this report be noted. 2 a proposal on the simplification of the DIY charging structur... | Noted | Open |
| 11 Jun 2026 | re3 Strategy ReportRESOLVED that 1 the re3 Strategy 2026–2031 be approved and progressed through each partner council’s decision-making ... | Approved | Open |
| 11 Jun 2026 | re3 Finance Report - part oneRESOLVED that the year end financial position for FY25/26 be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.