CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bracknell Forest Council
Joint Waste Disposal Board, Wednesday 12 December 2007 at 6.00pm

Engineering Procurement Construction (EPC), Planning and Licensing Report

Noted Committee 2 papers

Joint Waste Disposal Board noted this item on Wednesday 12 December 2007. Below is the council's own wording, with the papers it was decided on.

Item16

Resolved

RESOLVED that progress made in the areas of the Engineering Procurement Construction (EPC) Contract and Planning since the last meeting on 5 September 2007 be noted.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Joint Waste Disposal Board

Summary

The EPC Contractor is maintaining programme anticipating the completion of the Phase 1 works by the end of November currently showing a penetration in to the buffer by 20 days.

All subcontracts for the Phase 1 works have been placed and have been given commencement dates for their works in line with the current programme to complete.

1 HEALTH SAFETY & ENVIRONMENTAL

There have been no reportable accidents in the period.

ACCIDENT and INCIDENT RECORD In Period To date Reportable 0 0 Non reportable 2 2 Near Misses 13 176

Total Site Man Hours to date without a Lost Time Accident (LTA) 81’400 No dangerous occurrences in the period

We have had 2 no non reportable incidents in the period being minor cuts, the JV has taken action with the subcontractor in question to emphasise the need to be fully complaint in the wearing of gloves and the importance of a risk assessment thought process and have carried out toolbox talks with all employees.

Take time Near misses and suggestions are being monitored on a weekly basis and to date no apparent trend is occurring

A environmental incident report and conclusion have bee carried out by the JV to close out the incident involved in routing the main water supply to site by Clugstons Environmental manager.

1 DESIGN

2.1Smallmead

This period has seen the completion of the phase 1 external works and the continuation of the electrical and mechanical works.

Overall progress is summarised below:

• Design of the phase 1 external works, including barriers, fencing, signage and landscaping have been completed. • Design and detailing of the reinforced concrete works to the MRF area has continued, with all reinforced concrete works up to gridline 19 complete. • Outline design of the office steelwork has been completed and detailed design of the steelwork is now underway. • The internal road layout for the HWRC has been completed. Central Berks Waste PFI Project Date of Issue: 2.11.07 Progress Report 11 Page No: 4 of 7

• Building Services design has continued for the phase 1 works and is largely complete. Design of the ventilation system to the HWRC mess facility has been completed. • A Phase 1 commissioning plan has be developed and submitted to RE3. • The preparation of the Health and Safety File and O&M manuals has continued.

MRF A HAZOP has been arranged for 5/6th November when a detailed review of the hazards in operation will be carried out.

2.2Longshot

Work has commenced on the preparation of information required to gain discharge of the relevant planning conditions required, to enable works to commence in-line with the contract programme. An order has been issued for the additional site investigation works required with the timings and exact position of the works to be agreed with RE3.

3 CONSTRUCTION, PROCUREMENT - COMMISSIONING AND OPERATION

3.1Construction

Phase 1 – Main Site

Works are progressing to programme for the main phase one works to be complete for the end of November 2007 to allow a period for any snagging works to be carried out prior to the date given for the HWRC/TS to be fully operational.

Works remaining are as follows :

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Attachment to EPC reportReport 103 KB DownloadRead as text
PDF
Engineering Procurement Construction (EPC), Planning and Licensing ReportReport 54 KB Download

At this meeting

Whole meeting

Who was there

5 of 6 attended
MM
Councillor Mrs Mary Ballin CONCommittee Member, present
RS
Councillor Rob StantonCommittee Member, present
SW
Steve WaiteCommittee Member, present
SW
Councillor Simon WeeksCommittee Member, present
DH
Councillor Dorothy Hayes CONCommittee Member, present
BT
Mrs Bet TicknerCommittee Member, apologies

On this subject at Bracknell Forest

Search all
  1. Engineering Procurement Construction (EPC), Planning and Licensing ReportThis decision
  2. Engineering Procurement Construction (EPC) and Planning - Monthly Report 18 May 2008Noted
  3. Engineering Procurement Construction (EPC) Planning and Licensing ReportNoted

More from Bracknell Forest Joint Waste Disposal Board

All decisions
MeetingDecisionOutcome
11 Jun 2026 Election of ChairRESOLVED that Councillor Finn McGoldrick be elected Chair of the Board for the municipal year 2026/27. Decided Open
11 Jun 2026 Election of Vice-ChairRESOLVED that Councillor Stephen Newton be elected Vice-Chair of the Board for the municipal year 2026/27. Decided Open
11 Jun 2026 re3 Progress ReportRESOLVED that 1 the contents of this report be noted. 2 a proposal on the simplification of the DIY charging structur... Noted Open
11 Jun 2026 re3 Strategy ReportRESOLVED that 1 the re3 Strategy 2026–2031 be approved and progressed through each partner council’s decision-making ... Approved Open
11 Jun 2026 re3 Finance Report - part oneRESOLVED that the year end financial position for FY25/26 be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies