Resolved
RESOLVED that Members noted progress made in the areas of the EPC Contract and Planning since the last meeting on 19 March 2008 .
Joint Waste Disposal Board noted this item on Wednesday 25 June 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that Members noted progress made in the areas of the EPC Contract and Planning since the last meeting on 19 March 2008 .
Works are progressing in line with the contract programme for the Smallmead Phase 1A area and the Phase 2 area of site.
All Civil works within the building footprint up to grid line 19 are complete. The area grid lines 16-19 have now been handed over to OKLM on the 2.4.08 who have commenced works with delivery /installation of the MRF Plant, other trades within the building are Tyco and MTL.
The office block Brickwork/Cladding is now complete with exception to snagging works, works are progressing with M&E, Screeding, window/curtain walling installation, fire protection and finishes.
The external weighbridges have been handed over to RE3 with only some minor snagging items remaining.
External infrastructure and hard standing areas are almost complete and works are progressing with the preparation of the main car park for surfacing and associated footways and paved areas.
Longshot
Demolition works are now complete and reduced level excavation works ongoing, civils works are progressing in line with the programme for the office Block/ Transfer Station.
Erection of the structural frame to the office block is to commence on the 4th June 2008.
1 HEALTH SAFETY & ENVIRONMENTAL
There have been no reportable accidents in the period.
ACCIDENT and INCIDENT RECORD In Period To date Reportable 0 0 Non reportable 0 3 Near Misses 5 209
Total Site Man Hours to date without a Lost Time Accident (LTA) 158,603 No dangerous occurrences in the period.
A lifting incident occurred on the 27 May 2008, which is currently under review.
2 DESIGN
2.1Smallmead
This period has seen the continuation of the phase 2 civil works.
Overall progress is summarised below Central Berks Waste PFI Project Date of Issue: 2.6.08 Progress Report 18 Page No: 4 of 7
• Design of the office electrical layouts has now been completed. • Detailed design of the office Heating and Ventilation system has now been completed. • Detailed design of the office fire detection and protection systems have been completed. • Detailed design of the office/visitors centre has continued. • Design of the external works to the office block has been completed. Samples of the proposed paving are to be submitted and agreed RE3.
MRF – Key summary
Installation of the plant is progressing with the majority of the components having been delivered to site. Site electrical installation work to the MRF equipment to commence in June.
Subcontract progress meetings with OKLM/Re3 continue to be held on a monthly basis. A SCADA review with Re3 was held at the manufacturers offices (RMR) in the period
Longshot
Longshot construction works has got off to a good start, civils works are complete to the office block to take the erection of the structural frame. The transfer gas membrane works are complete and works are progressing to programme for the floor slab and pushwalls.
Overall progress is summarised below:
• Detailed design of the office cladding has been completed.
• Office architectural details including the window/door schedules have been completed.
• Detailed design of the office masonry details is nearing completion
• Preliminary design of the office H&V system has been carried out.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
18- May 08 Monthly ReportReport | 106 KB | DownloadRead as text |
PDF |
Engineering Procurement Construction (EPC) and Planning: Monthly Report 18 May 2008Report | 50 KB | Download |
Follow Joint Waste Disposal Board at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Jun 2026 | Election of ChairRESOLVED that Councillor Finn McGoldrick be elected Chair of the Board for the municipal year 2026/27. | Decided | Open |
| 11 Jun 2026 | Election of Vice-ChairRESOLVED that Councillor Stephen Newton be elected Vice-Chair of the Board for the municipal year 2026/27. | Decided | Open |
| 11 Jun 2026 | re3 Progress ReportRESOLVED that 1 the contents of this report be noted. 2 a proposal on the simplification of the DIY charging structur... | Noted | Open |
| 11 Jun 2026 | re3 Strategy ReportRESOLVED that 1 the re3 Strategy 2026–2031 be approved and progressed through each partner council’s decision-making ... | Approved | Open |
| 11 Jun 2026 | re3 Finance Report - part oneRESOLVED that the year end financial position for FY25/26 be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.