RESOLVED that 1. the virements requested by departments as set out in paragraph 5.1 of the report of the Director of Corporate Services be approved. 2. the outturn capital expenditure and in particular the key variances identified in section 5.6 of the report of the Director of Corporate Services be noted. 3. the carry forward of £13.441m from the 2008/09 capital programme to 2009/10 including £2.423m relating to projects approved in 2007/08 be approved. 4. the financing of capital expenditure as shown in table 2 of the report of the Director of Corporate Services be noted.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
a) Approves the virements requested by departments (see paragraph 5.1); b) Notes the outturn capital expenditure and in particular the key variances identified in section 5.6. c) Approves the carry forward of £13.441m from the 2008/09 capital programme to 2009/10 including £2.423m relating to projects approved in 2007/08 (see paragraph 5.7). d) Notes the financing of capital expenditure as shown in Table 2.
Reasons for recommendations
3.1The reasons for the recommendations are set out in section 5 below.
Alternative options considered
4.1Not Applicable.
5 SUPPORTING INFORMATION
Virements
5.1The following virements have been requested and are reflected in the capital outturn:
• A budget transfer of £37,400 from Social Care and Learning to Environment, Culture and Communities for the planned maintenance of libraries. This is to reflect the changes in responsibilities following the Council reorganisation.
• A transfer of £5,100 from Corporate Services to Environment, Culture and Communities for capital fees. The capital programme for Corporate Services assumed that £100,000 of IT salaries would be capitalised in support of capital schemes. An element of the actual salaries capitalised related to an Environment scheme and therefore the budget has been transferred to match this expenditure.
Outturn Capital Expenditure
5.2The capital programme for 2008/09 consisted of £32.699m on projects and programmes. The projected outturn is £19.184m (59% of approved expenditure) which is consistent with performance in previous years. These figures remain subject to change, pending external audit. However, no significant movement is anticipated. The capital programme is monitored on a monthly basis by officers and reported formally to the Corporate Management Team on a quarterly basis and through to Members in the Performance Monitoring Reports.
5.3The published capital budget is based on scheme approvals and does not reflect the anticipated cash flow. As part of the capital monitoring for 2008/09 cash budgets were introduced to reflect the spend profile of the capital works. The actual spend is 99.8% of the cash budget (£19.225m) and highlights the importance of setting cash budgets as well as scheme approvals. Cash budgets are a more accurate way of monitoring spend and performance. Many of the capital schemes are both technically and logistically complex to implement. Issues such as planning approvals, land transfers and inclement weather can all lead to unavoidable delays. In addition, their financial scale requires a lengthy tender process to ensure that best value is obtained prior to letting the works contract. It is therefore extremely difficult to complete such schemes within the financial year in which they are approved.
5.4Table 1 summarises the outturn position for schemes managed by Service Departments based on latest information available. The detailed monitoring sheets are provided at Annexes A-C.
Table 1: Capital outturn for each Service Annexe Service Approved Estimated Carry (Under) budget Outturn forward /Over spend £’000 £’000 £’000 £’000 A Corporate Services 1,225 604 603 -18 A Council Wide 2,000 776 1,225 1 B Social Care and Learning 20,040 10,919 8,927 -194 C Environment, Culture & 9,134 6,475 2,686 27 Communities Capitalisation of revenue 300 300 0 0 Residual Housing 0 110 0 110 Expenditure Total Capital Programme 32,699 19,184 13,441 -74 % spent 59%
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.