Capital Programme 2010/11 - 2012/13

Approved Executive 1 paper

Executive approved this item on Tuesday 15 December 2009. Below is the council's own wording, with the papers it was decided on.

Item35b

Resolved

RESOLVED that 1 Bracknell Forest Borough Council’s Capital Strategy 2009 as set out in Annex A to the Borough Treasurer report be endorsed; 2 An initial General Fund capital programme of £8.069m for 2010/12 summarised in Annex B, including the schemes listed in Annexes C – G to the Borough Treasurer report be approved for consultation; 3 The inclusion of an additional budget of £1m for Invest to Save schemes be approved for consultation; 4 It be approved that £25,000 of funding allocated in the Mercury Abatements for 2010/11 be brought forward into 2009/10 as set out in paragraph 5.13 of the Borough Treasurer report; 5 It be approved that £200,000 of funding allocated for low-cost home ownership mortgages for 2010/11 be brought forward into 2009/10 as set out in paragraph 5.14 of the Borough Treasurer report.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Executive

  72 7+((;(&87,9( '(&(0%(5   &$3,7$/352*5$00( %RURXJK7UHDVXUHU    385326(2)'(&,6,21  1.1 Under the Council’s Constitution, the Executive are required to issue their budget proposals for consultation for a minimum period of six weeks prior to making their recommendations to full Council on 16 February 2010. The capital programme forms an important part of the overall budget proposals and is a key means by which the Council can deliver its medium term objectives. This report draws together each service’s proposals so that the Executive can agree a draft capital programme for 2010/11-2012/13 as the basis for consultation. In compiling the draft programme the main focus is inevitably on determining the requirements for 2010/11, although future year’s schemes do form an important part of the programme.

1.2The financial implications of the recommendations in this report are reflected in the subsequent reports on the Council’s draft revenue budget. Any revisions to the proposals put forward by each service would also need to be reflected in this report which will also be published as the basis for consultation following the Executive’s meeting.

 5(&200(1'$7,216  7KDWWKH([HFXWLYH   (QGRUVHV%UDFNQHOO)RUHVW%RURXJK&RXQFLO¶V&DSLWDO6WUDWHJ\DVVHWRXW LQ$QQH[$   $SSURYHV IRU FRQVXOWDWLRQ DQ LQLWLDO *HQHUDO )XQG FDSLWDO SURJUDPPH RI PIRUVXPPDULVHGLQ$QQH[%LQFOXGLQJWKHVFKHPHVOLVWHGLQ $QQH[HV&±*   $SSURYHVIRUFRQVXOWDWLRQWKHLQFOXVLRQRIDQDGGLWLRQDOEXGJHWRI PIRU ,QYHVWWR6DYHVFKHPHV   $SSURYHV WKH  RI IXQGLQJ DOORFDWHG LQ WKH 0HUFXU\ $EDWHPHQW IRU WREHEURXJKWIRUZDUGLQWRDVVHWRXWLQSDUDJUDSK   $SSURYHV WKH  RI IXQGLQJ DOORFDWHG IRU ORZFRVW KRPH RZQHUVKLS PRUWJDJHV IRU  WR EH EURXJKW IRUZDUG LQWR  DV VHW RXW LQ SDUDJUDSK     5($6216)255(&200(1'$7,216

3.1The reasons for the recommendations are set out in the report.  $/7(51$7,9(237,216&216,'(5('

4.1The alternative options are considered in the report.

 6833257,1*,1)250$7,21  &DSLWDO6WUDWHJ\  5.1 Bracknell Forest’s first capital strategy was prepared in 2001 and has been updated and amended on several occasions to reflect updated guidance from Government and the Council’s changing requirements. This latest version has been updated to make the document reflect more closely the Council’s current requirements and provide the basis for developing and managing future year’s capital programmes.

5.2The latest version of the strategy is organised into the following sections:

1. Introduction 2. Background and Characteristics of Bracknell Forest 3. Framework for Bracknell Forest’s Capital Strategy 4. Approach to Prioritising Investment 5. Capital Receipts 6. Resources 7. Monitoring Progress 8. Managing Assets – Asset Management Group Annex A. Invest To Save Schemes

Attention is particularly drawn to the following highlights:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme 2010/11: 2012/13Report 159 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
PB
Councillor Paul Bettison OBE CONChair, present
AW
Alan Ward CONVice-Chair, present
MM
Councillor Mrs Mary Ballin CONCommittee Member, present
GB
Councillor Gareth Barnard CONCommittee Member, present
DB
Councillor Dale Birch CONCommittee Member, apologies
DH
Councillor Dorothy Hayes CONCommittee Member, present
AK
Councillor Alan Kendall CONCommittee Member, present
IM
Iain McCracken CONCommittee Member, present
JD
Jemma DurkanClerk, present

On this subject at Bracknell Forest

Search all
  1. Capital Programme 2010/11 - 2012/13This decision
  2. Highways and Transport Capital Programme 2026/27Approved
  3. Capital Programme 2026/27Approved
  4. Highways and Transport Capital Programme 2025/26Approved
  5. Capital Programme 2025/26Approved
  6. Highways and Transport Capital Programme 2024/25Approved

More from Bracknell Forest Executive

All decisions
MeetingDecisionOutcome
17 Sep 2024 Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... Noted Open
17 Sep 2024 Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... Agreed Open
17 Sep 2024 Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. Approved Open
17 Sep 2024 Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... Noted Open
17 Sep 2024 Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... Decided Open