What the committee will consider, in order, with every paper attached to its item. 07/00570/FUL - Bray Stage II Pipeline is the main business.
To approve as a correct record the minutes of the meeting of the Committee held on 12 November 2009. : RESOLVED that the minutes of the meeting of the Committee held on 12 November 2009 be approved as a correct record and signed by the Chairman.
Members are required to declare any personal or prejudicial interests and the nature of that interest, in respect of any matter to be considered at this meeting.
Any other items which, pursuant to Section 100B(4)(b) of the Local Government Act 1972, the Chairman decides are urgent.
Erection of two storey side extension, rear conservatory, extension to existing garage and formation of additional parking space
Decision: RESOLVED that the application be approved subject to the following conditions:- 01. The development hereby permitted shall be begun before the expiration of three years from the date of this permission. 02. The development hereby permitted shall be carried out only in accordance with the following approved plans received by the Local Planning Authority on 28 September 2009: AMX-Property-1201 Rev D AMX-Property-1201-1 Rev D AMX-Property-1201-2 Rev E AMX-Property-1201-3 Rev F AMX-Property-1201-4... Decision page
Erection of boundary fence varying from 1.5m to 1.8m following removal of existing hedge.
Decision: The following development plan policies have been taken into account in determining this planning application: Bracknell Forest Borough Local Plan: EN20 – as it would be acceptable in terms of its impact upon the character of the area, and amenity of surrounding properties and adjoining area. Core Strategy Development Plan Document: CS7 – which seeks to ensure that developments are of high quality design. South East Plan: CC6 – which seeks development that will respect and enhance the character... Decision page
Change of use from shop (Class A1) to hot food takeaway (Class A5).
Decision: The following development plan policies have been taken into account in determining this planning application: Bracknell Forest Borough Local Plan: Policy E5 which seeks development to be consistent with the hierarchy of shopping centres (major town centre, small town centres , village and neighbourhood centres , local parades), Policy E11 which permits changes of use to A2 or A3 uses where it would not adversely affect local retail provision and amenities of neighbouring properties in Village... Decision page
Change of use from retail (A1) to restaurant (A3).
Decision: RESOLVED that the application be approved subject to the following conditions:- 01. The development hereby permitted shall be begun before the expiration of three years from the date of this permission. 02. The development hereby permitted shall be carried out only in accordance with the following approved plans received by the Local Planning Authority on 20 October 2009: Supporting Planning Statement, drawing no. KIN/001/P (or any plans or details subsequently agreed in writing by the Local... Decision page
View the declarations of interest for item 70. Section 73 application for variation of (a) condition 11 of planning permission 610811 which states: "Deliveries to and despatch of goods from the site shall take place between the hours of 0700 hours and 1830 hours Monday to Saturday only" to allow deliveries to the store between 0700 hours and 2200 hours Monday to Saturday and 0900 hours and 1700 hours on Sundays and...
Decision: RESOLVED that the application be approved subject to the following conditions:- 01. The development hereby permitted shall be begun before the expiration of three years from the date of this permission. 02. No further external lighting shall be provided at the site unless otherwise approved in writing by the local planning authority. 03. All external lighting on the site shall be extinguished half an hour after closing time unless otherwise approved in writing by the local planning authority.... Decision page
To provide a response to the written request from South East Water to allow 24 hour working from 4 January 2010, for approximately 2 weeks, for tunnelling works associated with the rail crossing in Swinley Forest. This would be in conflict with Condition 3 of planning permission 07/00570/FUL. Response to letter from South East Water
Decision: RESOLVED that South East Water be advised that Bracknell Forest Council as the Local Planning Authority would not seek compliance with condition 3 of the planning permission 07/00570/FUL in relation to tunnelling works associated with the rail crossing in Swinley Forest, on the basis that the company followed the approach contained within its letter dated 23 November 2009. Decision page
Proposed modification of neighbourhood centre and affordable housing obligations in planning agreement dated 17 May 2004.
Decision: RESOLVED that (I) The Borough Solicitor be authorised to enter into an Agreement pursuant to Section 106A of the Town and Country Planning Act 1990 to modify obligations in the Peacock Farm Section 106 dated 17 May 2004 in accordance with the request received from Persimmon Special Projects set out in a letter dated 14 July 2009, except for the widening of the definition of the Medical Practice. (II) officers of the Council continue negotiations with the landowner and other stakeholders on the... Decision page
Item 71 is where most of this meeting's papers sit: 2 papers, about 2.2 MB.
To provide a response to the written request from South East Water to allow 24 hour working from 4 January 2010, for approximately 2 weeks, for tunnelling works associated with the rail crossing in Swinley Forest. This would be in conflict with Condition 3 of planning permission 07/00570/FUL. Response to letter from South East Water
This is the first time this subject appears in the meetings we have read.
Get the decision the day it is recorded, and anything that comes back to the committee on this subject.
All 15 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
The committee last met on 12 November 2009. 2 of its items lead into this meeting; 4 items are new. Point at any item to follow a thread. Procedural items are left out.
09/00610/RTD - Telecommunications Mast, Ringmead, Hanworth, Exclusion of Public and Press (S 100 A) do not return this time.
See the 12 November meetingEvery Planning & Highways Committee meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
Bracknell Forest, Planning & Highways Committee
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Planning & Highways Committee, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.