Capital Programme 2010/11 - 2012/13

Approved Executive 2 papers

Executive approved this item on Tuesday 16 February 2010. Below is the council's own wording, with the papers it was decided on.

Item41b

Resolved

RESOLVED that: 1 General Fund capital funding of £8.069m for 2010/11, in respect of those schemes listed in Annexes A – E of the report, be recommended to Council. 2 In addition to the capital funding of £8.069m for 2010/11, the release of £1.28m in respect of new affordable housing resulting from the LSVT in 2008 be recommended to Council. 3 The inclusion of an additional budget of £1m for ‘Invest To Save’ schemes, based on the underlying principles set out in the Capital Strategy approved by the Executive on 15 December 2009 be recommended to Council 4 Those schemes that attract external grant funding are included within the 2010/11 capital programme at the level of funding received be recommended to Council. 5 The release of £3.1m from s106 monies to fund capital projects outlined in paragraph 5.10 be recommended to Council. 6 That capital schemes that require external funding can only proceed once the Council is certain of receiving the grant, be agreed. 7 The indicative programme for 2011/12 and 2012/13 in the light of resources available and spending priorities in December 2010 be reviewed.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Executive

Recommendations

That the Executive:

2.1Recommends to the Council General Fund capital funding of £8.069m for 2010/11, in respect of those schemes listed in Annexes A - E.

2.2Recommends to the Council in addition to the capital funding of £8.069m for 2010/11, the release of £1.28m in respect of new affordable housing resulting from the LSVT in 2008.

2.3Recommends to the Council the inclusion of an additional budget of £1m for ‘Invest To Save’ schemes, based on the underlying principles set out in the Capital Strategy approved by the Executive on 15 December 2009

2.4Recommends to the Council that those schemes that attract external grant funding are included within the 2010/11 capital programme at the level of funding received.

2.5Recommends to the Council the release of £3.1m from s106 monies to fund capital projects outlined in paragraph 5.10.

2.6Agrees that capital schemes that require external funding can only proceed once the Council is certain of receiving the grant.

2.7Reviews the indicative programme for 2011/12 and 2012/13 in the light of resources available and spending priorities in December 2010.

Reasons for recommendations

3.1The reasons for the recommendation are set out in the report. 4 ALTERNATIVE OPTIONS CONSIDERED

4.1The alternative options are considered in the report below.

5 SUPPORTING INFORMATION

Background

5.1The Local Government Act 2003 requires councils to have regard to the Prudential Code for Capital Finance in Local Authorities when setting their capital expenditure plans, which must be affordable, prudent and sustainable.

5.2The proposed capital programme for 2010/11 has been developed, therefore, with particular regard to affordability and the impact of the Council’s capital expenditure plans on the revenue budget. The financing costs associated with the General Fund Capital Programme have been provided for in the Council’s revenue budget plans which appear later on tonight’s agenda.

5.3In addition to those schemes funded by the Council, the capital programme is supplemented by schemes funded by government grants and other external contributions. Details of these schemes are also included in the proposals for 2010/11 – 2012/13.

Capital Programme Proposals 2010/11 – 2012/13

5.4The Executive’s draft proposals for the Council’s capital programme for 2010/11 – 2012/13 were evaluated and prioritised into five broad categories, in accordance with the Council’s Corporate Capital Strategy and Asset Management Plan. This includes schemes within the previously approved programme for 2009/10, some of which are re-phased to reflect current information and priorities.

Unavoidable (Including committed schemes) This category covers schemes which must proceed to ensure that the Council is not left open to legal sanction and includes items relating to health and safety issues, new statutory legislation etc. Committed schemes are those that have been started as part of the 2009/10 Capital Programme. By their nature, schemes in this category form the first call on the available capital resources.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme: AnnexAppendix 23 KB Download
PDF
Capital Programme 2010/11: 2012/13Report 91 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
PB
Councillor Paul Bettison OBE CONChair, present
AW
Alan Ward CONVice-Chair, present
MM
Councillor Mrs Mary Ballin CONCommittee Member, present
GB
Councillor Gareth Barnard CONCommittee Member, present
DB
Councillor Dale Birch CONCommittee Member, present
DH
Councillor Dorothy Hayes CONCommittee Member, present
AK
Councillor Alan Kendall CONCommittee Member, present
IM
Iain McCracken CONCommittee Member, present
JD
Jemma DurkanClerk, expected

On this subject at Bracknell Forest

Search all
  1. Capital Programme 2010/11 - 2012/13This decision
  2. Highways and Transport Capital Programme 2026/27Approved
  3. Capital Programme 2026/27Approved
  4. Highways and Transport Capital Programme 2025/26Approved
  5. Capital Programme 2025/26Approved
  6. Highways and Transport Capital Programme 2024/25Approved

More from Bracknell Forest Executive

All decisions
MeetingDecisionOutcome
17 Sep 2024 Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... Noted Open
17 Sep 2024 Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... Agreed Open
17 Sep 2024 Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. Approved Open
17 Sep 2024 Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... Noted Open
17 Sep 2024 Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies