RESOLVED that: 1 The progress made since the last meeting on 1 July 2010 be noted; 2 The early procurement of a new haulage contract be endorsed; 3 The relaxation of the requirement for vehicles hauling re3 waste to be liveried with the re3 logo be endorsed . 4 The changes to the access controls at both Household Waste Recycling Centre’s be approved. 5 That a review of the Joint Agreement be undertaken to ensure that it remained fit for purpose.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
2.1To note progress made since the last meeting on 1st July 2010.
2.2That Members endorse the early procurement of a new haulage contract as described in paragraph 3.12 below.
2.3That Members endorse the relaxation of the requirement for vehicles hauling re3 waste to be liveried (with the re3 logo) as described in paragraph 3.15 below .
2.4That Members approve the changes to the access controls at both Household Waste Recycling Centre’s as described between paragraphs 3.23 and 3.25 and at 3.28.
3. SUPPORTING INFORMATION
Operations and Facilities
3.1A further incident of abuse towards a member of staff at the Smallmead Household Waste Recycling Centre (HWRC) occurred during August. The councils have made arrangements to highlight this issue, along with other information about safety and the ‘contamination’ of recyclables in the next issue of the monthly Green Pages supplement (in each of the Borough areas).
3.2The Contractor is reviewing the coverage of its CCTV provision within the (HWRC) as a result of the aforementioned incident.
3.3Repairs to the concrete floor slab in the HWRC shed at Longshot Lane are now complete. As a result, the contractor is now able to proceed with a trial of a mini- MRF. The mini-MRF is designed to capture recyclable materials such as metal or wood from the waste which residents deposit in the shed, for disposal, at the site.
3.4The Contractor has negotiated a new outlet for wood collected at the HWRC’s. With the new outlet both ‘clean’ wood (e.g. untreated) and ‘dirty’ wood (e.g. treated wood and mdf) can be placed in the same collection bay by patrons. This change has greatly increased the amount of wood captured. In the first two months of the new arrangement, the tonnage of wood collected has more than doubled on the same period in 2009.
3.5The new reprocessor for wood is able to recycle 80% of that collected and sends the remaining 20% for recovery via a biomass process.
3.6At the previous meeting of the JWDB (July 2010), Members received a presentation on the re-use trial being conducted at the Smallmead and Longshot Lane HWRC’s. The trial period has ended with a combined average of 20t per week being diverted from the two sites. The re-use activity continues at both sites and both the councils and Contractor will continue to explore ways in which activities can be expanded.
3.7At the previous meeting of the JWDB (July 2010), Members requested further information regarding consultants costs and also the potential implications of Contract Waste falling below 190,000 tonnes. Officers have subsequently provided detailed answers in both cases.
Joint Working Agreement
3.8There are currently no known proposals for changes to the Joint Working Agreement between the councils.
Haulage Contract Re-let
3.9Schedule 31.1 of the Project Agreement for the PFI Contract specifies that the Contractor should commence Market Testing of the haulage contract no later than six months prior to the Haulage Market Testing Date.
3.10Schedule 31.3 also specifies that, no earlier than eight months and not later than six months prior to the Haulage Market Testing Date, the Contractor should detail to the councils the charges for the current contract and engage in discussions about the specification for the impending procurement.
3.11The Haulage Market Testing Date will be five years after the commencement of the Contract and thus will fall early in December 2011. The practical effect of the two Schedules referred to above, would therefore combine to require the Contractor to begin the procurement process no earlier than April 2011.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.