Resolved
RESOLVED that 1 The Schools Forum noted the issues that have arisen over the current Reactive Maintenance SLA and that the Building Group were requested to provide an update to the next meeting of the Forum.
Schools Forum noted this item on Thursday 9 December 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that 1 The Schools Forum noted the issues that have arisen over the current Reactive Maintenance SLA and that the Building Group were requested to provide an update to the next meeting of the Forum.
1.1To consult Schools’ Forum on the proposal to change the current Service Level Agreement (SLA) for schools reactive maintenance.
2.1That the Schools Forum notes the issues that have arisen over the current Reactive Maintenance SLA and gives feedback on the proposal to adopt a new SLA (Option 2 in paragraph 5.15).
2.2The Schools Forum agrees that a ‘Pay As You Go’ SLA is offered to schools.
3.1The LA has a duty to consult Schools Forum on significant issues for schools. Reactive maintenance is a significant issue for schools for the continuing safe and effective operation of school buildings.
4 ALTERNATIVE OPTIONS TO BE CONSIDERED
4.1The options for schools are set out in the body of the report.
5 SUPPORTING INFORMATION
Existing Service Level Agreement
5.1The Schools Reactive Maintenance Service is provided to schools by the Council’s Building Group under a Service Level Agreement (SLA) and is an insurance type arrangement. There are 29 schools currently participating in the SLA (27 primaries, 1 secondary, 1 Special School), and 7 schools do not participate.
5.2Under the terms of the SLA participating schools contribute their devolved revenue budgets into a shared pot, which is administered by the Building Group. The schools report works required to the Council’s Call Centre, which raises a works order to an appropriate contractor. The Building Group procure and manage a term maintenance contractor to provide building maintenance services, which includes building, mechanical and electrical repairs.
5.3The budget can only be spent on re-active maintenance, which is revenue. When a job is likely to exceed £2,000 in value the school is advised, and is required to pay any excess above this threshold. Currently the average cost of a job is £486.
5.4The existing SLA operates on the principle of “insurance”, in that all works under £2,000 reported by schools are paid for from the shared pot regardless of the schools’ budget contribution. Some years a school may raise more works than its
5 budget contribution, and in other years it may raise fewer works than its budget contribution. Either way the school’s reactive maintenance contribution is fixed, which gives schools a degree of cost certainty in budget planning.
Reasons for SLA Review
5.5The following pressures have forced a review of the current SLA:
• A reduction in the overall shared budget pot
• An increase in the value and number of reported works
Costs and Funding
5.6In 2009/10 the shared budget available for repairs was £316k, but this was overspent at the financial year end by £195k for a number of reasons:
• The changeover of the main term contractor from William Davis and Son to ROK was accompanied by a surge of outstanding invoices from William Davis & Son. The reason for this was that William Davis was notoriously slow in submitting invoices for payment. Even after constant request to submit outstanding invoices the contractor failed to respond fully. However, on termination of the contract the company submitted all outstanding invoices, which the Council was legally required to pay within that financial year. The amount paid to William Davis in 2009/10 was £208k. This amounts to 66% of the 2009/10 budget, despite them being the contractor for only two months of that financial year.
• Unfortunately 2009/10 saw the worst winter for approximately 30 years and as a result schools experienced significant heating problems, as well as burst and leaking pipes that had to be dealt with. This placed additional pressure on the budget.
• In the four previous financial years some repairs raised under this SLA qualified for inclusion on the Council’s planned maintenance programme and were able to be capitalised, easing the budget pressure by an average of £30k per annum, In 2009/10, no works qualified so a further pressure was placed on the budget.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
School Reactive MaintenanceReport | 44 KB | DownloadRead as text |
PDF |
School SLA: 19-11-10Report | 122 KB | Download |
Follow Schools Forum at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Mar 2026 | High Needs Block 2026-27RESOLVED that: i . The High Needs Block deficit budget be set at £11.5 million ii. The local authority take all avail... | Decided | Open |
| 14 Jan 2026 | Early Years Budgets 2026-27RESOLVED that for the 2026-27 financial year the Executive Member for Children, Young People and Learning sets out th... | Approved | Open |
| 14 Jan 2026 | Exclusion of Public and PressRESOLVED that pursuant to Section 100A of the Local Government Act 1972, as amended, and having regard to the public ... | Decided | Open |
| 4 Dec 2025 | Minutes and Matters ArisingIt was agreed that further investigation and clarification was needed, with an update to be brought to the next meeting. | Agreed | Open |
| 4 Dec 2025 | Initial proposals for the 2026-27 Early Years Funding Formula and 2026-27 Early Years BudgetRESOLVED that the Schools Forum; Approves proposed changes to the Deprivation Supplement from April 2026; Approves pr... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.