Resolved
RESOLVED that the performance of the Council over the period from July to September 2010, highlighted in the Overview Report in Annex A be noted.
Executive noted this item on Tuesday 14 December 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the performance of the Council over the period from July to September 2010, highlighted in the Overview Report in Annex A be noted.
Corporate Performance Overview Report Second Quarter 2010/11 July - September 2010
Timothy Wheadon Chief Executive Overview of Council Performance
1 Introduction
1.1This report sets out an overview of the Council’s performance for the second quarter of 2010/11 (July - September 2010). It complements the detailed quarterly Performance Monitoring Reports (PMRs) produced by each Director, which are being circulated to Members in tandem with this report. The purpose of this report is to provide the Executive with a high-level summary of key achievements, and to highlight areas where performance is not matching targets or expectations, along with any remedial action that is being taken to address this.
2 Overview of Performance
2.1The departmental service plans for 2010/11 contain 375 detailed actions to be completed in support of the 13 medium-term objectives which underpin the Council’s six overarching priorities for 2008/09-2010/11. The status as at the end of quarter 2 is: • 361 (96%)green • 1 (0.3%) red • 13 (3.7%) not yet started due to them no longer being required, deferment or awaiting further guidance or legislation
2.2During this quarter, the Secretary of State for Local Government and Communities announced the abolition of Local Area Agreements (and associated reward monies) and the replacement of the National Indicator Set with a single, comprehensive list of data required by central government from local authorities. This is due to be in place for April 2011 and consultation is expected shortly.
2.3As this announcement came in the middle of the preparations for the quarter 2 performance reporting, officers have continued to prepare the quarter 2 reports. Indeed the national indicators are only one part of the total performance framework for the Council. The other elements for performance reporting link to the priorities and actions that the Council is undertaking and updates on their associated risks. Discussions are taking place to shape the future performance management across the Council, for the remainder of this financial year and beyond, as it is essential that we are able to accurately measure progress on those activities that are important to us in the meanwhile. Departments have already taken the opportunity to review the Service Plans for 2010/11 so that they now reflect the in-year budget cuts.
3 Progress against Medium-Term Objectives
3.1The second quarter of 2010/11 saw good overall progress towards achieving the Council’s objectives and work on the detailed actions and risk mitigations identified under the 13 medium term objectives for 2010/11 is continuing. The following paragraphs highlight some areas of notable progress against each medium-term objective.
Medium-Term Objective 1: Build a Bracknell Town Centre that residents are proud of
3.2Activity continues to enable the regeneration to go ahead as quickly as possible. This includes extension of the time limit for the outline planning permission, updating the
Corporate Performance Overview Report – 2010/11 Quarter 2 Page 2 plans to enable work to start as soon as possible, and the disposal of a small strip of land around Imation House to facilitate the development of a foodstore. The Town Centre Partnership has been refreshed and is focussing on work that can be done now to improve the town centre for our residents. It is anticipated that a number of positive developments resulting from recent activities will become apparent in the next quarter.
Medium-Term Objective 2: Keep our parks, open spaces and leisure facilities accessible and attractive
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Performance Overview ReportReport | 201 KB | DownloadRead as text |
PDF |
Corporate Performance Overview Report Quarter 2, 2010/11Report | 28 KB | Download |
Follow Executive at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2024 | Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... | Noted | Open |
| 17 Sep 2024 | Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... | Agreed | Open |
| 17 Sep 2024 | Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. | Approved | Open |
| 17 Sep 2024 | Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... | Noted | Open |
| 17 Sep 2024 | Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.