Resolved
RESOLVED that the disposal land identified on the site plan attached as Appendix A to the report be appropriated from education use to use for corporate purposes.
Executive decided this item on Tuesday 14 December 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the disposal land identified on the site plan attached as Appendix A to the report be appropriated from education use to use for corporate purposes.
2.1That the disposal land identified on the site plan attached as Appendix A be appropriated from education use to use for planning purposes.
3.1Following completion of the new Garth Hill College buildings, the Disposal land is now surplus to education use.
3.2The disposal of surplus land over 0.5 acres (0.202 hectares) or above £500,000 is the responsibility of the whole Executive under the terms of the Council’s Constitution.
4.1Alternative site options were considered by the Executive when approving the site strategy for GHC in December 2007. The current arrangements are consistent with the 2007 strategy.
5 SUPPORTING INFORMATION
5.1In December 2007 the Executive agreed the Site Strategy for the new GHC buildings and facilities, which included the following provisions:
a) To re-provide the school buildings broadly in line with the 2003 masterplan, including use of Bull Lane field as playing fields, maximising the capital receipt from the sale of surplus land.
b) The capital receipts to be used to fund the new school buildings and facilities.
c) The balance of any surplus capital receipt to be paid into corporate funds.
Progress with the GHC Project
5.2With the completion of Phase 1 of the GHC project in September 2010, the College has now vacated their old buildings. Phase 2 of the project includes the construction of a floodlit artificial turf pitch, multi use games area, running track and athletics facilities on the main school site, and construction of the new boundary fence between GHC and the surplus disposal land. This work is expected to be complete by May 2011.
GHC and Disposal Land
5.3Following completion of the new Garth Hill College buildings, the disposal land identified on the site plan attached as APPENDIX A is now surplus to educational requirements, and its appropriation out of education use forms a recommendation of this report.
5.4The areas of land involved are also set out in Table One below.
Table One: Site Areas Existing m2 Proposed m2
GHC Main Site 103,839 70,649 Bull Lane Field 0 31,521 Total Educational Land 103,839 102,162
Disposal Land 0 36,129
Land Sale
5.5In December 2007, the Executive gave authority to the Director of Children Young People & Learning to dispose of the surplus land at Garth Hill College on the open market. The timing of this disposal will depend on market conditions and will be subject of a future report.
6 ADVICE RECEIVED FROM STATUTORY AND OTHER OFFICERS
Borough Solicitor
5.6The disposal land is now surplus to educational requirements and is being prepared for disposal, and the council has the necessary statutory powers to appropriate this land for other statutory purposes and to dispose of it.
5.7Under section 122 of the Local Government Act 1972 the Council may appropriate land to any purpose which the Council is authorised to acquire land for where the land belongs to the Council and is no longer required for the purpose for which it is held immediately before the appropriation. Under section 226 of the Town and Country Planning Act 1990 the Council is authorised to acquire land if the Council thinks that the acquisition would facilitate the development/re-development or improvement on or in relation to the land. In this instance, as it is envisaged that the surplus land will be used for residential development, the criteria for appropriation to Planning use is clearly met.
Borough Treasurer
6.2The disposal will provide the Council with a sufficient capital receipt to cover the funding gap previously agreed as part of the Garth Hill College (GHC) project plan and site strategy. Equalities Impact Assessment
6.3An Equality Impact Assessment has been completed for this project and all of the new buildings and facilities will be accessible to disabled people.
Strategic Risk Management Issues
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appropriation of Surplus Land at Garth Hill CollegeReport | 371 KB | DownloadRead as text |
Follow Executive at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2024 | Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... | Noted | Open |
| 17 Sep 2024 | Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... | Agreed | Open |
| 17 Sep 2024 | Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. | Approved | Open |
| 17 Sep 2024 | Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... | Noted | Open |
| 17 Sep 2024 | Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.