CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bracknell Forest Council
Executive, Tuesday 5 July 2011 at 5.00pm

Commitment Budget 2012/13 - 2014/15

Approved Executive 2 papers

Executive approved this item on Tuesday 5 July 2011. Below is the council's own wording, with the papers it was decided on.

Item6g

Resolved

RESOLVED that 1 The Commitment Budget for the period 2012/13 to 2014/15, summarised in Table 1 of the report be approved. 2 The proposed budget process for 2012/13 as set out in paragraphs 5.19 to 5.22 of the report be approved.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Executive

Recommendations

2.1That the Commitment Budget for the period 2012/13 to 2014/15, summarised in Table 1 of the report be approved.

2.2That the proposed budget process for 2012/13 as set out in paragraphs 5.19 to 5.22 of the report be approved.

Reasons for recommendations

3.1The recommendations are designed to allow the Executive to develop its Medium Term Financial Strategy and to start to consider an appropriate budget strategy for 2012/13 and beyond.

Alternative options considered

4.1Background information relating to the options considered is included in the report.

5 SUPPORTING INFORMATION

Commitment Budget 2012/13-2014/15

5.1The preparation of the Commitment Budget for the coming three year period brings together the Council’s existing expenditure plans and is the first formal stage in planning for the revenue budget for 2012/13. The Council’s Commitment Budget is shown in detail in Annexe A and summarised in Table 1.

Table 1: Commitment Budget 2012/13-2014/15

Department Plans Base Planned Expenditure Budget 2011/12 2012/13 2013/14 2014/15 £m £m £m £m Base Budget 76,255 76,255 76,442 76,458 Movements in Year - 187 16 -14 Adjusted Base 76,255 76,442 76,458 76,444

This table illustrates the Council’s current planned spending. The Commitment Budget is based upon the 2011/12 budget approved by Council in March adjusted to exclude the effects of drawings from balances, and takes account of approved existing commitments, including the full-year effect of pressures and economies approved for the 2011/12 budget. Although the individual implications of these items is significant, after an increase of £0.187m in 2012/13 the Commitment Budget is almost static. 5.2 Savings identified for future years within the revenue proposals for 2011/12 have been included in the commitment budget. Significant changes to the Commitment Budget submitted in March include:

• Dementia Advisory Service – End of one year funding for service • Refuse Collection – Additional savings from tender exercise • Terms and Conditions – Cost savings across range of benefits • Car Park Season Ticket – Additional pressure from loss of major customer

5.3As part of the process for building the 2012/13 budget, all commitments will be reviewed over the coming months to ensure that they remain valid and have been accurately costed.

Resources

5.4There are a number of inherent difficulties in medium-term financial planning, in terms of accurately estimating both available resources and spending needs. As such multi-year grant settlements are welcomed and as part of the 2011/12 Local Government Finance Settlement the Council was notified of the level of government support it can expect to receive in 2012/13. Total external support in the form of general revenue grant will be £23.12m, a reduction of £2.97m compared with 2011/12 (which itself reflected a net reduction of £3.2m on 2010/11).

5.5Such a significant reduction in external support is consistent with the Government’s policy of front loading spending reductions on local government spending as part of its overall strategy of deficit reduction and is a major contributory factor to the overall funding gap identified for 2012/13. External funding in future years (2013/14 and 2014/15) is less clear. Control totals at governmental departmental levels indicate further reductions of 2% in 2013/14 and 4% in 2014/15. However the Government have begun consulting on what may amount to a fundamental change in the way that local government is centrally funded.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Commitment Budget 2012/13: 2014/15Report 74 KB DownloadRead as text
PDF
Commitment Budget July 11 Annexe AAppendix 9 KB Download

At this meeting

Whole meeting

Who was there

6 of 10 attended
PB
Councillor Paul Bettison CONChair, apologies
AW
Councillor Alan Ward CONVice-Chair, present
MM
Councillor Mrs Mary Ballin CONCommittee Member, present
DG
Councillor Dr Gareth Barnard CONCommittee Member, present
DB
Councillor Dale Birch CONCommittee Member, present
MD
Councillor Mrs Dorothy Hayes MBE CONCommittee Member, present
IM
Councillor Iain McCracken CONCommittee Member, present
AK
Councillor Alan Kendall CONCommittee Member, apologies
BR
Berkshire Record OfficePublic, expected
JD
Jemma DurkanClerk, expected

On this subject at Bracknell Forest

Search all
  1. Commitment Budget 2012/13 - 2014/15This decision
  2. Commitment Budget Report 2015/16 - 2017/18Approved
  3. Commitment Budget Report 2014/15 - 2016/17Approved
  4. Commitment Budget Report 2013/14 - 2015/16Approved
  5. Commitment Budget 2011/12 - 2013/14Approved
  6. Commitment Budget 2010/11 - 2012/13Approved

More from Bracknell Forest Executive

All decisions
MeetingDecisionOutcome
17 Sep 2024 Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... Noted Open
17 Sep 2024 Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... Agreed Open
17 Sep 2024 Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. Approved Open
17 Sep 2024 Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... Noted Open
17 Sep 2024 Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies