Commitment Budget Report 2015/16 - 2017/18

Approved Executive 2 papers

Executive approved this item on Tuesday 22 July 2014. Below is the council's own wording, with the papers it was decided on.

Item11d

Resolved

RESOLVED that: The Commitment Budget for the period 2015/16 to 2017/18, summarised in Table 1 of the Borough Treasurer’s report be approved. The proposed budget process for 2015/16 as set out in paragraphs 5.18 to 5.21 of the Borough Treasurer’s report be approved.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Executive

Recommendations

2.1That the Commitment Budget for the period 2015/16 to 2017/18, summarised in Table 1 of the report be approved.

2.2That the proposed budget process for 2015/16 as set out in paragraphs 5.18 to 5.21 of the report be approved.

Reasons for recommendations

3.1The recommendations are designed to allow the Executive to develop its Medium Term Financial Strategy and to start to consider an appropriate budget strategy for 2015/16 and beyond.

Alternative options considered

4.1Background information relating to the options considered is included in the report.

5 SUPPORTING INFORMATION

Commitment Budget 2015/16-2017/18

5.1The preparation of the Commitment Budget for the coming three year period brings together the Council’s existing expenditure plans and is the first formal stage in planning for the revenue budget for 2015/16. The Council’s Commitment Budget is shown in detail in Annexe A and summarised in Table 1.

Table 1: Commitment Budget 2015/16-2017/18

Department Plans Base Planned Expenditure Budget 2014/15 2015/16 2016/17 2017/18 £m £m £m £m Base Budget 87,058 87,058 88,052 89,522 Movements in Year - 994 1,470 504 Adjusted Base 87,058 88,052 89,522 90,026

This table illustrates the Council’s current planned spending. The Commitment Budget is based upon the 2014/15 budget approved by Council in February adjusted to exclude the effects of drawings from balances, and takes account of approved existing commitments, including the full-year effect of pressures and economies approved for the 2014/15 budget. 5.2 Savings identified for future years within the revenue proposals for 2014/15 have been included in the commitment budget. Significant changes to the Commitment Budget submitted include: • Revenue impact of ICT schemes implemented in 2014/15 Capital Programme (+£0.054m) • The impact of the indicative 2014/15 Capital Programme (MRP and Interest Costs) are now included in the Commitment Budget (+£0.214m) along with impact of future year’s capital programmes. • Cost of increase in Employers Pension fund contributions (+£0.140m) • Pre-paying Pension Fund contributions in advance curtailed (-£0.100m)

5.3As part of the process for building the 2015/16 budget, all commitments will be reviewed over the coming months to ensure that they remain valid and have been accurately costed.

Resources

5.4There are a number of inherent difficulties in medium-term financial planning, in terms of accurately estimating both available resources and spending needs. The Commitment Budget covers a very uncertain period with a General Election in 2015 and a new Spending Review covering the years 2016 onwards to be set by the incoming Government. However with a 2-year Local Government Financial Settlement (LGFS) announced this year covering 2014/15 to 2015/16 there is at least some certainty on Government Funding for the first year of the Commitment Budget.

5.5For planning purposes the reduction in central government support included in the 2014/15 LGFS has been incorporated within these Budget Projections reflecting a further reduction of £4.3m in 2015/16. For the remaining period of the Commitment Budget a reduction of 8% overall in government support has been assumed. This may be conservative given past reductions, however recent history shows that local government has delivered substantially more, in terms of relative savings, than nearly all other central government departments, and as such there is support for a reduced level of cuts.

5.6The Council also receives substantial external funding through a number of specific grants for which the following assumptions have been included within the latest budget projections.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
096b Commitment Budget Annex AAppendix 15 KB Download
PDF
Commitment Budget Report 2015/16: 2017/18Report 59 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
JD
Jemma DurkanClerk, expected
PB
Councillor Paul Bettison CONChair, present
AW
Councillor Alan Ward CONVice-Chair, present
DG
Councillor Dr Gareth Barnard CONCommittee Member, present
DB
Councillor Dale Birch CONCommittee Member, present
MB
Councillor Marc Brunel-Walker CONCommittee Member, present
MD
Councillor Mrs Dorothy Hayes MBE CONCommittee Member, present
IM
Councillor Iain McCracken CONCommittee Member, present
CT
Councillor Chris Turrell CONCommittee Member, present

On this subject at Bracknell Forest

Search all
  1. Commitment Budget Report 2015/16 - 2017/18This decision
  2. Commitment Budget Report 2014/15 - 2016/17Approved
  3. Commitment Budget Report 2013/14 - 2015/16Approved
  4. Commitment Budget 2012/13 - 2014/15Approved
  5. Commitment Budget 2011/12 - 2013/14Approved
  6. Commitment Budget 2010/11 - 2012/13Approved

More from Bracknell Forest Executive

All decisions
MeetingDecisionOutcome
17 Sep 2024 Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... Noted Open
17 Sep 2024 Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... Agreed Open
17 Sep 2024 Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. Approved Open
17 Sep 2024 Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... Noted Open
17 Sep 2024 Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... Decided Open