It was agreed that once the draft regime had been to the Executive it would be brought to the Panel for comment. Arising from Members’ questions and comments the following points were noted: The CIL tariff was more flexible than the previous s.106 regime. Once the funds had been collected there was no specific plan stating what the funding was to be spent on or where. It would not be appropriate to set the CIL tariff based on market forces as a robust local evidence base would be required to justify the tariff. As CIL was a new system it would be important to ensure a robust process was in place for the governance of the regime. A meaningful proportion of the CIL from a development would be given directly to Parish and Town Councils. In relation to the CIL in Bracknell Forest the terms neighbourhood and local communities referred to the Parish and Town Council areas. The CIL was in place to mitigate the infrastructure impacts of a new development. Whilst the funding was allocated to projects in the local area where appropriate, for some projects the funding would be spent on improvement works that were not in the immediate area, but that best mitigated the developments impact. The Panel expressed its wish to be regularly updated of progress made in relation to the development of the CIL and to be involved in consultation when appropriate. The Panel noted the proposed CIL and how the Council was preparing for ... view the full minutes text for item 18.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
Report to Environment, Culture and Communities Overview & Scrutiny Panel
Purpose of report
1.1This report summarises the Community Infrastructure Levy (CIL) which will be replacing, in part, the use of s.106 agreements for infrastructure delivery as part of new development proposals. It also sets out how the Council is preparing for its introduction.
1.2The Council will want to put itself into the best position possible to maximise the legitimate charging potential from new development to deliver the Council’s policies and priorities. This will be key in making sure the Council is able to deliver development that is as sustainable as possible and to minimise the impact new development has not only on future generations, but by implication, on the ability for the Council to deliver its services in the future.
2. RECOMMEDATION
2.1That the Panel notes the proposed Community Infrastructure Levy and how the Council is preparing for its introduction.
3. REASONS FOR RECOMMEDATION
To inform the Panel of the proposed Community Infrastructure Levy and how the Council is preparing for its introduction.
Alternative options considered
None.
5. THE COMMUNITY INFRASTRUCTURE LEVY
5.1CIL is a standardised tariff system for collecting contributions towards infrastructure provision from developers of residential and commercial development. It is up to Councils whether or not to introduce a CIL, but if they do not, then by April 2014, they will not be able to continue with their own system via s106 planning obligations for pooled contributions as the Council presently does through the ‘Limiting the Impact of Development’ Supplementary Planning Document. CIL is very important for Bracknell Forest where planned development will result in the need for significant highway improvement works and a new secondary school, among other infrastructure requirements.
5.2CIL payments will be calculated by applying a tariff rate to the net increase in floor area resulting from a development. The rate to be set will be based on a schedule that can set different levels of charge for different land uses (residential, business, retail etc.) and for different geographic areas. The rates, and any variations within them must be set at a level that will ensure that most development is viable. Any variations between uses and geographic areas must be based on there being quantifiable differences in their viability.
5.3Liability for payment of CIL
The liability for and payment of CIL will be based on the following:
• Liability for payment of CIL arises on grant of planning permission and payment will be due on commencement of development (there is now provision in amended regulations for phased payments); • CIL will apply to increases in floorspace (where the increase in gross internal area is 100 sq metres or more or where any new dwelling is created); • The CIL amount charged will be indexed from the date of adoption of the charging schedule to the date of planning permission; • Larger developments may make ‘land payments’ on which infrastructure is to be provided in lieu of some financial payment; • An exemptions process is included to allow up to 100% relief for charities, social housing and exceptional circumstances; • Provisions are made for enforcement and surcharging for late or non-payment of CIL; and, • Provisions are included for appeal.
5.4Application of CIL
CIL can be used for funding for infrastructure outside the Council’s area that would support development within its area. The Council must report annually on CIL receipts and expenditure. The CIL provisions allow Councils to prudentially borrow against expected future CIL receipts
5.5Planning Obligations
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Culture and Communities Overview & Scrutiny Panel at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.