RESOLVED that 1 The Draft Charging Schedule at Appendix A of the Director of Environment, Culture & Communities’ report be approved for publication, consultation and submission to the Secretary of State; 2 The Draft ‘Regulation 123’ List of Infrastructure Projects for which CIL will be charged at Appendix B be approved for the purpose of consultation; 3 The Instalment Policy at Appendix C be approved for the purpose of consultation; and, 4 The Director of Environment, Culture and Communities, in consultation with the Executive Member for Planning and Transport, be authorised to: (a) To agree minor modifications to the Draft Charging Schedule as appropriate following public consultation; and, (b) To approve the statements referred to in regulations 16 (Publication) and 19 (Submission) of the Community Infrastructure Regulations 2010.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
• inform the Executive of the results of the consultation on the Community Infrastructure Levy (CIL) Preliminary Draft Charging Schedule;
• summarise the findings of further viability work; and,
• seek approval for the publication and submission of a Draft Charging Schedule.
1.2The report also seeks approval for a draft list of infrastructure projects which it is proposed will be fully or partly funded through CIL (the ‘Regulation 123’ List) and an instalments policy.
2 RECOMMENDATION(S)
2.1That the Executive:
(i) approves the Draft Charging Schedule at Appendix A for publication, consultation and submission to the Secretary of State;
(ii) approves the Draft ‘Regulation 123’ List of Infrastructure Projects for which CIL will be charged at Appendix B for the purpose of consultation;
(iii) approves the Instalment Policy at Appendix C for the purpose of consultation; and,
(iv) authorises the Director of Environment, Culture and Communities, in consultation with the Executive Member for Planning and Transport, to:-
(a) agree minor modifications to the Draft Charging Schedule as appropriate following public consultation; and,
(b) approve the statements referred to in regulations 16 (Publication) and 19 (Submission) of the Community Infrastructure Regulations 2010.
3 REASONS FOR RECOMMENDATION(S)
3.1The Community Infrastructure Levy (CIL) will become an important mechanism by which the Council will secure money to create new and improve existing infrastructure to support growth in the Development Plan. The publication and submission of a Draft Charging Schedule and carrying out consultation on it are legal requirements for the introduction of CIL. Unrestricted
3.2The Statements at recommendation (iv)(b) are a statement of the representations procedure at the publication stage (Regulation 16) and a statement of representations made and any modifications at the submission stage (Regulation 19).
Alternative options considered
4.1The Council is not required to introduce a CIL, but if it does not, then by April 2014, it will no longer be able to pool five or more s106 planning obligations towards any infrastructure project. This would make it very difficult to secure large items of infrastructure such as the new secondary school needed in the north of the Borough for which contributions from a large number of developments will be required.
4.2Within Bracknell Forest, planned development will result in the need for significant highway improvement works and a new secondary school, among other infrastructure requirements. For this reason, it is considered important for the Council to proceed with the introduction of CIL.
5 SUPPORTING INFORMATION
Background to CIL
5.1CIL was introduced in the Planning Act 2008 and further measures relating to its operation are contained in the Localism Act and in Regulations.
5.2CIL essentially a standardised tariff system for collecting contributions towards infrastructure provision from developers. CIL payments will be calculated by applying tariff rates to the net increase in floor area resulting from a development. 5.3 Developing the CIL is an Executive function, and has been informed by input from an Overview and Scrutiny Working Group, an Officer Steering Group and public consultation.
Setting the Level of CIL
5.4In setting its CIL rates the Council must aim to strike what appears to be an appropriate balance between the desirability of securing CIL funding to meet the expected costs of infrastructure required to support development and the potential effects of imposing CIL on the economic viability of development.
5.5There are therefore two key elements to the setting of CIL:
• Demonstrating the need for new infrastructure and that there is a gap in the funding available for its provision that should be met by CIL; and, • Demonstrating that CIL rates will not put development at serious risk of being unviable.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.