RESOLVED that: the nature of Natural England’s response to the HRA, and the Council’s position is noted by the Executive. the Executive confirms its approval for the introduction of car parking charges at The Look Out and Coral Reef in September 2012.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1.1The purpose of this report is to update the Executive on the most recent response from Natural England to the Habitats Regulations Assessment (HRA) carried out by the Council for the introduction of car parking charges at The Look Out, to confirm the Council’s position and note the full support of the Crown Estate.
2 RECOMMENDATION(S)
2.1That the Executive notes the nature of Natural England’s response to the HRA, and the Council’s position.
2.2That the Executive confirms its approval for the introduction of car parking charges at The Look Out and Coral Reef in September.
3 REASONS FOR RECOMMENDATION(S)
3.1The Council had hoped to secure the full support of Natural England in advance of introducing car parking charges at The Look Out and Coral Reef but at this juncture has been unable to do so. The Executive are asked to note the lack of full support but to proceed with the project as planned.
3.2The Council, as Competent Authority, has conducted an HRA and concluded that there will be no adverse impact on the integrity of the Thames Basin Heaths Special Protection Area (SPA).
Alternative options considered
4.1Introduction of car parking charges could be delayed to allow more time to attempt to resolve any concerns expressed by Natural England. This would require further research but it is not felt that this would contribute significantly to the information the council would have at its disposal given the significant work already carried out.
5 SUPPORTING INFORMATION
5.1The Executive approved the proposals to introduce car parking charges at The Look Out and Coral Reef on May 22nd 2012. Given the sites’ close proximity to the Thames Basin Heaths Special Protection Area (SPA), it was required to carry out a Habitats Regulations Assessment to gauge what impact, if any, the project would have on the integrity of the SPA. Using a precautionary principle, the Council, as
Page 1 of 4 competent authority, must be satisfied that the proposal will not have an adverse effect on the integrity of the SPA before it can proceed.
5.2The Council appointed independent consultants to undertake the HRA and in May their draft report concluded that there would be no adverse impact on the SPA provided that mitigation measures were put in place. The report also recommended a few actions the Council could take to make this conclusion even more robust.
5.3This draft report was shared with Natural England and their initial response was broadly supportive although some suggestions were made which they felt would enhance the report. This response is attached as Annexe A. Broadly speaking, the matters they raised referred to the conduct of the HRA although they felt the process was comprehensive, they queried some of the evidence and conclusions, and asked for more detail on the mitigation actions proposed. While the Council was confident of its own assessment that there would be no impact on the SPA, in the spirit of partnership more detail was added to the final draft HRA regarding mitigation measures, monitoring and possible responses to unforeseen circumstances. The Council therefore felt it had responded to the concerns of Natural England in its final draft which was completed in August. Unexpectedly, Natural England’s response to the final draft was much more robust than previously such that they do not currently support the Council’s conclusion that the introduction of car parking charges will not have a detrimental effect on the SPA. They suggest a deferral of the project until further work is undertaken.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.