Highway Maintenance Works Programme 2013-14

Decided Executive 2 papers

Executive decided this item on Tuesday 12 March 2013. Below is the council's own wording, with the papers it was decided on.

Item34c

Resolved

RESOLVED that the budget for 2013-14 be targeted at the indicative Highway Maintenance Works Programme as set out in Annex 1 of the Director of Environment, Culture and Communities’ report.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Executive

Recommendation

2.1That the budget for 2013-14 be targeted at the indicative Highway Maintenance Works Programme as set out in Annex 1.

Reasons for recommendation

3.1To meet the Council’s Local Transport Targets and improve the condition of the highway network in pursuance of the Council’s Medium Term Objectives.

Alternative options considered

4.1No alternative options are appropriate. The proposals seek to effect works according to priority needs based on an assessment of condition that also reflects general safety. The need to have a large range of schemes is essential in order to minimise delay and maximise operational efficiencies. The Annex is updated annually.

5 SUPPORTING INFORMATION

5.1The 2013/14 budget includes £1.427M for the non routine highway maintenance schemes. This is the level of funding provided via the Local Transport Plan (LTP) capital allocation along with a further £228k from the Council’s own capital programme by way of capitalised revenue for road maintenance and street lighting. This is the funding we use for the schemes as indicated in Annex 1.

5.2In addition, as a one-off the Government have recently allocated £259k in the year 2013-2014 towards the costs associated with road damage due to the severe weather. This money comes with conditions to ensure that it is used for the purpose intended. 5.3 The LTP money is not ring fenced and could in theory be spent according to local needs. However, the clear expectation is that it is used for the purpose intended. The revenue budget is used for basic maintenance purposes mainly related to ensuring safety to the users.

5.4The level of maintenance demand far exceeds available budgets. Accordingly funding has to be targeted and, as per the LTP, we prioritise spend according to an assessment of need having regard to the condition of the asset. The deterioration evident in many streets as a direct result of the unusually severe wet weather has been taken into account in the selection process.

5.5The nature of the actual work in any given street will vary and will only be fully defined once a more detailed survey has been undertaken. The form of treatment for each road will be the most appropriate for the nature and category of the individual road to ensure the most cost effective use of available budgets and preserve the useful life of the structure. At this stage in the process the costings have to be considered 'indicative'. The list is therefore no more than a statement of intention subject to the funds. In addition whilst the need to do the works may be noted at times the ability to do the work is restricted because of other plans for the network. Where possible we try to co-ordinate activity in order to minimise local disruption but also to try to avoid new surfacing being dug up shortly after it has been laid. Such streets remain on the programme and are carried forward into next year's plan.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
08b Highway Maintenance Works Programme 2013-15 Annex AAppendix 65 KB Download
PDF
Highway Maintenance Works Programme 2013-14Report 59 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
PB
Councillor Paul Bettison CONChair, present
AW
Councillor Alan Ward CONVice-Chair, present
MM
Councillor Mrs Mary Ballin CONCommittee Member, present
DG
Councillor Dr Gareth Barnard CONCommittee Member, present
DB
Councillor Dale Birch CONCommittee Member, present
MB
Councillor Marc Brunel-Walker CONCommittee Member, present
MD
Councillor Mrs Dorothy Hayes MBE CONCommittee Member, present
IM
Councillor Iain McCracken CONCommittee Member, present
KS
Katharine SimpsonClerk, expected

On this subject at Bracknell Forest

Search all
  1. Highway Maintenance Works Programme 2013-14This decision
  2. Highways Maintenance Works Programme 2018-19Decided
  3. Highway Maintenance Works Programme 2017-18Decided
  4. Highway Maintenance Works Programme 2016-17Decided
  5. 2015/16 Highway Maintenance ProgrammeApproved
  6. Highway Maintenance Works Programme 2014-15Decided

More from Bracknell Forest Executive

All decisions
MeetingDecisionOutcome
17 Sep 2024 Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... Noted Open
17 Sep 2024 Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... Agreed Open
17 Sep 2024 Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. Approved Open
17 Sep 2024 Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... Noted Open
17 Sep 2024 Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies