RESOLVED that the budget for 2017-18 be targeted at the four year indicative Highway Maintenance Works Programme as set out in Annex 1 of the Director of Environment, Culture & Communities report, having due regard to the priority, availability of road space and available budget.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
2.1That the budget for 2017-18 be targeted at the four year indicative Highway Maintenance Works Programme as set out in Annex 1 having due regard to the priority, availability of road space and available budget.
Reasons for recommendation
3.1The proposals in this report therefore identify the priority work across the network to maintain the highway in as good a condition as resources allow, having due regard to the Council’s intervention policy based on condition as set out in the Local Transport Plan.
Alternative options considered
4.1The proposals seek to effect works according to priority based on an assessment of condition that also reflects general safety. It is essential to have a large range of schemes is essential in order to minimise delay and maximise operational efficiencies. The Annex represents a continual 4 year rolling programme and is updated annually. Given the current financial position the Council faces and the reducing spend on highway maintenance, it would not be appropriate to allocate resources to anything other than that identified through a methodical and objective needs assessment.
5 SUPPORTING INFORMATION
5.1The 2017/18 budget includes £1.637m for the non-routine highway maintenance schemes. This is the level of funding provided via the Department for Transport’s (DfT) Highway Maintenance Capital Funding which is a reduction on last year. This funding allocation is not ring fenced and could in theory be spent according to local needs. However, the clear expectation is that it is used for the purpose intended.
5.2The DfT now also awards Council’s further funding based on their ‘efficiency’ assessments. Councils will be graded in three bands following completion of a self- assessment questionnaire and those in the higher bands will receive, on a sliding scale, up to 100% of the available additional funding based on the assessment of our Unrestricted
bid. In Bracknell’s case the maximum we can expect under this process is £127,000 in the financial year 2017/18.
5.3There is an additional £228,000 from the Council’s own capital programme by way of capitalised revenue for road maintenance and street lighting. This funding is generally used for the schemes within the estates and for footpaths.
5.4The Council also makes additional provision in its revenue budget. The sum included in the 2017/18 budget proposals is circa £2.4m. This is used for routine maintenance purposes on bridges , roads , paths and cycleways, drainage, street lighting, winter service and our 24/7 emergency event response service.
5.5Even with this level of funding, the level of maintenance demand far exceeds available budgets. Accordingly funding has to be targeted. The Local Transport Plan defines how we prioritise spend according to an assessment of need having regard to the condition of the asset. Annex 1 sets out the results of that objective assessment according to road type.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.