Resolved
RESOLVED that the contract to complete the Time Square refurbishment works be awarded to Tenderer A.
Executive decided this item on Tuesday 16 April 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the contract to complete the Time Square refurbishment works be awarded to Tenderer A.
2.1That the Restricted Annex is noted and that the contract to complete the Time Square works is awarded to Tenderer A.
3.1To progress Time Square refurbishment and increase the occupancy capacity in Time Square which will help unlock the town centre regeneration by releasing Seymour House.
3.2To enable the Council to reduce the number of buildings it currently occupies in the Town Centre.
3.3To enable the Council to amalgamate all its customer facing services in one building.
3.4To address the backlog of maintenance and urgent repairs required in Time Square.
4.1A reduced scope of works for Time Square was considered which would be self funding through an Invest to Save bid. However this would only address a proportion of the outstanding maintenance and there would still be the need to carry out extensive works at some point in the future. There would also not be the opportunity to optimise the increase in occupation of Time Square. Consequently the Council would be unable to release either Amber House or Ocean House. Therefore this option was rejected.
5 SUPPORTING INFORMATION
5.1The appointed design team (Ridge and Partners LLP) have prepared and issued the tender package. The estimated project cost was prepared by Ridge & Partners LLP
1 Project and is £3.62m (estimate report No 8 dated 12 February 2013 for the construction works). This includes the cost for the refurbishment of Easthampstead House ground floor.
5.2The contract is to complete the refurbishment of Time Square and the Ground Floor of Easthampstead House (EH) to enable Corporate ICT to be relocated into EH. The contract includes all move management throughout; to enable the work to progress through the building while it remains occupied and fully functioning. It will ultimately allow for restacking the services when the works programme is complete to co locate the departments closer together in the building.
5.3The following is a summary of the works included:
Building Fabric: Car park sealed and insulated Balcony work to repair seals Window gasket replacements
Internal Works: Remove partitions and rebuild offices Replace ceilings and lighting Provide insulation panelling in the window units
Mechanical Works: Heating and cooling replacement Ventilation and domestic services
Move Management: Vacate each wing as required to enable the works Finally relocate all departments as per floor plan Transfer staff from Ocean house
Easthampstead House: Internal works to accommodate Corporate ICT
5.4The proposed date for the award of the works contract is May 2013
Selection process
5.4Ridge and Partner LLP acted as our agents through the pre-contract stages, to prepare the tender documents and coordinate the tender process. The works contract was advertised on the South East Business Portal; being below the public Contracts regulations threshold it did not need to be advertised in the OJEU as well.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Award of the Works Contract Time Square and Easthampstead HouseReport | 76 KB | DownloadRead as text |
Follow Executive at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2024 | Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... | Noted | Open |
| 17 Sep 2024 | Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... | Agreed | Open |
| 17 Sep 2024 | Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. | Approved | Open |
| 17 Sep 2024 | Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... | Noted | Open |
| 17 Sep 2024 | Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.