Resolved
RESOLVED that the contract for Phase 3 of the expansion of Crown Wood Primary School be awarded to the preferred supplier subject to the final lump sum not exceeding the amount set out in section 1.9 of the Confidential Appendix.
Executive decided this item on Tuesday 16 April 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the contract for Phase 3 of the expansion of Crown Wood Primary School be awarded to the preferred supplier subject to the final lump sum not exceeding the amount set out in section 1.9 of the Confidential Appendix.
1.1The purpose of the report is to seek approval to award the contract for Phase 3 of the expansion of Crown Wood Primary School under the Education Capital Programme previously approve by the Executive.
2.1That the Executive approves the award of contract for Phase 3 of the expansion of Crown Wood Primary School to the preferred supplier subject to the final lump sum not exceeding the amount set out in section 1.9 of the Confidential Appendix.
3.1The value of this contract constitutes a Key Decision under the Council’s Contract Standing Orders, and Executive approval is required.
3.2The project to expand Crown Wood Primary school was previously approved as part of the Education Capital Programme and the cost of the project is already budgeted for.
4.1A masterplan has been undertaken to identify different options for the expansion of the school buildings which has been subject to consultation and agreement with the Headteacher and Governing Body.
4.2Doing nothing is not an option because the Council has a statutory duty to provide sufficient pupil places.
5. SUPPORTING INFORMATION
5.1The Council’s approved capital programme includes a range of schemes in schools that are designed to meet the statutory duty to provide sufficient school places. Education related elements of the programme are funded from various sources including Basic Need Grant from the government, Section 106 developer contributions and the Council’s own resources.
5.2The expansion of Crown Wood primary school forms part of the Education Capital Programme approved by the Executive in February 2012 and is also set out in the school Capacity Strategy approved by the Executive in October 2012. Unestricted
Crown Wood School
5.3The expansion of Crown Wood Primary School commenced in 2010, and the school is being expanded from 323 to 630 places or 2 Forms of Entry (FE) to 3 FE. This expansion is required meet the demand for additional pupil places in South Bracknell. The Phase 3 works will comprise of the demolition of the old modular KS2 part of the school, replacing it with a new 2 storey building and additional parking, and play space.
5.4Phases 1 and 2 were completed in 2010 and 2011 respectively, and Phase 3 forms the final phase of the expansion of this school. The development has been phased to keep pace with pupil numbers in the school as they move up from the intake (Reception) year through to Year 6.
5.5The contractor has been selected on the basis of best value for money through the Council’s established tender evaluation process. The tender returns have been evaluated 40% quality and 60% price. The evaluation score summaries can be found in Table Two of the Confidential Appendix A.
Costs and Funding
5.6The approved Education Capital Programme includes sufficient funding to meet the full cost of this contract and all other works associated with creating new school places in the current financial year.
5.7As schemes are firmed up through the verification of demand for places, design, planning and tendering, there will be instances where budget adjustments are required to align funding to revised costs. The Council’s Financial Regulations provide the framework for managing the authority's Capital Programme and these require any changes to the approved budget to be agreed by Full Council which ordinarily discusses such matters in December and June.
5.8In order to effectively manage the building programme, the Education Capital Programme Board is used to regularly review scheme updates and is used to endorse proposed self balancing budget adjustments in advance of a Full Council decision.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Education Capital Programme: Crown Wood Primary School award of contractReport | 74 KB | DownloadRead as text |
Follow Executive at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2024 | Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... | Noted | Open |
| 17 Sep 2024 | Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... | Agreed | Open |
| 17 Sep 2024 | Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. | Approved | Open |
| 17 Sep 2024 | Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... | Noted | Open |
| 17 Sep 2024 | Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.