RESOLVED that: i. the scope and programme for Blue Mountain Learning Village as per paragraphs 5.12 and 5.13 of the Chief Executive’s report be approved. ii. the funding model as per Appendix 3 of the Chief Executive’s Report for the delivery of the Learning Village after noting the dependencies and risks (paragraphs 5.14 to 5.39 of the Chief Executive’s report) be agreed iii. the site acquisition in principle with the land owner of the Blue Mountain site as laid out in Appendix 4 of the Chief Executive’s report subject to the due diligence to be completed by the Council’s property and legal team be approved iv. the Leader be requested to arrange that the decision relating to the terms of acquisition (and disposal) of land at Blue Mountain be taken by the Executive Member for Transformation and Finance. v. the Procurement Plan in Appendix 2 of the Chief Executive’s report for the use of the Improvement Efficiency South East (IESE) framework to procure the contractor for pre-construction services and main works for the Learning Village be approved
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1.1The purpose of the report is to seek approval of the delivery strategy for the Learning Village (a nursery, two form entry primary and seven form entry secondary with post- 16 all through school) and community facilities for the site at Blue Mountain.
Recommendations
That the Executive:
2.1Approve the scope and programme for Blue Mountain Learning Village as per paragraphs 5.12 and 5.13 of this report.
2.2Agree the funding model as per Appendix 3 (Restricted) for the delivery of the Learning Village after noting the dependencies and risks (paragraphs 5.14 to 5.39).
2.3Approve the site acquisition in principle with the land owner of the Blue Mountain site as laid out in Appendix 4 (Restricted), subject to the due diligence to be completed by the Council’s property and legal team.
2.4That the Leader be requested to arrange that the decision relating to the terms of acquisition (and disposal) of land at Blue Mountain be taken by the Executive Member for Transformation and Finance.
2.5Approve the Procurement Plan in Appendix 2 for the use of the Improvement Efficiency South East (IESE) framework to procure the contractor for pre-construction services and main works for the Learning Village.
Reasons for recommendation
3.1The Blue Mountain Programme is a priority for Bracknell Forest Council. The programme will deliver statutory school places required in the Borough alongside meeting the need for new housing and the associated community facilities. The strategy for this programme requires Executive approval.
Alternative options considered
4.1Doing nothing is not an option because the Council has a statutory duty to provide sufficient pupil places. A viable alternative site for a secondary school is not available.
1 Recommended Option
4.2On the assumption that a commercial deal between the land owner of the Blue Mountain site and the Bracknell Town Football Club will be made, a Learning Village co-located with the football club is the preferred option for the programme. However, the co-location is dependent upon several external factors including a commercial element between the football club and the land owner; the football club will need to provide funding for its re-location and the new facilities; shared provision will need to be operationally viable for both the school and the football club.
Default Option
4.3In the event that the option for the Learning Village and Bracknell Town Football Club co-location is not achievable, the default option will be to deliver the Learning Village by September 2017 without co-location.
5. SUPPORTING INFORMATION
Background
5.1The borough is keeping pace with changing times and is in the process of delivering several regeneration and development schemes. Recent years have already seen developments across the Borough, including the construction of the new Garth Hill College and significant improvements to the railway station. A new Post 16 Centre has been built at Edgbarrow School in Crowthorne, and new neighbourhoods have developed and been established at Jennett’s Park and The Parks in Bracknell.
5.2Further plans include regeneration of the town centre, which will attract many new businesses and consumers. The proposed development of new neighbourhoods at Amen Corner, TRL, Warfield and Blue Mountain sites will inject new vibrancy to an already thriving population of Bracknell Forest. These developments form part of the national planning policy for the borough to meet its housing need. This means providing additional homes within the Borough-wide Site Allocations Local Plan (SALP), which was adopted by the Council in July 2013, following extensive consultation and consideration. New dwellings at Blue Mountain as well as at other sites within North Bracknell will create a deficit of secondary and primary school places from September 2016. The challenge for the council is to provide the right number of school places to meet the demand.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.