RESOLVED that: i. The progress to date on the community centre and health & wellbeing hub in partnership with the Care Commissioning Group (CCG) is noted and the timetable in paragraph 5.23 of the Director: Place, Planning & Regeneration’s report is agreed. ii. the community centre budget of up to £2.4m is agreed as per paragraph 5.10 of the Director: Place, Planning & Regeneration’s report ; the development cost of the health centre to be met by the CCG/NHS as noted in paragraph 5.1 of the Director: Place, Planning & Regeneration’s report. iii. to forward fund up to £4.6m (including ancillary costs as per paragraph 5.10 of the Director: Place, Planning & Regeneration’s report ),the capital costs of the Health part of the building, on the basis that the consequent capital financing costs will be matched by long term rental income from Health. iv. the Procurement Plan (paragraph 5.25 of the Director: Place, Planning & Regeneration’s report ) for the community centre and health care hub in Appendix C (Restricted), is approved.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1.1The purpose of this report is to provide an update on the progress of the Blue Mountain Community and Health Care Hub scheme and the supporting financial summary. The project is in partnership with the East Berkshire Clinical Commissioning Group (CCG). A decision is required to proceed to the next stage of the project, which includes completion of the heads of terms, appointment of a design team for completion of RIBA Stage 3 design and applying for planning permission. The CCG position on funding the health provision is summarised within the body of the report. A procurement plan tailored to the specific requirements of this project requires approval.
Recommendations
That the Executive:
2.1Note the progress to date on the community centre and health & wellbeing hub in partnership with the Care Commissioning Group (CCG) and agree the timetable in paragraph 5.23.
2.2Approve the community centre budget of up to £2.4m as per paragraph 5.10; the development cost of the health centre to be met by the CCG/NHS as noted in paragraph 5.11.
2.3Agree to forward fund up to £4.6m (including ancillary costs as per paragraph 5.10), the capital costs of the Health part of the building, on the basis that the consequent capital financing costs will be matched by long term rental income from Health.
2.4Approve the Procurement Plan (paragraph 5.25) for the community centre and health care hub in Appendix C (Restricted).
Reasons for recommendation
3.1The Blue Mountain programme consists of Binfield Learning Village all-through school for 1851 pupils (operated as King’s Academy Binfield) and community centre required alongside 400 new homes at the Blue Mountain site. In the first phase, the Council has delivered the new school which opened in September 2018. The next phase requires the Council to deliver the community hub in line with the ongoing building of the new housing development being undertaken by a Bloor and Linden Homes partnership.
3.2The development of the Blue Mountain site in accordance with the Site Allocation Local Plan has been previously approved through the Executive process, which included a full Council consultation. Planning Permission for the new all-through school and outline planning permission for the standalone community centre was granted in June 2016. Subsequently, the Council received the land from the former site owner on the basis that an all-through school and community centre will be delivered by the Council. The residential parcel of land was part of the same outline planning permission, which was subsequently bought by Bloor Homes who are now building new homes in partnership with Linden Homes.
3.3The forecast increase in the population of Binfield and the surrounding areas would require additional healthcare facilities for the local community. The Council is working in partnership with the East Berkshire Clinical Commissioning Group to develop a joint community and health & wellbeing centre. A joint centre will provide enhanced benefits to the local community. The scheme will also deliver a “one public estate objective” with BFC, CCG and primary care practices all sharing a facility which will be owned by BFC.
Alternative options considered
4.1The proposed health and wellbeing centre is subject to NHS funding. If adequate funding is not provided, the health facility will not be affordable. In this event, the Council will revert to building a standalone community centre to meet the Council’s legal obligation, and meet the needs of the new community. At that stage, some redesigning of the scheme will be needed.
5 SUPPORTING INFORMATION
Background
Site Allocation Local Plan and Planning Permission
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.