RESOLVED that 1 The addendum to the Learning Village Procurement Plan in Appendix 2 to create an option for combining the procurement of the refurbishment works to the existing club house building earmarked for community facilities with the previously approved procurement plan authorising the use of the Improvement Efficiency South East (IESE) framework for the Learning Village be approved. a) waive contract standing orders such as to permit the decision for the award of the contracts for pre-construction services and the main contract (including enabling works) in relation to Binfield Learning Village at Blue Mountain to be taken by an Executive Committee. b) requests the Leader to delegate the decision to be taken by the Executive Committee. 2 The decisions be reported to the next available meeting of the Care Portfolio Review Group .
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1.1Further to the approval of the delivery strategy for the Learning Village and Community Facilities on 21 October 2014, the purpose of this report is to agree the process for awarding the contracts for the pre-construction services and main works for Binfield Learning Village at Blue Mountain using the IESE framework. The report proposes that the decision, as to contract award, be taken by the Executive Committee approved by the Leader.
Recommendations
That the Executive:
2.1approve the addendum to the Learning Village Procurement Plan in Appendix 2 to create an option for combining the procurement of the refurbishment works to the existing club house building earmarked for community facilities with the previously approved procurement plan authorising the use of the Improvement Efficiency South East (IESE) framework for the Learning Village.
2.2a) waive contract standing orders such as to permit the decision for the award of the contracts for pre-construction services and the main contract (including enabling works) in relation to Binfield Learning Village at Blue Mountain to be taken by an Executive Committee.
b) requests the Leader to delegate the decision to be taken by the Executive Committee.
2.3require the decisions be reported to the next available meeting of the Care Portfolio Review Group.
Reasons for recommendation
3.1The Binfield Learning Village at Blue Mountain is a priority for Bracknell Forest Council. The programme will deliver statutory school places required in the Borough alongside meeting the need for new housing and the associated community facilities.
3.2The development of the Blue Mountain site in accordance with the Site Allocation Local Plan has been previously approved through the Executive process, which included a full Council consultation.
3.3The new Learning Village is due to commence from September 2017, which means that the current timetable has very limited contingency. The programme also has several external dependencies, which could negatively impact the programme delivery.
3.4The scope, timetable, funding model and the procurement plan for the Learning Village was approved by the Executive in October 2014. An addendum to the procurement plan to include the use of the same procurement process for the refurbishment design and main works for providing community facilities requires Executive approval.
3.5Following the decision taken by the Executive on 21 October 2014 to use the IESE Framework, the next decision to appoint a contractor using the IESE framework for pre-construction services is required in April 2015. The procurement evaluation activities will continue into early April 2015. This will not leave sufficient time for a report to be taken to the full Executive due to the timings of the Executive meetings in 2015; hence it is recommended for the Executive to waive the Contract Standing Orders and for the Leader to delegate the decision to award contracts to an Executive Committee.
Alternative options considered
4.1A decision to award the contract for pre-construction services and main works (including enabling works) could be taken by the Executive after it reconvenes in June 2015, which would lead to a significant delay to the delivery of the programme. As a result, the new Learning Village would most likely open a year later in September 2018. Over and above, external dependencies could further delay the programme delivery. The cost of delivering the programme would also increase during this period due to inflation. In addition, there would be the added risk of not being able to use the current IESE framework rates, which are due for renewal in July 2015 and are likely to increase as a result of the current market situation.
4.2The Executive could convene a special meeting to approve the contract awards within the timescale constraints of the programme. However, this approach may be difficult to achieve due to the restrictions around the election period.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.