Resolved
RESOLVED that the use of Special Urgency Procedures by the Leader to revise the award of contract for the construction works to create new classrooms at Cranbourne Primary School be noted.
Executive noted this item on Tuesday 31 March 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the use of Special Urgency Procedures by the Leader to revise the award of contract for the construction works to create new classrooms at Cranbourne Primary School be noted.
2.1That the use of Special Urgency Procedures by the Leader to revise the award of contract for the construction works to create new classrooms at Cranbourne Primary School be noted.
3.1To comply with Contract Standing Order 7 in relation to the reporting of any waiver of Contract Standing Orders approved by the Leader in relation to contracts valued at over £400k.
4.1None, as to have delayed the decision until the next meeting of the Executive would have impacted significantly on the works programme and jeopardised the timely delivery of the new classrooms.
5 SUPPORTING INFORMATION
5.1The works to Cranbourne Primary School form part of the Education Capital Programme approved by the Executive in February 2013 and is also set out in the Unrestricted
school Capacity Strategy approved by the Executive in October 2013. The works include demolition of the existing pre-school classroom, reception classroom and creation of 3 new classroom areas including associated toilets, kitchen and storage areas.
Reason for Urgency
5.2Urgency Procedures in the Council’s Constitution cover both “General Exception” and “Special Urgency” procedures as defined in the Access to Information Procedure Rules where there is a need to make decisions at short notice outside of the established decision making process where special circumstances apply. This decision was taken in accordance with the General Exception procedure.
5.3Urgency arose in this case following issues with the original tenderer who had been awarded the contract which came to light after the contract award decision by the Executive in September 2014. The time required to follow the established decision making process to revise the award of the contract would have resulted in an unacceptable delay to the construction on site and mean that classrooms would not be completed before they are needed at the beginning of the academic year in September 2015.
5.4Doing nothing was not an option because the Council has a statutory duty to provide sufficient pupil places and there is insufficient time to undertake a new tendering exercise and deliver the required classrooms for September 2015.
Call In Period
5.5The urgency also meant that the call-in period after the award decision has been waived with the consent of the Mayor in order to serve a letter of intent on the contractor to achieve the key programme dates. The Mayor was satisfied that call-in would have seriously prejudiced the Council’s and the public’s interests.
Timescales
5.6The Works are planned to start on site in March 2015 for completion of key classrooms by September 2015 and overall completion of all areas later during the 2015 autumn term.
Costs and Funding
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Cranbourne Award of Contract: Special Urgency ProceduresReport | 85 KB | DownloadRead as text |
Follow Executive at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2024 | Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... | Noted | Open |
| 17 Sep 2024 | Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... | Agreed | Open |
| 17 Sep 2024 | Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. | Approved | Open |
| 17 Sep 2024 | Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... | Noted | Open |
| 17 Sep 2024 | Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.