RESOLVED that the contract for the construction works for the new classrooms at Cranbourne Primary School under the Education Capital Programme, previously approved by the Executive, be awarded to Tenderer A as detailed in Appendix A of the Director of Children, Young People and Learning’s report, subject to the final lump sum not exceeding the amount set out in paragraph 18 of the restricted Appendix A attached to the Director of Children, Young People and Learning’s report.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1.1The purpose of the report is to seek approval to award the contract for the construction works for the new classrooms at Cranbourne Primary School under the Education Capital Programme previously approved by the Executive.
Recommendation
2.1That the Executive approves the award the contract for the construction works for the new classrooms at Cranbourne Primary School under the Education Capital Programme previously approved by the Executive to Tender A, subject to the final lump sum not exceeding the amount set out in paragraph 18 of the attached Restricted APPENDIX A.
Reasons for recommendation
3.1The value of this contract requires Executive approval under the Council’s Contract Standing Orders.
Alternative options considered
4.1Doing nothing is not an option because the Council has a statutory duty to provide sufficient pupil places.
5. SUPPORTING INFORMATION
Background
5.1The works to Cranbourne Primary School form part of the Education Capital Programme approved by the Executive in February 2013 and is also set out in the school Capacity Strategy approved by the Executive in October 2013.
The Works
5.2The works will include demolition of the existing pre-school classroom, reception classroom and lean-to storage areas and the creation of 3 new classroom areas including associated toilets, kitchen and storage areas.
5.3The recommended contractor has been selected on the basis of best value for money through the Council’s established procurement and tender evaluation process. Unrestricted
Timescales
5.4The Works are planned to start on site in November 2014 for completion by the start of the September 2015 academic year.
Costs and Funding
5.5Funding for this contract has already been approved by the Executive as part of the Education Capital Programme, and the funding envelope includes DfE grants for Basic Need and Schools Capital Maintenance, plus a capital receipt from the sale of the former caretaker’s house.
6. ADVICE RECEIVED FROM STATUTORY AND OTHER OFFICERS
Borough Solicitor
6.1The value of the contract is below the Public Contracts Regulations threshold, and the Council’s contract standing orders have been complied with in the procurement of it.
Borough Treasurer
6.2The Borough Treasurer is satisfied that the Council has allocated sufficient resources to finance the proposed contract.
Equalities Impact Assessment
6.3All new construction will be fully accessible to disabled pupils, staff and visitors.
Strategic Risk Management Issues
6.4Strategic Risk Management Issues are set out in the attached Restricted APPENDIX A.
Consultation
Principal Groups Consulted
7.1The Headteacher, Governing Body, pupils, and neighbours of Cranbourne Primary School.
Method of Consultation
7.2The Headteacher and Governors have been consulted throughout the design stage development and attended meetings and via presentations. Unrestricted
7.3A representative consultation was undertaken with pupils across all year groups by way of a survey questionnaire.
7.4Pre-planning public consultation was held in March 2013 which included leaflet drops to all neighbouring properties. An open afternoon/evening was also held at the school where the plans and drawings were on display and the designers, Headteacher and Council officers were available to deal with queries and answer questions.
Representations Received
7.5In total 91.8% of those consulted supported the proposed development, and the feedback and comments received were fed back to the design team and incorporated in the final designs.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.