RESOLVED that the minutes of the meeting of the Joint Waste Disposal Board held on the 15 January 2015 be approved as a correct record and signed by the Chairman. Arising on the minutes, it was noted: Minute 21 – It was agreed that a date would be set for members to meet at the Sutton Courtney MRF. Minute 29 – It was agreed to progress a date to meet with DEFRA. Minute 29 – It was confirmed that the Fire System works were ongoing. Minute 29 – It was confirmed that a report reviewing the trial described in paragraphs 5.25 to 5.30 of the re3 Strategic Waste Manager’s report and recommendations relating to changes to the Service Delivery Plan, would be brought back to the Board at the next meeting. Minute 32 - It was confirmed that future reports would be amended to include two columns showing recycling rates with and without the recycling of bottom ash waste.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
Present: Bracknell Forest Borough Council Councillor Mrs Dorothy Hayes MBE Councillor Iain McCracken
Reading Borough Council Councillor Paul Gittings
Wokingham District Council Councillor Anthony Pollock Councillor Angus Ross
Officers Oliver Burt, re3 Project Manager Anna Fowler, re3 Communications and Marketing Officer Steve Loudoun, Bracknell Forest Council Mark Smith, Reading Borough Council Josie Wragg, Wokingham Borough Council
Apologies for absence were received from: Councillor Liz Terry, Reading Borough Council
26. Declarations of Interest There were no declarations of interest.
27. Minutes of the Meeting of the Joint Waste Disposal Board RESOLVED that the minutes of the meeting of the Joint Waste Disposal Board held on 16 October 2015 be approved as a correct record and signed by the Chairman.
Minute 21 – It was agreed that a visit to the Sutton Courtney MRF would be arranged for later in the year.
28. Urgent Items of Business There were no urgent items of business.
29. re3 Partnership Progress Update Report The Board considered a report providing an update on the progress made in relation to the shared re3 PFI Contract since its last meeting on 16 October 2015. The report covered updates on: street sweepings, correspondence with Government, insurance matters, the re3 Material Reclamation Facility (MRF), business continuity and contingencies and changes to service delivery plans.
It was reported that, following work to ensure the processing of street sweepings met with approval from the Environment Agency, a two month trial during October and November 2015, had collected 718 tonnes of street sweepings. Of which, 75-80% had been recycled. It was stressed that the composition of the sweepings would change through the year and the recycling rates would fluctuate as the trial progressed. To date no response had been received in response to a letter sent to Defra relating to the strategic requirements of local government and the ways that the Government might create the conditions within which councils and the waste industry could thrive. It was agreed that rather than continuing to correspond with Defra to minimal effect the possibility of arranging a meeting with Defra so that these concerns could be put directly to representatives would be explored.
Further work had taken place to establish more accurate costs for work to improve the existing fire system. Estimates now placed the cost of the work as being approximately £450,000. It was envisaged that this shortfall could be funded from the Maintenance Reserve Fund however the situation would need to be carefully considered.
A workshop had been held to enable the testing of business continuity plans and emergency plans were now being updated to ensure they continued to be fit for purpose.
RESOLVED that:
i. The progress made over the last quarter in relation to the aspects of contract delivery described in the re3 Strategic Waste Manager’s report be noted ii. The changes described in paragraphs 5.25 to 5.30 of the re3 Strategic Waste Manager’s report be trialled iii. A report reviewing the trial described in paragraphs 5.25 to 5.30 of the re3 Strategic Waste Manager’s report and recommendations relating to changes to the Service Delivery Plan be brought back to the Board in six months time
30. re3 Proposed Marketing and Communication Activity for 2016 Anna Fowler, re3 Marketing and Communications Officer, attended the meeting to present a report setting out the proposed marketing and communications activity for 2016.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.