Resolved
RESOLVED that the content of this report be noted.
Joint Waste Disposal Board noted this item on Friday 8 April 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the content of this report be noted.
2.1That Members note the contents of this report.
3.1Not applicable.
4.1This report contains no decisions for Members, only briefing.
5 BACKGROUND INFORMATION
5.1The re3 PFI Contract commenced on December 4 th 2006 following over a year of intensive negotiations. The Contract was initially valued at £611m over its 25 year term.
5.2The re3 councils were successful in securing £37m support for the project through the Private Finance Initiative (PFI). In cash terms, as the councils chose to receive the support throughout the life of the contract, the support equates to £74m and very broadly to £1m per council per annum.
5.3The current annual cost of the contract is £26m. Management of the Contract (additionally including internal and statutory reporting, financial management and monitoring of KPIs) is delivered by 2.6 FTE.
5.4Recommendation 1 in the report on the 2015 audit of the re3 contract advises that there is a need for guidance for Members and senior officers. It says:
‘…it would be helpful to produce a consolidated guidance document which explains the relationship between elements of the Contract’.
5.5The recommendation was accepted, by the prevailing Project Director and a timetable for the production of such guidance set for the first Joint Waste OFFICIAL
Disposal Board meeting of 2016.
5.6This report contains advice on the Payment Mechanism, the contract document which sets out the calculation of the Unitary Charge payable by the Councils to the Contractor.
Guidance
5.7This report provides a consolidated source of guidance for Members and Senior Officers of the re3 councils on the Payment Mechanism. The report constitutes neither legal advice nor advice on managing the contract or Contractor.
5.8The monthly Unitary Charge is based upon a Waste Flow Forecast (of tonnage) that is agreed between the Councils and the Contractor in advance of the contract year.
5.9The Unitary Charge comprises the following payments:
a) the Baseline Payment b) the Recycling Payment c) the Composting Payment d) the Energy Recovery Payment e) the Landfill Payment f) the Beneficial Use Payment g) the CA Site Payment h) the Waste Minimisation Fee i) the Monthly Estimated Recyclate Income Compensation Payment j) Passthrough Costs k) the Extended Hours Payment l) the Rejected Load Payment m) the Contamination Payment n) the First Annual Reconciliation Payment and o) the Second Annual Reconciliation Payment Less i. Excess Profit Share in respect of the previous Contract Year ii. the Royalty Payment and iii. the Quarterly Reconciliation Payment
Baseline Payment
5.10The Baseline Payment is applicable to every tonne of contract waste that is delivered to the re3 Project Facilities (the Transfer Stations, the MRF and the Longshot Lane and Smallmead Recycling Centres/HWRCs).
5.11The Baseline Payment is subject to a guaranteed tonnage of 190,000 tonnes per year. The guarantee is required because the Baseline Payment is the means of the Councils repaying the costs of building the re3 facilities to the Contractor.
5.12As noted in the Contract Guidance report, the re3 councils secured PFI credits OFFICIAL
in order to fund the construction costs, which are spread over the life of the contract.
5.13Since commencement of the contract in 2006, annual contract waste has only been below the guaranteed threshold once – in 2012/13 during the economic crisis.
5.14Contract tonnage in excess of the 190,000 tonne threshold is charged in banded rates, which are significantly reduced costs per tonne.
Recycling Payment
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Contract Guidance ReportReport | 246 KB | DownloadRead as text |
Follow Joint Waste Disposal Board at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Jun 2026 | Election of ChairRESOLVED that Councillor Finn McGoldrick be elected Chair of the Board for the municipal year 2026/27. | Decided | Open |
| 11 Jun 2026 | Election of Vice-ChairRESOLVED that Councillor Stephen Newton be elected Vice-Chair of the Board for the municipal year 2026/27. | Decided | Open |
| 11 Jun 2026 | re3 Progress ReportRESOLVED that 1 the contents of this report be noted. 2 a proposal on the simplification of the DIY charging structur... | Noted | Open |
| 11 Jun 2026 | re3 Strategy ReportRESOLVED that 1 the re3 Strategy 2026–2031 be approved and progressed through each partner council’s decision-making ... | Approved | Open |
| 11 Jun 2026 | re3 Finance Report - part oneRESOLVED that the year end financial position for FY25/26 be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.