RESOLVED that; i) the outturn capital expenditure and in particular the key variances identified in paragraph 5.4 of the Borough Treasurer’s report be noted. ii) the carry forward of £50.602m from the 2016/17 capital programme to 2017/18 including £0.236m relating to projects approved in 2015/16 be approved (see paragraph 5.5 of the Borough Treasurer’s report). iii) the financing of capital expenditure as shown in Table 2 of the Borough Treasurer’s report be noted.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
a) Notes the outturn capital expenditure and in particular the key variances identified in paragraph 5.4. b) Approves the carry forward of £50.602m from the 2016/17 capital programme to 2017/18 including £0.236m relating to projects approved in 2015/16 (see paragraph 5.5). c) Notes the financing of capital expenditure as shown in Table 2.
Reasons for recommendations
3.1The reasons for the recommendations are set out in section 5 below.
Alternative options considered
4.1Not Applicable
5 SUPPORTING INFORMATION
Outturn Capital Expenditure 5.1 The capital programme for 2016/17 consisted of £127.594m on projects and programmes. The projected outturn is £76.300m (60% of approved budget). These figures remain subject to change, pending external audit. However, no significant movement is anticipated. The capital programme is monitored on a monthly basis by officers and reported formally to the Corporate Management Team on a quarterly basis and through to Members in the Quarterly Service Reports.
5.2Table 1 summarises the outturn position for schemes managed by Service Departments based on latest information available. The detailed monitoring sheets are provided at Annexes A-D. Unrestricted
Table 1: Capital outturn for each Service
Annex Service Approved Estimated Carry (Under) budget Outturn forward /Over spend £’000 £’000 £’000 £’000 A Adult Social Care, Health & 17,837 15,742 1,515 -580 Housing B Children, Young People & 42,580 17,389 25,191 0 Learning C Council Wide 30,912 16,194 14,700 -18 C Corporate Services 5,140 4,767 299 -74 D Environment, Culture & 31,125 22,208 8,897 -20 Communities Total Capital Programme 127,594 76,300 50,602 -692 % spent 60%
5.3The total carry forwards requested by service departments amount to £50.602m. Many of the projects are either close to being completed or are contractually committed and underway.
5.4According to Financial Regulations, departments are required to manage their budgets to ensure that the overall department capital programme is not exceeded. As can be seen above the overall capital programme is underspent against budget and there have been some variances which are required to be drawn to the attention of Members (>£25,000). The key budget variances are detailed below.
Adult Social Care, Health and Housing Waymead Flats Refurbishment (Invest-to-Save - £580k underspend) – After further feasibility studies the scheme was considered no longer viable and was stopped.
Corporate Services Disposal of Land at Sandy Lane (£70k underspend) – A budget was allocated to meet the potential costs of the disposal of Sandy Lane depending on the agreed sale of the land. The direct sale to a developer resulted in much lower disposal costs
5.5In accordance with Financial Regulations, funding for capital projects is automatically permitted to roll forward for one year. After this, funding may only be rolled forward if work on a project has commenced on-site, unless the approval of Members has been obtained. Projects totalling £0.236m (as detailed in Annex E) carried forward from 2015/16 have not yet been contractually committed. However, work is planned to commence on these schemes in the near future. Consequently, it is requested that these funds be carried forward into 2017/18.
Use of capital resources 5.6 Capital expenditure can be financed from four main sources. These are Developers’ Contributions (S106 monies and Community Infrastructure Levy), Grants, Capital Receipts and Borrowing. Unrestricted
Capital Receipts
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.