Capital Programme Outturn 2016/17

Noted Executive 3 papers

Executive noted this item on Tuesday 18 July 2017. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

RESOLVED that; i) the outturn capital expenditure and in particular the key variances identified in paragraph 5.4 of the Borough Treasurer’s report be noted. ii) the carry forward of £50.602m from the 2016/17 capital programme to 2017/18 including £0.236m relating to projects approved in 2015/16 be approved (see paragraph 5.5 of the Borough Treasurer’s report). iii) the financing of capital expenditure as shown in Table 2 of the Borough Treasurer’s report be noted.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Executive

Recommendations

2.1That the Executive:

a) Notes the outturn capital expenditure and in particular the key variances identified in paragraph 5.4. b) Approves the carry forward of £50.602m from the 2016/17 capital programme to 2017/18 including £0.236m relating to projects approved in 2015/16 (see paragraph 5.5). c) Notes the financing of capital expenditure as shown in Table 2.

Reasons for recommendations

3.1The reasons for the recommendations are set out in section 5 below.

Alternative options considered

4.1Not Applicable

5 SUPPORTING INFORMATION

Outturn Capital Expenditure 5.1 The capital programme for 2016/17 consisted of £127.594m on projects and programmes. The projected outturn is £76.300m (60% of approved budget). These figures remain subject to change, pending external audit. However, no significant movement is anticipated. The capital programme is monitored on a monthly basis by officers and reported formally to the Corporate Management Team on a quarterly basis and through to Members in the Quarterly Service Reports.

5.2Table 1 summarises the outturn position for schemes managed by Service Departments based on latest information available. The detailed monitoring sheets are provided at Annexes A-D. Unrestricted

Table 1: Capital outturn for each Service

Annex Service Approved Estimated Carry (Under) budget Outturn forward /Over spend £’000 £’000 £’000 £’000 A Adult Social Care, Health & 17,837 15,742 1,515 -580 Housing B Children, Young People & 42,580 17,389 25,191 0 Learning C Council Wide 30,912 16,194 14,700 -18 C Corporate Services 5,140 4,767 299 -74 D Environment, Culture & 31,125 22,208 8,897 -20 Communities Total Capital Programme 127,594 76,300 50,602 -692 % spent 60%

5.3The total carry forwards requested by service departments amount to £50.602m. Many of the projects are either close to being completed or are contractually committed and underway.

5.4According to Financial Regulations, departments are required to manage their budgets to ensure that the overall department capital programme is not exceeded. As can be seen above the overall capital programme is underspent against budget and there have been some variances which are required to be drawn to the attention of Members (>£25,000). The key budget variances are detailed below.

Adult Social Care, Health and Housing Waymead Flats Refurbishment (Invest-to-Save - £580k underspend) – After further feasibility studies the scheme was considered no longer viable and was stopped.

Corporate Services Disposal of Land at Sandy Lane (£70k underspend) – A budget was allocated to meet the potential costs of the disposal of Sandy Lane depending on the agreed sale of the land. The direct sale to a developer resulted in much lower disposal costs

5.5In accordance with Financial Regulations, funding for capital projects is automatically permitted to roll forward for one year. After this, funding may only be rolled forward if work on a project has commenced on-site, unless the approval of Members has been obtained. Projects totalling £0.236m (as detailed in Annex E) carried forward from 2015/16 have not yet been contractually committed. However, work is planned to commence on these schemes in the near future. Consequently, it is requested that these funds be carried forward into 2017/18.

Use of capital resources 5.6 Capital expenditure can be financed from four main sources. These are Developers’ Contributions (S106 monies and Community Infrastructure Levy), Grants, Capital Receipts and Borrowing. Unrestricted

Capital Receipts

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
5.a Capital Outturn Annex A-DAppendix 84 KB Download
PDF
5.b Capital Outturn Annex EAppendix 7 KB Download
PDF
Capital Programme Outturn 2016/17Report 235 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 9 attended
PB
Councillor Paul Bettison OBE CONChair, apologies
DG
Councillor Dr Gareth Barnard CONVice-Chair, in the Chair, present
DB
Councillor Dale Birch CONCommittee Member, apologies
MB
Councillor Marc Brunel-Walker CONCommittee Member, present
MD
Councillor Mrs Dorothy Hayes MBE CONCommittee Member, present
PH
Councillor Peter Heydon CONCommittee Member, present
IM
Councillor Iain McCracken CONCommittee Member, apologies
CT
Councillor Chris Turrell CONCommittee Member, present
PP
Priya PatelClerk, expected

On this subject at Bracknell Forest

Search all
  1. Capital Programme Outturn 2016/17This decision
  2. Highways and Transport Capital Programme 2026/27Approved
  3. Capital Programme 2026/27Approved
  4. Highways and Transport Capital Programme 2025/26Approved
  5. Capital Programme 2025/26Approved
  6. Highways and Transport Capital Programme 2024/25Approved

More from Bracknell Forest Executive

All decisions
MeetingDecisionOutcome
17 Sep 2024 Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... Noted Open
17 Sep 2024 Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... Agreed Open
17 Sep 2024 Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. Approved Open
17 Sep 2024 Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... Noted Open
17 Sep 2024 Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies