Resolved
RESOLVED that the performance of the Council over the period from July - September 2018 highlighted in the Overview Report in Annex A of the Chief Executive’s report is noted.
Executive noted this item on Tuesday 18 December 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the performance of the Council over the period from July - September 2018 highlighted in the Overview Report in Annex A of the Chief Executive’s report is noted.
TO: THE EXECUTIVE 18 DECEMBER 2018
COUNCIL PLAN OVERVIEW REPORT Chief Executive
1 PURPOSE OF REPORT 1.1 To inform the Executive of the performance of the Council over the second quarter of the 2018/19 financial year (July - September 2018).
2 RECOMMENDATION 2.1 To note the performance of the Council over the period from July - September 2018 highlighted in the Overview Report in Annex A.
3 REASONS FOR RECOMMENDATION 3.1 To brief the Executive on the Council’s performance, highlighting key areas, so that appropriate action can be taken if needed.
4 ALTERNATIVE OPTIONS CONSIDERED 4.1 None applicable.
5 SUPPORTING INFORMATION
Performance Management 5.1 The Council’s performance management framework provides for the preparation of Quarterly Service Reports (QSRs) by each department. These QSRs provide an update of progress and performance against departmental Service Plans. Quarterly Service Reports 5.2 Executive Portfolio Holders will have received the first quarter QSRs for their areas of responsibility. QSRs are also distributed electronically to all Members, and will be considered by the Overview & Scrutiny Commission and Scrutiny Panels. This process enables all Members to be involved in performance management. Council Plan Overview Report 5.3 The QSRs have been combined into the Council Plan Overview Report (CPOR), which brings together the progress and performance of the Council as a whole. The CPOR enables the Corporate Management Team and the Executive to review performance, highlight any exceptions and note any remedial actions that may be necessary, either from under-performing or over-performing services, across the range of Council activities. 5.4 The CPOR for the second quarter (July - September 2018) is shown at Annex A.
6 ADVICE RECEIVED FROM STATUTORY AND OTHER OFFICERS Borough Solicitor 6.1 There are no specific legal issues arising from this report. Borough Treasurer 6.2 There are no direct financial implications arising from this report. Equalities Impact Assessment 6.3 Not applicable. Strategic Risk Management Issues 6.4 Any specific issues are included in the QSRs and in the CPOR in Annex A. Other Officers 6.5 Not applicable.
7 CONSULTATION Principal Groups Consulted 7.1 Not applicable Method of Consultation 7.2 Not applicable. Representations Received 7.3 None.
Background Papers QSR – Resources – Quarter 2 2018/19 QSR – Environment, Culture and Communities – Quarter 2 2018/19 QSR – Adult Social Care, Health and Housing – Quarter 2 2018/19 QSR – Children, Young People and Learning – Quarter 2 2018/19
Contact for further information Timothy Wheadon, Chief Executive - 01344 345601 [email protected]
Genny Webb, Principal Policy Officer – 01344 352172 [email protected]
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Council Plan Overview ReportReport | 114 KB | DownloadRead as text |
PDF |
CouncilPlanOverviewReportReport | 612 KB | Download |
Follow Executive at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2024 | Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... | Noted | Open |
| 17 Sep 2024 | Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... | Agreed | Open |
| 17 Sep 2024 | Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. | Approved | Open |
| 17 Sep 2024 | Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... | Noted | Open |
| 17 Sep 2024 | Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.