Resolved
RESOLVED that the Integrated Transport Capital Programme for 2019/20 is approved.
Executive approved this item on Tuesday 12 March 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Integrated Transport Capital Programme for 2019/20 is approved.
2.1That the Integrated Transport Capital Programme for 2019/20 (Annex 1) is approved.
3.1To facilitate transport services in line with the Council’s Local Transport Plan 3.
4.1Failure to approve the Integrated Transport Capital Programme would prevent the delivery of local transport services contrary to the requirements set out in the Council’s adopted Transport Policy (LPT3).
5 SUPPORTING INFORMATION
5.1The Integrated Transport Capital Programme is formed to support the adopted Local Transport Plan which sets out the key challenges facing Bracknell Forest through the period 2011-2026. Schemes are developed taking account of wider policy goals alongside strategic and local transport needs. Issues such as deliverability and public impact/acceptability are also reflected within the scheme selection.
5.2Historically, funding for the programme has been made up of an Integrated Transport Grant from Central Government, alongside developer contributions for transport mitigation measures via S106 agreements. However, in addition to the grant allocation (£520k) and S106 funds (£400k), the Council has been successful in securing additional funds from Central Government through the Local Growth Fund and The National Productivity Investment Fund. Both funds are aimed towards implementing transport measures linked to economic growth and carbon reduction with a focus on removing pinch points which unlock regeneration and housing development.
5.3Past successful bids to the Local Growth Fund have included the Warfield Link Road, Coral Reef Junction improvements and the Bracknell town centre accessibility improvements linked to regeneration. More recently, the funds have enabled the A329 London Road Corridor improvements. 5.4 This expanded work programme will continue in 2019/20 as work begins on the latest scheme to be awarded Local Growth Funds - the A3095 corridor improvements. This scheme will include capacity and environmental enhancements linked to current congestion issues and future growth. A total of £8.1m has been secured towards the scheme, made up of Government funding and developer contributions associated with the TRL housing site. This two-year scheme will be further funded within 2020/21 programme.
5.5In addition to Local Growth Funds, a further £3.29m has been secured from the Government’s National Productivity Investment Fund for the dualling of A322 Downshire Way. This scheme will commence in February 2019 and continue into 2020 with remaining funding allocated within the 2020/21 programme.
5.6As well as large scale schemes, the Council continues to implement local improvements that support the Local Transport Plan. These focus on improving access, mobility and travel choice, highway capacity and road space allocation, road safety, residential parking and traffic management.
5.7Annex 1 shows the Integrated Transport Capital Programme for 2019/20. These schemes align with the transport policies and objectives within the Local Transport Plan but with a reduction in grant allocation of £200k (the Executive previously made a decision to prioritise £200k of the Integrated Transport Block toward highway maintenance). This reduced allocation has resulted in a greater need to focus local improvements on identifiable traffic management, accessibility and road safety issues where intervention is considered a priority for the Council.
6 ADVICE RECEIVED FROM STATUTORY AND OTHER OFFICERS
Borough Solicitor
6.1The approval of the Recommendation falls within the decision making remit of the Executive under Part 2, Section 5 of the Council Constitution. Paragraph 6.3 confirms the steps taken to ensure compliance with the Council’s equalities duties under the Equality Act 2010.
Borough Treasurer
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Programme 2019/2020 Integrated TransportReport | 119 KB | DownloadRead as text |
PDF |
Integrated Transport Capital Programme 2019-20 Annex 1Appendix | 22 KB | Download |
Follow Executive at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2024 | Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... | Noted | Open |
| 17 Sep 2024 | Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... | Agreed | Open |
| 17 Sep 2024 | Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. | Approved | Open |
| 17 Sep 2024 | Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... | Noted | Open |
| 17 Sep 2024 | Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.