RESOLVED that i. The overall Highways and Transport Capital Programme for 2020/21 is approved. ii. The highway maintenance funding for 2020/21 is targeted towards the Highway Maintenance Forward Programme (Annex 2 of the Director: Place, Planning and Regenerations report) having due regard to priority, availability of road space and available budget; iii. The implications for resourcing the delivery of the work programmes are noted.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
2.1That the overall Highways and Transport Capital Programme for 2020/21 (Annex 1) is approved;
2.2That highway maintenance funding for 2020/21 is targeted towards the Highway Maintenance Forward Programme (Annex 2) having due regard to priority, availability of road space and available budget;
2.3That the implications for resourcing the delivery of the work programmes are noted (paras 5.13 to 5.15).
Reasons for recommendation
3.1The proposals in this report identify the current highway and transport priorities across the network. The schemes seek to facilitate transport in line with the Council’s Local Transport Plan 3 (LTP3) and ensure that the Council maintains the highway in as good a condition as resources allow, having due regard to the Council’s intervention policy based on network condition.
Alternative options considered
4.1Failure to approve the Highways and Transport Capital Programme would prevent the delivery of the Council’s obligations as a Highway Authority and be contrary to the position set out in the Council’s adopted Transport Policy (LPT3).
4.2Given the necessary reduction in highway maintenance funding levels in previous years, it would not be appropriate to allocate resources to anything other than the priorities identified through methodical and objective needs assessments.
5 SUPPORTING INFORMATION
Transport Programme
5.1The Transport Capital Programme is formed to support the adopted LTP3 which sets out the key transport challenges and opportunities facing Bracknell Forest through the period 2011-2026. Schemes are developed taking account of wider policy goals alongside strategic and local transport needs. Issues such as deliverability and public impact/acceptability are also reflected within the scheme selection. 5.2 Core funding for the 2020/21 programme is made up of an Integrated Transport Grant from Central Government (£720k) alongside developer contributions for transport mitigation measures via S106 agreements and Community Infrastructure Levy (CIL) receipts – totalling £3.4m. In addition, the Council has been successful in securing additional funds from Central Government through the Local Growth Fund (LGF) which is aimed towards implementing transport measures linked to economic growth and carbon reduction with a focus on removing pinch points. LGF funding (£5.519m) has been awarded for A3095 (south) corridor improvements and further enhancements to the A322/A329 corridor.
5.3A required local contribution from Borough Capital (£200k) will support completion of the A322 Downshire Way scheme which has been substantially funded by the Government’s National Productivity Investment Fund in preceding financial years.
5.4As well as large scale schemes, the Council continues to implement local improvements that support the Local Transport Plan. These focus on improving access, mobility and travel choice, highway capacity and road space allocation, road safety, residential parking and traffic management. Additional match-funding has been committed by Silva Homes (£100k) to support further provision of residential parking schemes in priority areas.
5.5The overall Transport Capital Programme for 2020/21 totals £9.939m and is contained within Annex 1. This expenditure significantly exceeds the 2019/20 programme value of £5.4m.
Highway Maintenance Programme
5.6The Highway Maintenance Capital Programme seeks to ensure that the Council maintains the highway network in as good a condition as resources allow, giving due regard to public safety. It also supports objectives within the Council’s adopted LTP3. The Highway Maintenance programme continues to focus on the integrity of a wide range of highway assets including carriageways, highway structures, drainage and street lighting.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.