Resolved
RESOLVED that the overall Highways and Transport Capital Programme for 2021/22 is approved.
Executive approved this item on Tuesday 27 April 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the overall Highways and Transport Capital Programme for 2021/22 is approved.
2.1That the overall Highways and Transport Capital Programme for 2021/22 (Annex 1) is approved.
3.1The proposals in this report identify the current highway and transport priorities across the network. The schemes seek to facilitate transport in line with the Council’s Local Transport Plan 3 (LTP3) and ensure that the Council maintains the highway in as good a condition as resources allow, having due regard to the Council’s intervention policy based on network condition.
4.1Failure to approve the Highways and Transport Capital Programme would prevent the delivery of the Council’s obligations as a Highway Authority and be contrary to the position set out in the Council’s adopted Transport Policy (LPT3).
4.2Given the reduction in highway maintenance funding levels in previous years, it would not be appropriate to allocate resources to anything other than the priorities identified through methodical and objective needs assessments.
5 SUPPORTING INFORMATION
5.1The overall Highways and Transport Capital Programme for 2021/22 totals £7.003m, of which over 90% of funding is derived from external sources. A further breakdown of the programme and its objectives is set out below.
Transport Programme
5.2The Transport Capital Programme is formed to support the adopted LTP3 which sets out the key transport challenges and opportunities facing Bracknell Forest through the period 2011-2026. Schemes are developed taking account of wider policy goals alongside strategic and local transport needs. Issues such as deliverability and public impact/acceptability are also reflected within the scheme selection.
5.3Core funding for the 2021/22 programme is made up of an Integrated Transport Grant from Central Government (£726k) alongside developer contributions for transport mitigation measures via S106 agreements and Community Infrastructure Levy (CIL) receipts – totalling £3.689m. 5.4 In 2020/21, the Council was successful in securing additional funds from Central Government through the Local Growth Fund (LGF) which is aimed towards implementing transport measures linked to economic growth and carbon reduction with a focus on removing pinch points. The 2021/22 programme will include completion of the A3095 (South) Highway Improvement Scheme and commencement of improvements to the A322 Sports Centre Roundabout, both of which are part-funded in this way.
5.5As well as large scale schemes, the Council continues to implement local improvements that support the Local Transport Plan. These focus on improving access, mobility and travel choice, highway capacity and road space allocation, road safety, residential parking and traffic management. Additional match-funding has been committed by Silva Homes (£100k) to support further provision of residential parking schemes in priority areas.
5.6The overall Transport Capital Programme for 2021/22 totals £4.515m and is contained within Annex 1.
Highway Maintenance Programme
5.7The Highway Maintenance Capital Programme seeks to ensure that the Council maintains the highway network in as good a condition as resources allow, giving due regard to public safety. It also supports objectives within the Council’s adopted LTP3. The Highway Maintenance programme continues to focus on the integrity of a wide range of highway assets including carriageways, highway structures, drainage and street lighting.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Programme 2021/22: Highways and TransportReport | 272 KB | DownloadRead as text |
PDF |
Highways and Transport Capital Programme 2021-22: ANNEX 1Appendix | 23 KB | Download |
PDF |
Highways and Transport Capital Programme 2021-22: ANNEX 2Appendix | 135 KB | Download |
PDF |
View as HTML (151./2) 2 KBAppendix | 2 KB | Copy on its way |
PDF |
View as HTML (151./3) 2 KBAppendix | 2 KB | Copy on its way |
PDF |
View item 151. as HTML 22 KBReport | 22 KB | Copy on its way |
Follow Executive at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2024 | Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... | Noted | Open |
| 17 Sep 2024 | Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... | Agreed | Open |
| 17 Sep 2024 | Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. | Approved | Open |
| 17 Sep 2024 | Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... | Noted | Open |
| 17 Sep 2024 | Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.