Resolved
RESOLVED that, the minutes of the meeting of the committee held on the 16 September 2020 be approved as a correct record, and signed by the Chairman.
Governance & Audit Committee approved this item on Wednesday 27 January 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that, the minutes of the meeting of the committee held on the 16 September 2020 be approved as a correct record, and signed by the Chairman.
GOVERNANCE & AUDIT COMMITTEE 16 SEPTEMBER 2020 7.30 - 8.28 PM
Present: Councillors Allen (Chairman), Wade (Vice-Chairman), Gbadebo, [name removed], Heydon, Leake, Neil and Tullett Non-Voting Co-optees Present: David St John Jones
10. Declarations of Interest Cllr Tullett declared an affected interest as he was the managing director of a company that had received a discretionary grant.
11. Minutes of previous meeting
RESOLVED that, subject to the amendments above, the minutes of the meeting of the committee held on the 24 June 2020 be approved as a correct record and signed by the Chairman. The Director: Resources provided an update to the Committee on the Statements of Accounts, which had been expected to be brought to this meeting of the Committee for formal sign off. However, the Council’s external auditors, Ernst & Young had not yet completed the audit of the accounts, and they were still waiting for Deloitte’s to finish the audit of the pension funds.
It was hoped that this would be brought back to the Committee before the deadline of 30 November 2020, and a special meeting may be required around this date.
12. Urgent Items of Business
There were no urgent items of business.
13. Internal Audit and Risk Management Update The Committee received a report, which presented an update on progress on the annual Internal Audit Plan and the latest version of the Strategic Risk Register.
Sally Hendricks, Head of Audit and Risk Management, reported that, progress against the 2020/21 Internal Audit Plan was set out in Appendix 1 and as expected was behind original schedule due to delays in starting audits with departments due to the Covid-19 pandemic which had created a backlog which was now being addressed.
Delivery of the Council’s internal audit services have historically been outsourced and at a previous meeting it had been reported that there had been delivery issues with the contractor, therefore the decision was made to increase in-house capacity and an experienced senior auditor had been assisting us since late July.
Although it was too early in the financial year to comment on progress in improving the control environment especially given the delay in progressing the Audit Plan due to COVID 19, the Head of Audit and Risk Management was able to report that the planned action to set up a working group to identify other approaches that could help address continuing weaknesses in the area of expenses and purchase cards had been implemented and arising from this a number of workshops had already been held providing training on use and controls of purchase cards.
Arising for the Committees comments and questions, the following points were made:
The Head of Audit and Risk Management was hopeful that the team would be able to catch up with the audit plan as good progress was being made, however it would depend on the service areas being able to accommodate the audits, but Sally was keen for not too many audits to be deferred to quarter 4, as they had the previous year which had been delayed further due to Covid- 19. The audit plan was being monitored at every DMT meeting. Since the Covid-19 pandemic, the government business rate grants had been audited, which was key. Audits on the first tranche of grants around small businesses had been completed, and the arrangements for the discretionary grants were being currently looked at. The cash management audit was currently being relooked at, as there were limited cash transactions happening due to the pandemic. Since the pandemic, the priorities of audits hadn’t changed too much, but the grants being key thing too look at, however there hadn’t been too much movement in the plan. It was being addressed at DMT whether there were now additional areas that needed to be included within the plan as a result of the pandemic.
Sally Hendricks, Head of Audit and Risk Management provided an update on the Council’s risk register.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of previous meetingReports_pack | 154 KB | DownloadRead as text |
Follow Governance & Audit Committee at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Minutes of previous meetingRESOLVED that, the minutes of the meeting of the committee held on the 17 June 2026 be approved as a correct record, ... | Approved | Open |
| 16 Sep 2026 | External Audit Update 2025/26 Financial StatementsThat the update be noted. | Noted | Open |
| 17 Jun 2026 | Minutes of previous meetingRESOLVED that, subject to the amendments above, the minutes of the meeting of the committee held on the 18 March 2026... | Approved | Open |
| 17 Jun 2026 | Annual Governance Statement 2026RESOLVED that the draft Annual Governance Statement (“AGS”) and Action plan appended to this report be approved. | Approved | Open |
| 17 Jun 2026 | Annual Standards Report 2025-2026RESOLVED that the Standards outputs in 2025/26 as set out in Appendix B be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.